Contractor dumps flammable cladding on balconies

Grant Prior 1 year ago
Share

A specialist contractor has been fined £240,000 after flammable cladding was found lying on residents’ balconies at a Liverpool apartment block during removal work.

Exposed combustible material on exterior of the building
Exposed combustible material on exterior of the building

The combustible cladding was similar to that used on Grenfell Tower. Green Facades Limited had been contracted to remove the potentially dangerous aluminium composite panels and combustible insulation material from The Circle, an eight-storey building on Henry Street in Liverpool.

When an HSE inspector first visited the site in January 2022, the inspection revealed that, in preparation for the removal work, combustible material had been left exposed and there were inadequate means of escaping from the scaffold which was being erected.

The situation had worsened when the inspector returned a few days later. Further combustible material had been exposed with no protection from potential sources of ignition, and combustible cladding material was found lying on residents’ balconies.

As the building remained occupied during the works, the inspector alerted Merseyside Fire and Rescue Service who took their own enforcement action.

Green Facades Limited had been subject to earlier enforcement for similar breaches during cladding removal at a site in London. At that time the company was provided with advice on sustainable compliance with the regulations.

An HSE investigation found that Green Facades Limited had failed to take appropriate precautions to address the risk of fire and to ensure the safety of residents, workers, and others.  It had also failed to take account of published guidance on the safe removal of cladding following the previous issue in London.

The company of Woolwich Road, London pleaded guilty to safety breaches at  Liverpool Magistrates’ Court and was fined £240,000 and ordered to pay costs of £5,405.

After the hearing HSE inspector Jackie Western said: “The disturbing irony of this case is that work to protect residents from fire risk ended up making the situation more dangerous.

“This prosecution highlights the need for responsible management of the removal of cladding. The potentially tragic consequences of fire involving this type of material are well known following the Grenfell Tower fire.

“Despite earlier interventions and advice from HSE, and the availability of a wealth of guidance from HSE and others, this company continued to fail in its duty to address the risk of fire, putting people’s lives at risk.”

Latest news

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
4 days ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
4 days ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
1 week ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
1 week ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
1 week ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
1 week ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
1 week ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
1 week ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
1 week ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
1 week ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
1 week ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
1 week ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
1 week ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
1 week ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
1 week ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
1 week ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
1 week ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
1 week ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
1 week ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
1 week ago

Mace to close construction logistics arm

Specialist business being wound down
1 week ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
1 week ago

Profits double at Barhale

Civils specialist sees order book top £1bn
1 week ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
1 week ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
1 week ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
1 week ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
2 weeks ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
2 weeks ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
2 weeks ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
2 weeks ago

Contractor services