Belgian steelwork specialist Victor Buyck has jacked in the first 300-tonne steel viaduct section on HS2’s complex Delta Junction project.

Working for the Balfour Beatty Vinci JV, it took the firm 11.5 hours using push-pull jacking to install the 84m long section.

It is the first section of two 158m viaducts which will take high speed trains over the M42/M6 link roads in North Warwickshire.

Before the end of this year, a similar two-stage operation will move the identical ‘West Link Viaduct’ which runs parallel to the East Link Viaduct.

Tibo Suvée, project manager at Victor Buyck Steel Construction said: “This is the first time our push-pull jacking system has been used in the UK.

“The technique provides greater flexibility during the launching operation by allowing the bridge to be moved backwards or both ways if needed.

“This is really the first milestone of four, and over the next eight months we look forward to delivering the second launch of the East Link Viaduct and the same two-stage operation for the West Link Viaduct, which will complete these first viaducts on Delta Junction.”

Alex Staines, sub agent – Composite Structures at Balfour Beatty Vinci, said: “Delivering this milestone is a really proud moment for me and the team.

“By using an innovative launching technique, we were able to build the viaduct deck offline and move it into position over a weekend closure of the highway, greatly reducing the impact on road users.”

Delta Junction Viaducts:


A total of 153 piers will be built for the 13 viaducts in the triangle-shaped Delta Junction.

  • 4 composite viaducts (M42/M6 Link Road East and West; River Cole East and West). Composite viaducts with their decks built off weathered steel boxes or beams, with a concrete deck on top.
  • 6 precast segmental viaducts (River Tame East and West; Water Orton 1 and 2; Coleshill East and West). Segmental viaducts have standard spans of 45 metres with decks built off concrete precast segments which are prefabricated at HS2’s Kingsbury Precast Yard at Lea Marston.
  • 3 low viaducts (M42 Coleshill North and South; Watton House). Low viaducts have standard spans of 25 metres with their decks built off standard concrete precast beams, with a concrete deck on top.

Latest news

Morgan Sindall contracts league champion for second year

Kier ranks second in closely contested race between majors
4 hours ago

New Year layoffs as Scottish modular house builder collapses

East Ayrshire Connect Modular falls into administration
4 hours ago

Thames Water bidders day for £2.2bn reservoir scheme

Tenders to be invited in October for new Abingdon reservoir in Oxfordshire
4 hours ago

Buckingham Plant Hire quits heavy kit market

Firm to sell fleet and focus on lighter, sustainable plant
22 hours ago

Clients ‘ignoring building safety’ reforms

Clients still subjecting contractors to aggressive and sub-economic pricing
3 hours ago

Castleforge plans expansion after £100m data centre deal

Investor moves into booming data centre market
3 hours ago

Construction output growth drops to six-month low

Subcontractor rates rise at fastest rate for 18 months
1 day ago

Suir Engineering swoops for Scottish M&E contractor

Irish M&E firm launches UK expansion with Taylor & Fraser acquisition
1 day ago

Aggregates supply firm files administration notice

Ashville Aggregates and Concrete operates across London and South East
1 day ago

Plans in for 44-storey Manchester resi tower

Developer Glenbrook to appoint contractor this year
2 days ago

Briggs & Forrester names new engineering services MD

Will Newman replaces Ian Lawrence who steps down after eight years
1 day ago

Morgan Sindall bags Salford Uni acoustics building

Planning submitted for Acoustics Building at Crescent Innovation area
1 day ago

Lambeth to release six sites for £250m homes plan

Call for development partner to deliver 450 mixed tenure homes
1 day ago

Adrian Speller joins brother as joint MD of Midlands builder

Speller Metcalfe boosts senior leadership team
2 days ago

Winner unveiled for £2.9bn aqueduct revamp

Construction costs for Haweswater Aqueduct rise to £2.9bn from £1.75bn
5 days ago

Fortem and Equans face fight for £3bn housing upkeep deal

Birmingham City Council aims to sign new 10-year deals for four regions
2 days ago

Lendlease strikes deal to sell UK construction arm for £35m

US private equity firm Atlas to finalise purchase deal by summer
6 days ago

Hercules to offload suction excavator arm

Fleet of 30 trucks generates around £5m revenue a year
2 days ago

Tarmac trials new technique to cut concrete road noise

Quieter trips for drivers and longer-lasting roads
2 days ago

HS2 set for “fundamental reset” to lower construction costs

New chief executive promises action after latest project update
1 week ago

Solar panel installer fined £120,000 after roof fall

Court hears how employee broke his leg in fall
6 days ago

Network Rail chief Andrew Haines knighted

Thin pickings for construction in this year's New Year Honours
1 week ago

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
2 weeks ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
2 weeks ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
3 weeks ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
3 weeks ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
3 weeks ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
3 weeks ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
3 weeks ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
3 weeks ago

Contractor services