Work starts on epic year-long HS2 viaduct deck slide

Aaron Morby 1 year ago
Share

HS2 main works contractor EKFB has started a year-long bridge slide to push almost half a kilometre of deck into position high above the Misbourne Valley in Buckinghamshire.

Specialist engineers from Eiffage Metal carefully slide the Wendover Dean Viaduct deck into position
Specialist engineers from Eiffage Metal carefully slide the Wendover Dean Viaduct deck into position

The Wendover Dean Viaduct will be the first major railway bridge in the UK to be built with a ‘double composite’ approach.

The increased strength of the steel/concrete composite deck design allows it to slide over the viaduct piers in an epic push of 90 to 180m long sections.

Wendover Viaduct deck from above during the first deck slide looking south

This critical new stage of construction will see sections pushed out in sequence from the north abutment across teflon pads.

With each new section being attached behind the other, the weight of the deck will increase with each push, up from an initial 590 tonnes this week to 3,700 tonnes by the end of the year.

Deck beam at dusk as the first day of the Wendover Dean deck slide came to an end

James Collings, EKFB’s senior engineer, said: “The project team has reached a fundamental milestone in the build of this industry-leading viaduct.

“We’re progressing well with the first-of-three steel launches being conducted this year and already looking forward to seeing this viaduct come to life. Along with our supply chain partners, Eiffage Metal, we’re proud to be delivering this viaduct safely and to programme.”

Tomas Garcia, HS2 Ltd’s Head of Civil Structures said: Double composite structures maximise the combined strength of steel in tension and concrete in compression. This approach has been tried and tested around the world and it’s great to see it applied on this scale for the first time in the UK at Wendover Dean.”

Composite deck carbon savings


View of the underside of the Wendover Dean Viaduct showinhg the double composite structure

Instead of using solid pre-stressed concrete beams to form the spans between the viaduct piers, the ‘double composite’ structure uses two steel beams sandwiched between two layers of reinforced concrete to create a lightweight and super strong hollow span.

EKFB worked with their design partner, ASC (a joint venture between Arcadis, Setec and COWI) and architects Moxon on the ‘double composite’ approach which was inspired by structures on the French high speed TGV network.

The approach is set to cut the carbon footprint of the structure by 56% – saving almost 13,000 tonnes of embodied carbon – and helping HS2 achieve its goal of halving the amount of embedded carbon in construction.

Deck beam slid into position with deck slabs and balancing ponds behind

Latest news

Comment: Gateway is acting like a barricade

Contractors left banging their heads on an (unbuilt) brick wall
1 day ago

Final phase of £1.5bn Elephant and Castle revamp hits planning

Get Living submits revised plan for 500 homes and 450-bed student block
2 days ago

Ealing backs final phase of £1.3bn estate rebuild

Friary Park estate rebuild in Acton reaches end stage
1 day ago

Green light for scaled-down Nottingham student tower

Glasshouse Street scheme will deliver 247 student rooms
1 day ago

Aston Villa to revamp North Stand

Club to reuse existing structure rather than complete rebuild
2 days ago

Mace signs ex-ISG director to lead Euro health and tech push

Gary Sweeney to head up healthcare and life sciences consultancy arm
1 day ago

Sir Robert McAlpine claws way back into profit

Firm says return to profit and strong cash balance validates new strategy
2 days ago

Severfield to cut staff by 6% amid pricing pressure

Steelwork contractor warns of extended tighter pricing due to project delays
2 days ago

JRL completes sale of 50% stake to Malaysian giant IJM

Deal boosts balance sheet and kicks starts growth plan
3 days ago

Green light for £100m Liverpool Baltic station build

Enabling highway works to start in the autumn
3 days ago

First live tests for flying construction robots

Drones can lay construction materials at height on site
2 days ago

Three firms land £170m Gentoo Sunderland housing deal

PHS Solutions, Esh and RE:GEN to deliver 10-year home upgrade plan
3 days ago

Gateway gridlock hits build-to-rent delivery as starts nosedive

Build to rent starts plunge 18% in the capital
4 days ago

Call to shift Gateway 2 checks to end building bottleneck

"The current system isn't working but we all want to see safe buildings"
3 days ago

GBN launches £600m bid race for SMR engineer roles

Owner engineers to provide technical and assurance services
4 days ago

Wates hires ex-Homes England chief to head public sector push

Robert Stone to spearhead its public sector and national frameworks strategy
4 days ago

Acheson Construction collapse costs suppliers £8.5m

One frustrated creditor seized a telehandler after contractor went into administration
4 days ago

Dominus wins go-ahead for 173-bed Glasgow scheme

Old Wynd Street job expected to cost around £25m to build
4 days ago

Safety Regulator misses deadline to clear Gateway 2 backlog

Investors pulling out of funding high rise buildings
4 days ago

CITB still sitting on £95m cash pile

Staff numbers jump from 666 to 763 as training body wage bill soars
5 days ago

£500m road surfacing framework market call

NEPO goes out to consultation on north east regional highways deal
5 days ago

Two share £220m Scottish rail repairs and minor works deal

AmcoGiffen and CPMS win civils and building repair deals
5 days ago

Builder wanted for £60m London leisure and flats job

Tower Hamlets aims to replace St George’s Leisure Centre in Shadwell
5 days ago

Contractor confirmed for business park expansion

Roe Developments to start on next phase of Castle Donington scheme
5 days ago

Driver escapes injury as scaffold collapses onto van

Major three-lift scaffold fall blocks north London high street
1 week ago

Gilbert Ash to be sold to staff

£267m turnover contractor to transition to an Employee Ownership Trust
1 week ago

M Group seals biggest-ever deal with Telent takeover

Digital infrastructure specialist deal lifts turnover to £3bn
1 week ago

Aggregates firm Ashville went down owing more than £3m

Debts revealed in Companies House update
1 week ago

Cardo saves 100 jobs at Breyer roofing arm

Private equity-backed Welsh maintenance group continues to expand
1 week ago

Excavator knocked off lorry going under bridge

Traffic Commissioner inquiry after accident in south London
1 week ago

Contractor services