Giant concrete pour at HS2 Curzon Viaduct: Video

Grant Prior 10 months ago
Share

HS2 has released new images showing construction progress as work ramps up on the 300 metre-long viaduct that will bring high-speed trains into Birmingham’s Curzon Street Station.

Over 2,000 cubic metres of concrete have been poured to create the first two 90 metre viaduct deck structures, with construction of two further deck sections well advanced.

The concrete was delivered and poured during night-time operations to minimise impacts on local roads. In total over 11,000 cubic metres of concrete will need to be poured to complete the whole viaduct.

A total of 26 piers, between five and six metres tall, have also been built to carry the viaduct, with 4 huge steel tripods currently under construction to support the viaduct over Digbeth Canal.

Over the next few months, once the concrete has been poured on each section, the shuttering and scaffolding will be removed, the viaduct sections will receive precast parapets and other finishing works will start.

Further sections of the viaduct will be built in the same way, and next summer, the span over the canal will be completed using jacks to slide 34 temporary steel girders, each measuring 38 metres, below the four steel tripods to support the formwork and further deck construction.

Curzon Viaduct No.3 is part of a series of five connected viaducts between Washwood Heath and Curzon Street Station in central Birmingham. On the approach to the station, the viaduct widens from a single deck to four separate decks, spanning 65 metres at the wideset point, to carry seven tracks to the platforms. Work on Curzon Street Station will begin next year.

David King, Senior Project Manager at HS2 Ltd said: “It’s fantastic to see this iconic viaduct taking shape in central Birmingham. This is one of our busiest construction sites, as we now reach peak construction on key HS2 structures across the Midlands, with over 9,750 people in the region working on the project.”

“The design of the viaduct is part of our vision to maximise social and economic development opportunities around Curzon Street Station. Widening to four separate decks near the station will maximise daylight underneath the viaduct, creating opportunities for a usable and flexible public space.”

The viaduct is being built by HS2’s Midlands contractor Balfour Beatty VINCI, with a team of more than 150 people including specially trained joiners, steel fixers and scaffolders from the local area, including five apprentices. The steel tripods have been manufactured by steelwork specialists Severfield, based in Bolton.

Lenka Vosvrdova, Curzon Street Site Agent at Balfour Beatty VINCI said: “We’re extremely proud of the significant progress our team have made on the Curzon Street Viaduct site. Since we revealed the first giant pier in January this year, we have successfully constructed 26 new concrete piers, with the first sections of the four-span viaduct also nearing completion.

“Over the coming months, works will ramp up on the series of viaducts in Birmingham, as we continue to build structures over Digbeth Canal, Lawley Middleway and the original Victorian railway line.”

The viaduct was designed by Balfour Beatty VINCI’s Design Joint Venture, made up of Mott MacDonald and SYSTRA (MMSDJV).

Nicholas Robertshaw, MMSDJV Design Lead added: “We’re delighted to see this superstructure starting to take shape and transform the Birmingham skyline.

“The Curzon Viaduct is positioned in a challenging built-up environment, adjacent to a Network Rail corridor. It’s only through the tireless work of the Design Joint Venture that we’ve been able to overcome these constraints. We feel we’ve produced an iconic design which everyone, including residents of Birmingham, can take pride in. “

Latest news

McAlpine healthcare MD joins BAM as Northern chief

Mark Gibson joins as Northern regional director
2 days ago

HS2 Align JV completes Britain’s longest rail bridge – video

Final deck segment sees HS2 viaduct break 137-year old record held by Tay Bridge
2 days ago

Green light for major London city fringe office retrofit

Overhaul of 30 Finsbury Square to start next Summer
2 days ago

John Lewis submits plan for £80m Reading rental flats scheme

Construction hoped to start on 215 flats scheme at the start of 2026
2 days ago

Balfour Beatty lands £27m Highlands flood defence scheme

Work to start imminently building river walls in Comrie
2 days ago

Buyers believe construction has “turned a corner”

Residential rebounds, commercial still strong but civils slows
3 days ago

Vistry unseats Barratt as Britain’s biggest house builder

Partnership homes specialist on track to build 18,000 homes this year
3 days ago

23 jobs axed as Lincolnshire contractor goes under

C G Godfrey provided civils and M&E services in Eastern England
3 days ago

Winvic first to use remote-control tower crane on site

Crane driver sits in ground floor command centre at Birmingham 33-storey tower
3 days ago

Starmer vows to ban Grenfell firms from public contracts

Prime Minister to write to named and shamed construction firms
3 days ago

Grenfell Inquiry calls for uber construction regulator

Shake-up must include licensing of main contractors taking on high rise projects
4 days ago

Robertson to restore historic Newcastle market

Work to revamp Grainger Market to start by the end of this month
3 days ago

Three bidders chase £1.4bn Midlands rail hub alliance

Balfour, Skanska, Bam and Laing O'Rouke in bidding for eight-year rail upgrade
4 days ago

Barratt profit nosedives as margin slumps to 4.2%

Fire safety provisions jump by an extra £126m to total £628m
4 days ago

First viaduct completed on HS2: Video site report

Eiffage, Kier, Ferrovial Construction and Bam Nuttall finish 163m long Highfurlong Brook Viaduct
4 days ago

Bouygues bags £28m Oxfordshire school job

St John’s Academy to be at heart of Wellington Gate Development
4 days ago

Willmott Dixon wins £49m Wigan college expansion

New campus for Wigan & Leigh College to be net zero in operation
4 days ago

Work to start on Liverpool office to flats job

Truman D&B wins resi conversion in Moorfields district
4 days ago

Government mothballs plan to scrap CE Mark

Building safety minister warns there is insufficient capacity in present testing regime
5 days ago

Government backs record number of clean energy projects

131 projects will produce electricity to power 11 million homes.
5 days ago

Tube station housing plan gets Government green light

Plans to transform Cockfosters Tube station were blocked by previous regime
5 days ago

Go-ahead for Bristol Temple Quay hotel and build to rent job

A trio of blocks will house a 230-room hotel, 170-room apart-hotel and 100 rental flats
5 days ago

Construction costs cut for Plymouth city centre revamp

Price of Armada Way scheme falls to £30m after exploratory work on site
5 days ago

Tilbury Douglas chief Paul Gandy to step down

Craig Tatton to take on CEO role from November
6 days ago

Local pressure unblocks £240m Oxford sewage works upgrade

Council warns Thames Water delay is halting building of thousands of new homes
6 days ago

Knights Brown bags last phase of £86m Portsmouth flood defence job

Contractor has already completed second and third phases of North Portsea Coastal Scheme
6 days ago

Bidding starts for £1bn housing decarbonising framework

National housing energy efficiency retrofit deal will come into force in 2015
6 days ago

World’s strongest land-based crane launched

Mammoet crane will help build major energy and infrastructure projects
6 days ago

Big Yellow gets go-ahead for largest London site

Storage giant to build 176,000 sq ft scheme next to Kensington Olympia
6 days ago

Worker dies after being buried by trench collapse

Court hears workers on new build housing site had no training on working within excavations
6 days ago

Contractor services