HS2 to Birmingham true cost likely to be £67bn

Aaron Morby 11 months ago
Share

The cost of building HS2 between London and Birmingham has ballooned to nearly £67bn at today’s prices.

Colne Valley viaduct
Colne Valley viaduct

The new estimate provided by HS2 chief Sir Jon Thompson is nearly double what the entire project was expected to cost in 2013.

Then the whole project, including the planned phase two routes to both Manchester and Leeds, had an original price tag of £37.5bn.

Giving evidence to the Transport Select Committee, Sir Jon confirmed that HS2 Ltd’s latest estimate for the London to Birmingham stretch is between £49bn and £56.6bn in 2019 prices.

This is at odds with the government’s present expectation, set out in its recent Network North plan, which said the truncated project would be delivered at £45bn.

He estimated after three years of industry-wide rampant cost inflation in steel and concrete in particular around £8bn-£10bn should be added to the estimate for an indication of the true cost at today’s prices.

Sir Jon also told the committee that he could not guarantee costs would not rise further while contractors were incentivised through cost-plus contracts to spend money.

He said that HS2 was currently trying to renegotiate terms with contractors and for the first time had put in place proper management control systems to keep tabs on individual contracts.

Sir Jon explained there were four chief reasons for the massive overrun.

“The first is that the cost estimate and budget set in the first place was too low, in my opinion.

“Second there has been some changes to scope. Thirdly there has definitely been some poor delivery and fourthly there has been cost inflation.”

He added that a ‘hostile project environment’ with Covid and local planning challenges had also contributed to problems but to a much lesser extent.

Covid cost up to £600m extra, slow planning also hit the project, with one local consent taking over two years to then be turned down.

“And then lastly Government itself said ‘we can’t really afford to fund the schedule; we will need you to go slower because we can’t afford it in cash flow terms’.”

“Obviously if you wait to do something in three year’s time, it is going to cost more than now,” he explained.

 

Latest news

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
7 hours ago

Enabling works to start £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
7 hours ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
7 hours ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
7 hours ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
8 hours ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
8 hours ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
7 hours ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
1 day ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
1 day ago

House builder Camstead goes into administration

Work stopped on three current sites
2 days ago

Death of piling legend Roger Bullivant

Industry innovator dies after long illness aged 85
1 day ago

ESS Modular went down owing suppliers £7m

Modular specialist owned by ISG owner Cathexis
1 day ago

Builders back farmers in inheritance tax protest

"A rethink is desperately needed" say National Federation of Builders
1 day ago

Willmott Dixon wins £36m leisure centre upgrade

Work to start on historic Westminster 1930s Grade II listed Seymour Centre
1 day ago

Graham wins £100m Cardiff Crossrail phase 1

Work on route to Cardiff Bay to start before end of next year
2 days ago

Laing O’Rourke appoints new European MD

Peter Lyons to take-up new role in February
3 days ago

Profits dip at Stepnell ahead of demerger

Turnover and secured workloads up ahead of restructure
3 days ago

HS2 green bridge deck takes shape

100m-wide wildlife bridge to carry hedgerows and country lane over HS2
2 days ago

1,000-home Wolverhampton city centre scheme in for planning

ECF and council advance City Centre West build to rent scheme
3 days ago

Sisk clinches £54m North London council HQ revamp

Haringey's iconic Grade II listed civic centre to be brought back into use
3 days ago

Ofgem approves £2.5bn Eastern Green Link 1

Work to start next Spring on cable project from Scotland to the north of England
3 days ago

Anglian Water hunts for £1bn delivery partner

Programme delivery partner wil integrate with client team over 15-year plan
3 days ago

Hadden collapse costs supply chain £6.7m

"Highly unlikely" subcontractors will receive anything for their unpaid invoices
3 days ago

Management buyout at M&E specialist

£25m turnover Kimpton in second MBO in its 60-year history
3 days ago

BAM finalises £71m deal to replace first major RAAC school

Work to start on new St Leonards Catholic School in Durham
3 days ago

Scaffolder hit by two tonne weight at nuclear plant

Court hands out £633,000 in fines after Dungeness B decommissioning incident
3 days ago

Go-ahead for 860,000 sq ft East London medical campus

Whitechapel Road scheme of six new and repurposed buildings
3 days ago

Site labour rates hit record high as cost inflation returns

Industry's biggest payroll firm says rates rose nearly 5% last month in London
6 days ago

Morris & Spottiswood acquires part of ISG fit-out division

ISG Cathedral acquisition saves 111 jobs and expands presence across England
7 days ago

New work drives Q3 construction output uplift

Third quarter activity up 0.8% despite slowdown in September
6 days ago

Contractor services