Innovative viaduct building method used for first time in UK

Aaron Morby 3 months ago
Share

HS2 contractors are using a specialist cantilever process for the first time in the UK to build viaduct spans at the scheme’s complex Delta junction in the West Midlands.

Temporary works give the box viaduct an appearance of a cable-stayed bridge during construction
Temporary works give the box viaduct an appearance of a cable-stayed bridge during construction

The viaduct intersection is being built by Balfour Beatty Vinci, using a method initially developed by French civil engineering specialist Campenon Bernard, now part of Vinci.

The River Tame West Viaducts presently under construction carry three rail tracks and form the northern tip of the planned Delta junction, which will require nine viaducts to be built in total.

Construction of the 20 piers to support the first of these viaducts started last year. The initial phase involved conventional methods placing precast viaduct segments onto two 42m truss beams, moving them into place with a skidding trolley, and securing them by post-tensioning techniques.

Since then, a giant cantilever structure has been built to extend the viaduct. Temporary works include erecting a 22m high mast that anchors post-tensioning cable stays to support concrete segments being installed. These are installed by a 14m high mobile swivel crane at the leading edge of the construction process.

The approach is similar to that employed for building cable-stayed bridges, but once the box viaduct is complete and permanent post-tensioning tendons have been stressed the mast and stays are removed.

The crane lifts and installs one concrete segment into place at a time, eventually completing each 45m span length. The same process is repeated between each pier until all of the spans are complete.

A team of 40 people are currently involved in the operation, and a total of 2,500 concrete segments will be moved into place using this specialist technique.

All the deck segments are due to be in place by August 2026.

The concrete segments are being manufactured at HS2’s bespoke outdoor factory near Lea Marston. The 200-strong team on this site has just celebrated producing the 1,000th segment out of a total 2,742 segments which are being made for the six segmental viaducts of the Delta Junction.

Nicolas Gallone from Balfour Beatty VINCI said: “We’re using a specialist construction method to build the River Tame West Viaducts – a technique which has never been used in the UK before. It’s a significant moment for Balfour Beatty VINCI, the HS2 project and the construction industry in this country.

“This post-tensioning technology, pioneered by VINCI, is used on other major construction projects around the world. Now, it’s helping us to deliver these complex viaducts and overcome engineering challenges along the way, including existing waterways and utilities.”

HS2’s Delta Junction is a triangular section of line, enabling trains to travel between London and Birmingham, Birmingham and Manchester, and direct between London and Manchester without stopping at Birmingham.

It is considered to be the most complex sections of the project as it is made up of embankments, cuttings and a total of 13 viaducts taking high speed tracks over motorways, local roads, existing rail lines, rivers and floodplains. The viaducts include six precast segmental viaducts, four composite viaducts and three low viaducts.

 

Latest news

Demolition giant John F Hunt Group sold to staff

Chairman John Hall to remain at helm
15 hours ago

University of Warwick advances £700m campus plan

Enabling works to get underway for main build works next year
20 hours ago

Go-ahead for £750m East London data centre

Urban 11-storey data centre to be built next to River Lea and A13 in Newham
1 day ago

Keltbray Infrastructure Services buys Linbrooke rail arm

First deal since infrastructure business was bought by private equity this summer
2 days ago

Elizabeth Line wins Stirling Prize for architecture

Infrastructure scheme wins premier design prize
20 hours ago

Winners named for Worcestershire and West Mids framework

Deal covers development work from design to construction
19 hours ago

Piling starts on HS2 Curzon Street Station

Mace Dragados Joint Venture and Keltbray working on Birmingham site
20 hours ago

M Group joins top seven as revenue jumps to £2.2bn

Infrastructure services specialist continues to hunt acquisitions
2 days ago

BlackRock to take control of Lanes Group

Takeover of leading water contractor to complete this month
2 days ago

Yorkshire and Lincolnshire builders’ merchant goes under

1928-founded Builders Merchant Company hit by winding up petition
2 days ago

Trio wins £170m West Country new build housing deal

Curo Enterprise, E.G. Carter and Speller Metcalfe Malvern
2 days ago

Roofer dies in fall from potato box on forklift

Court hears how victim fell 16ft from makeshift platform
2 days ago

Clancy bolsters senior management team

Skanska project director Jon Arnold joins as operations director of energy
2 days ago

High tech construction plant could save country £417bn

Costain report says kit which connects and drives itself will provide a massive economic boost
3 days ago

Concrete frame defects cost Bellway another £14m

Cost of repairing Greenwich scheme rises while £5.4m was spent on aborted Crest Nicholson chase
3 days ago

Green light for 52-storey Isle of Dogs resi tower

460 flats One East Point project will be built at 3-4 Harbour Exchange
3 days ago

Contractors urged to “hire now” as labour supply crunch looms

Vacancies rise and wages grow as fight for new workers intensifies
3 days ago

Kier confirmed for £20m Yasa Motors Bicester HQ

Developer Bicester Motion advances future mobility business park
3 days ago

Data centres and airport expansion to spur growth

Government hails £25bn data centre and £1.1bn Stansted Airport expansion plan
3 days ago

Hinkley Point second reactor unit build up to 30% faster

Engineering team lifts last giant steel ring onto reactor 2 yesterday
3 days ago

BAM reassures supply chain after winding-up petition

Firm's credit rating temporarily affected after dispute with supplier
4 days ago

Winvic secures Leeds build to rent scheme

Phase one of £500m Sweet Street South Bank regeneration starts
4 days ago

£60m turnover construction group sold to staff

Meldrum Construction Services Group becomes Employee Owned Trust
4 days ago

Starmer vows to “rip out” obstacles to investment

Prime Minister to make pledge at inaugural International Investment Summit
4 days ago

VolkerFitzpatrick starts prep-work for £210m M3 junction upgrade

Main works to begin in early 2025 on Winchester junction job
4 days ago

London super sewer turned on after eight years of construction

£4.5bn project starts protecting River Thames from pollution
4 days ago

Housing and office new work jump fuels output recovery

August new construction work rebounds 1.6% after early summer fall
7 days ago

£300m London City fringe office tower approved

Rocket's 27-storey One Fairchild Street job set for take-off
1 week ago

Consultants named for London Tube Bakerloo Line extension

Aecom and architect WW+P to work up designs for four new stations
7 days ago

15 giant bridge beams lifted into place at HS2 station

Balfour Beatty VINCI carries-out civils work for Solihull station: Video
1 week ago

Contractor services