New HS2 boss blasts cost-plus contracts for £6bn of overspend

Aaron Morby 1 year ago
Share

HS2’s new boss has laid the blame for massive phase 1 budget overruns on the Government’s decision to let cost-plus contracts for main civil works.

Sir Jon Thompson warns cost plus contracts will hamper efforts to control overspend
Sir Jon Thompson warns cost plus contracts will hamper efforts to control overspend

Incoming executive chairman Sir Jon Thompson said that 89% of the cost increase from 2020 till now was down to these contracts alone.

He said the decision had tied his hands preventing him from pulling levers on contractors to rein back costs.

The latest projected cost for HS2 Main Works Civils Contracts is £21.8bn to £23.4bn, a cost hike of £6.1bn.

The latest estimate at 2019 prices still does not take into recent rampant cost inflation across the industry, and the Government has now demanded a new cost estimate at today’s prices.

Sir Jon, who has been in post as executive chairman since Mark Thurston stepped down in September, criticised the procurement decision as he was cross-examined by the Public Account Committee yesterday.

He said: “We have to be upfront with you now, the Government decision to let cost-plus contracts where there are very few incentives or penalties around them does not provide me with any real levers on contractors to do better in relation to schedule and costs because they receive a marginal reduction in their fee.

“If they spend 100% more than what was agreed, they only get 1% reduction in their fee.”

“I can attempt to see if we can reset that in some way, but we are where we are.

“The decisions was made for all the right reasons, I assume back in 2019, but these contracts do not provide me with very much leverage.”

Sir Jon also warned that extra cost pressures loomed with plans to connect HS2 to the West Coast Main Line through a major redesign at the Handsacre junction, already a choke point on the route.

This would need to be expanded requiring extra land and incurring extra cost, he said.

At the same time, the PAC was told that the Department of Transport and HS2 were presently at odds about the final cost for Phase One with the DfT setting a £45bn-£54bn price range and HS2 estimating £49bn – £57bn.

HS2 is planning to tighten management controls on budgets with the appointment in January of a Chief Railway Officer for the project. The new role will to be to integrate all elements of phase one, working alongside a new chief executive replacement for Mark Thurston.

“A lessons learnt from Crossrail is you need a single controlling mind for the programme overall, rather than working through individual lines,” said Thompson.

He revealed that the present working completion date for the project was now 2030.

Latest news

Winners revealed for £5.4bn electricity grid upgrade

SP Energy Networks unveils 19 winners - full list
6 hours ago

Malaysian property giant to buy 50% stake in JRL

IJM Land to buy into diversified £800m turnover south east contractor
12 hours ago

Fast-track skills hubs to train 5,000 extra apprentices

Plan for network of 32 skills hubs to rain construction apprentices in half the time
5 hours ago

Luxury house builder files administration notice

£31m turnover Octagon Developments Ltd lodges court notice
13 hours ago

Morgan Sindall takes on £22m stalled ISG Cardiff school job

Workplan is being drawn up ahead of restart on Penarth school
13 hours ago

Walker Modular wins bathroom pod deal on student tower

Sealant-free construction method helps supplier dominate student market
13 hours ago

Over £600m awarded for decarbonisation projects – full lists

Over 240 public building energy upgrade projects secure cash
1 day ago

Enabling works to start on £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
2 days ago

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
2 days ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
2 days ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
1 day ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
2 days ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
2 days ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
1 day ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
2 days ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
3 days ago

House builder Camstead goes into administration

Work stopped on three current sites
3 days ago

Death of piling legend Roger Bullivant

Industry innovator dies after long illness aged 85
2 days ago

ESS Modular went down owing suppliers £7m

Modular specialist owned by ISG owner Cathexis
3 days ago

Builders back farmers in inheritance tax protest

"A rethink is desperately needed" say National Federation of Builders
3 days ago

Willmott Dixon wins £36m leisure centre upgrade

Work to start on historic Westminster 1930s Grade II listed Seymour Centre
3 days ago

Graham wins £100m Cardiff Crossrail phase 1

Work on route to Cardiff Bay to start before end of next year
3 days ago

Laing O’Rourke appoints new European MD

Peter Lyons to take-up new role in February
4 days ago

Profits dip at Stepnell ahead of demerger

Turnover and secured workloads up ahead of restructure
4 days ago

HS2 green bridge deck takes shape

100m-wide wildlife bridge to carry hedgerows and country lane over HS2
3 days ago

1,000-home Wolverhampton city centre scheme in for planning

ECF and council advance City Centre West build to rent scheme
4 days ago

Sisk clinches £54m North London council HQ revamp

Haringey's iconic Grade II listed civic centre to be brought back into use
4 days ago

Ofgem approves £2.5bn Eastern Green Link 1

Work to start next Spring on cable project from Scotland to the north of England
4 days ago

Anglian Water hunts for £1bn delivery partner

Programme delivery partner wil integrate with client team over 15-year plan
5 days ago

Hadden collapse costs supply chain £6.7m

"Highly unlikely" subcontractors will receive anything for their unpaid invoices
5 days ago

Contractor services