RWE to start construction on third Scottish wind farm

Grant Prior 1 year ago
Share

German energy giant RWE has confirmed plans to start construction work on a third Scottish onshore wind farm site this year as part of a £6.9bn investment programme across the UK.

The 63 megawatts Strathy Wood project in Caithness will become the latest to begin full construction, with pre-construction work now underway.

Main contractor Farrans is already working at two other sites at Enoch Hill in East Ayrshire and Camster II in Caithness.

Strathy Wood will have 11 turbines generating enough electricity to power 68,000 homes and will be completed by 2025.

Victoria Allen, Head of Onshore Renewables Development Scotland, said: “RWE is entering 2024 strong, with our ambition in Scotland ever growing, and we are delighted to have reached significant construction milestones for Enoch Hill, Camster II and now Strathy Wood.

“Onshore wind has an important role to play in helping deliver the UK and Scottish governments’ net zero emission targets in the coming years and remains the lowest cost form of renewable electricity generation.”

Latest news

McLaren winning spree as £1bn turnover in sight

Major deals imminent as contractor posts stable set of results
2 hours ago

Ring road builder wanted at £4bn Somerset gigafactory

Bidders wanted for £60m job. Latest video update from site
12 hours ago

Kier seals HMP Glasgow super prison job at £684m

Deal finally signed to replace Scotland's notorious Barlinnie prison
13 hours ago

Fraudsters jailed after £22m construction tax scam

Gang sentenced after bogus payroll firm failed to pay VAT and CIS money to revenue
19 hours ago

MPB clinches substructure for HS2 Curzon Street station

Contracts for station superstructure to be let in coming months
1 day ago

Flood defence spend rises to record £2.65bn over two-years

Key projects mapped as Government injects extra £250m to shore up defences
18 hours ago

Turnaround strategy continues to pay off for Careys

Profits continue to rise as £50m investment plan in full swing
1 day ago

All change on £800m Eastern Highways Alliance

Octavius and Winvic sweep up all three lots in new line-up
18 hours ago

Vinci bags first phase of £350m Stockport scheme

Contractor edges-out Willmott Dixon to start major mixed-used project
1 day ago

Crest Nicholson slumps to £144m loss

Incoming CEO review unearths further writedowns on fire remediation and closed divisions
2 days ago

Piling job cuts loom over safety regulator project delays

Bottleneck in high rise project approvals hits demolition and foundation firms
2 days ago

Developer Ghelamco swaps to self delivery for Battersea tower

John F Hunt no longer part of project team on 24-storey resi scheme
3 days ago

Pagabo starts renewal race for two mega frameworks

Contractors and developers asked for input on reshaping deals worth billions
2 days ago

Giant HS2 viaduct deck slide breaks records: Video

EKFB consortium oversees four-day installation
2 days ago

Ferrovial lands £230m National Grid tunnel

Work to start shortly on Grain to Tilbury electricity infrastructure upgrade
2 days ago

Tax-row tunnellers down tools on Balfour Hinkley job

Lodge allowance tax dispute hits tunnelling site
3 days ago

Go-ahead for Square Mile’s fifth tallest tower

Multiplex set to start 99 Bishopsgate job late next year
3 days ago

New £4.5bn funding model for stalled London rail schemes

Residential TIF funding offers key to unlock Bakerloo and DLR extensions
3 days ago

Speedy Hire latest to be hit by slow CP7 rail spending

Plant-hire firm flags issues with latest Network Rail spending round
3 days ago

FM Conway family chair steps away from business after Vinci deal

Joanne Conway steps away as Andrew Hansen becomes MD
3 days ago

Manchester Hotspur Press mill scheme rescued

37-storey student tower will now go-ahead
3 days ago

Watkin Jones to advance 260-room London aparthotel

Development deal for New Kent Road project
5 days ago

Plan for film studios switched to data centre cluster

Plans in for six data centre buildings in Buckinghamshire
6 days ago

Hunt for firm to deliver £75m Cambridge Civic Quarter

Work includes £41m Guildhall and £21m Corn Exchange revamps
6 days ago

Plans in for £200m Middlesbrough regen scheme

Wates is lined up to deliver landmark Gresham rental homes scheme
6 days ago

£600m Bristol shopping centre redevelopment approved

Galleries centre will be demolished for homes and offices quarter
6 days ago

Ant Yapi lands ultra prime London homes job

Prestige scheme replicates Regency mansions around nearby Regent’s Park
6 days ago

CITB survives another review

Report published after two more years talking about skills crisis
6 days ago

Strucktor wins record M&E package from Ardmore

Major subcontract on £240m Tribeca life science development
6 days ago

Over 800 high-rise resi jobs stalled by safety regulator

Building safety regulator project logjam hits Government growth plan
7 days ago

Contractor services