Government told to stop dithering over HS2 Euston tunnel start date

Aaron Morby 12 months ago
Share

Spending watchdog MPs have called on the Government to urgently take a decision on the start date for the last remaining phase one tunnel drive to Euston station.

In a highly critical report published this morning, the Public Accounts Committee warned that there are still huge uncertainties over key areas of the project that threatened to continue to see costs soar.

The MPs said that the decision to axe the second phase of HS2 meant the project now offers very poor value for money to the taxpayer, and the Department and HS2 Ltd could not set out what the final benefits of the project would be.

The report warns that the Department of Transport must take a decision soon on funding the tunnelling from Old Oak Common to Euston to avoid incurring much greater costs from stopping and restarting work. 

It also raised concerns that the Government has failed to set out a plausible proposal on how its expects to attract private sector investment to deliver Euston station and the final tunnel drive from Old Oak Common.

The Government has redirected £6.5bn of expenditure away from Euston, and the Department of Transport is now looking for private funding to cover the costs of the re-scoped Euston station and the over-site development.

It recommended the Government must develop plans for a range of private investment scenarios, including different levels of public finance, as part of its consideration of how to progress with the station at Euston.

Dame Meg Hillier MP, Chair of the Committee, said: “The decision to cancel HS2’s Northern leg was a watershed moment that raises urgent and unanswered questions, laid out in our report.

“HS2 is the biggest ticket item by value on the Government’s books for infrastructure projects.

“As such, it was crying out for a steady hand at the tiller from the start.

“But, here we are after over a decade of our warnings on HS2’s management and spiralling costs – locked into the costly completion of a curtailed rump of a project and many unanswered questions and risks still attached to delivery of even this curtailed project.”

The MPs are also concerned about the uncertainty of the cost impact on the final project bill of the complex challenge of connecting HS2 to the West Coast Mainline.

A spokesperson for HS2 Ltd said: “We’ve been clear about our cost challenges, which have been compounded by significant levels of inflation.

“HS2 Ltd is now under new leadership and implementing changes across the programme aimed at controlling costs and learning the lessons of the past.”

 

Latest news

MPB clinches substructure for HS2 Curzon Street station

Contracts for station superstructure to be let in coming months
11 hours ago

Vinci bags first phase of £350m Stockport scheme

Contractor edges-out Willmott Dixon to start major mixed-used project
12 hours ago

Turnaround strategy continues to pay off for Careys

Profits continue to rise as £50m investment plan in full swing
12 hours ago

Crest Nicholson slumps to £144m loss

Incoming CEO review unearths further writedowns on fire remediation and closed divisions
18 hours ago

Piling job cuts loom over safety regulator project delays

Bottleneck in high rise project approvals hits demolition and foundation firms
1 day ago

Developer Ghelamco swaps to self delivery for Battersea tower

John F Hunt no longer part of project team on 24-storey resi scheme
2 days ago

Pagabo starts renewal race for two mega frameworks

Contractors and developers asked for input on reshaping deals worth billions
19 hours ago

Giant HS2 viaduct deck slide breaks records: Video

EKFB consortium oversees four-day installation
18 hours ago

Ferrovial lands £230m National Grid tunnel

Work to start shortly on Grain to Tilbury electricity infrastructure upgrade
1 day ago

Tax-row tunnellers down tools on Balfour Hinkley job

Lodge allowance tax dispute hits tunnelling site
2 days ago

Go-ahead for Square Mile’s fifth tallest tower

Multiplex set to start 99 Bishopsgate job late next year
2 days ago

New £4.5bn funding model for stalled London rail schemes

Residential TIF funding offers key to unlock Bakerloo and DLR extensions
2 days ago

Speedy Hire latest to be hit by slow CP7 rail spending

Plant-hire firm flags issues with latest Network Rail spending round
2 days ago

FM Conway family chair steps away from business after Vinci deal

Joanne Conway steps away as Andrew Hansen becomes MD
2 days ago

Manchester Hotspur Press mill scheme rescued

37-storey student tower will now go-ahead
2 days ago

Watkin Jones to advance 260-room London aparthotel

Development deal for New Kent Road project
4 days ago

Plan for film studios switched to data centre cluster

Plans in for six data centre buildings in Buckinghamshire
5 days ago

Hunt for firm to deliver £75m Cambridge Civic Quarter

Work includes £41m Guildhall and £21m Corn Exchange revamps
5 days ago

Plans in for £200m Middlesbrough regen scheme

Wates is lined up to deliver landmark Gresham rental homes scheme
5 days ago

£600m Bristol shopping centre redevelopment approved

Galleries centre will be demolished for homes and offices quarter
5 days ago

Ant Yapi lands ultra prime London homes job

Prestige scheme replicates Regency mansions around nearby Regent’s Park
5 days ago

CITB survives another review

Report published after two more years talking about skills crisis
5 days ago

Strucktor wins record M&E package from Ardmore

Major subcontract on £240m Tribeca life science development
5 days ago

Over 800 high-rise resi jobs stalled by safety regulator

Building safety regulator project logjam hits Government growth plan
6 days ago

McAlpine under fire after another panel comes loose from hotel

High winds cause more problems at recently completed Woking hotel
6 days ago

McGee starts demolition for £500m South Bank scheme

Former ITV studios will be replaced by two office towers
6 days ago

Four arrested after hospital construction site burglary

Damage and copper wiring stolen at Hinckley and District General Hospital new building
6 days ago

Caddick kicks off Digbeth regen plan with £43m flats job

First phase 211 flats job starts wider £260m Upper Trinity Street scheme
6 days ago

Sisk starts work on £300m Children’s Cancer Centre

Great Ormond Street Hospital job will employ 500 on site and last three years
6 days ago

McAlpine clinches £1.25bn Port Talbot low carbon steelworks job

Deal to build one of the largest electric arc furnaces in the world
1 week ago

Contractor services