Work starts on epic year-long HS2 viaduct deck slide

Aaron Morby 1 year ago
Share

HS2 main works contractor EKFB has started a year-long bridge slide to push almost half a kilometre of deck into position high above the Misbourne Valley in Buckinghamshire.

Specialist engineers from Eiffage Metal carefully slide the Wendover Dean Viaduct deck into position
Specialist engineers from Eiffage Metal carefully slide the Wendover Dean Viaduct deck into position

The Wendover Dean Viaduct will be the first major railway bridge in the UK to be built with a ‘double composite’ approach.

The increased strength of the steel/concrete composite deck design allows it to slide over the viaduct piers in an epic push of 90 to 180m long sections.

Wendover Viaduct deck from above during the first deck slide looking south

This critical new stage of construction will see sections pushed out in sequence from the north abutment across teflon pads.

With each new section being attached behind the other, the weight of the deck will increase with each push, up from an initial 590 tonnes this week to 3,700 tonnes by the end of the year.

Deck beam at dusk as the first day of the Wendover Dean deck slide came to an end

James Collings, EKFB’s senior engineer, said: “The project team has reached a fundamental milestone in the build of this industry-leading viaduct.

“We’re progressing well with the first-of-three steel launches being conducted this year and already looking forward to seeing this viaduct come to life. Along with our supply chain partners, Eiffage Metal, we’re proud to be delivering this viaduct safely and to programme.”

Tomas Garcia, HS2 Ltd’s Head of Civil Structures said: Double composite structures maximise the combined strength of steel in tension and concrete in compression. This approach has been tried and tested around the world and it’s great to see it applied on this scale for the first time in the UK at Wendover Dean.”

Composite deck carbon savings


View of the underside of the Wendover Dean Viaduct showinhg the double composite structure

Instead of using solid pre-stressed concrete beams to form the spans between the viaduct piers, the ‘double composite’ structure uses two steel beams sandwiched between two layers of reinforced concrete to create a lightweight and super strong hollow span.

EKFB worked with their design partner, ASC (a joint venture between Arcadis, Setec and COWI) and architects Moxon on the ‘double composite’ approach which was inspired by structures on the French high speed TGV network.

The approach is set to cut the carbon footprint of the structure by 56% – saving almost 13,000 tonnes of embodied carbon – and helping HS2 achieve its goal of halving the amount of embedded carbon in construction.

Deck beam slid into position with deck slabs and balancing ponds behind

Latest news

Fraudsters jailed after £22m construction tax scam

Gang sentenced after bogus payroll firm failed to pay VAT and CIS money to revenue
1 hour ago

MPB clinches substructure for HS2 Curzon Street station

Contracts for station superstructure to be let in coming months
17 hours ago

Flood defence spend rises to record £2.65bn over two-years

Key projects mapped as Government injects extra £250m to shore up defences
29 mins ago

Turnaround strategy continues to pay off for Careys

Profits continue to rise as £50m investment plan in full swing
18 hours ago

All change on £800m Eastern Highways Alliance

Octavius and Winvic sweep up all three lots in new line-up
28 mins ago

Vinci bags first phase of £350m Stockport scheme

Contractor edges-out Willmott Dixon to start major mixed-used project
18 hours ago

Crest Nicholson slumps to £144m loss

Incoming CEO review unearths further writedowns on fire remediation and closed divisions
1 day ago

Piling job cuts loom over safety regulator project delays

Bottleneck in high rise project approvals hits demolition and foundation firms
2 days ago

Developer Ghelamco swaps to self delivery for Battersea tower

John F Hunt no longer part of project team on 24-storey resi scheme
2 days ago

Pagabo starts renewal race for two mega frameworks

Contractors and developers asked for input on reshaping deals worth billions
1 day ago

Giant HS2 viaduct deck slide breaks records: Video

EKFB consortium oversees four-day installation
1 day ago

Ferrovial lands £230m National Grid tunnel

Work to start shortly on Grain to Tilbury electricity infrastructure upgrade
2 days ago

Tax-row tunnellers down tools on Balfour Hinkley job

Lodge allowance tax dispute hits tunnelling site
2 days ago

Go-ahead for Square Mile’s fifth tallest tower

Multiplex set to start 99 Bishopsgate job late next year
2 days ago

New £4.5bn funding model for stalled London rail schemes

Residential TIF funding offers key to unlock Bakerloo and DLR extensions
2 days ago

Speedy Hire latest to be hit by slow CP7 rail spending

Plant-hire firm flags issues with latest Network Rail spending round
2 days ago

FM Conway family chair steps away from business after Vinci deal

Joanne Conway steps away as Andrew Hansen becomes MD
2 days ago

Manchester Hotspur Press mill scheme rescued

37-storey student tower will now go-ahead
2 days ago

Watkin Jones to advance 260-room London aparthotel

Development deal for New Kent Road project
4 days ago

Plan for film studios switched to data centre cluster

Plans in for six data centre buildings in Buckinghamshire
6 days ago

Hunt for firm to deliver £75m Cambridge Civic Quarter

Work includes £41m Guildhall and £21m Corn Exchange revamps
5 days ago

Plans in for £200m Middlesbrough regen scheme

Wates is lined up to deliver landmark Gresham rental homes scheme
5 days ago

£600m Bristol shopping centre redevelopment approved

Galleries centre will be demolished for homes and offices quarter
5 days ago

Ant Yapi lands ultra prime London homes job

Prestige scheme replicates Regency mansions around nearby Regent’s Park
5 days ago

CITB survives another review

Report published after two more years talking about skills crisis
6 days ago

Strucktor wins record M&E package from Ardmore

Major subcontract on £240m Tribeca life science development
5 days ago

Over 800 high-rise resi jobs stalled by safety regulator

Building safety regulator project logjam hits Government growth plan
6 days ago

McAlpine under fire after another panel comes loose from hotel

High winds cause more problems at recently completed Woking hotel
7 days ago

McGee starts demolition for £500m South Bank scheme

Former ITV studios will be replaced by two office towers
6 days ago

Four arrested after hospital construction site burglary

Damage and copper wiring stolen at Hinckley and District General Hospital new building
7 days ago

Contractor services