Soaring costs at London incinerator job force M&E rethink

Aaron Morby 4 weeks ago
Share

Spanish contractor Acciona’s massive incinerator project in North London has been hit by spiraling costs and delays.

Civils work packages have largely completed at the Edmonton energy from waste incinerator project
Civils work packages have largely completed at the Edmonton energy from waste incinerator project

The Energy Recovery Facility forms part of the wider North London Heat and Power Project in Edmonton where costs have soared from £1.2bn to £1.5bn, due to construction material and wage inflation.

The EFR project is now at a critical stage with steelworks due to start shortly and main M&E works to follow.

But supply chain problems have forced Acciona to rethink its procurement strategy for the critical M&E stage of works.

Client body, the North London Waste Authority, representing seven councils, has revealed that the project originally due to be commissioned in 2025 will now be completed in 2027.

While civils works have proceeded well, officials from NWLA are concerned the M&E phase works could hit out-turn costs further.

The programme director for NWLA revealed Acciona has faced problem securing and mobilising subcontractors for the mechanical and electrical sections of the ERF build.

He added that the contractor was reviewing its approach to packaging tasks, to respond to feedback from potential subcontractors. The NWLA is now demanding a ‘realistic schedule and delivery plan.’

He said: “Acciona have identified issues in their delivery of the next stages of the design, procurement, and construction of the ERF facility, namely the mechanical and electrical sections of the build, in what is a challenging period for the construction industry.

“Officers are in regular discussions with Acciona to understand both how on-site momentum can be restored and how future delays can be minimised.

“Acciona are considering as part of this revising their approach to packaging work to generate increased interest from the potential supply chain.”

He added: “Our contract with Acciona provides that delays in the programme are their risk, and they may be liable to pay damages if the new facility is not delivered on time.

“However, it is not in the Authority’s interest to be working with a contractor facing significant financial challenges.”

The value of work completed so far has hit £790m with a Resource Recovery Facility to receive and transfer  waste and EcoPark House visitor centre completed on budget.

The remaining cost to complete is forecast at £730m.

The programme director said: “Until officers are satisfied of the robustness of Acciona’ s schedule and delivery plan, caution must be applied to the certainty of the costs and contingency, although the figures above represent current best estimates.”

 

Latest news

Hadden Construction goes into administration

66 jobs lost at £30m turnover Perthshire contractor
2 hours ago

Tight cost control returns Laing O’Rourke to profit

Group margin back to 1.9% as orders swell to record £10.8bn
9 hours ago

Kier to noise-proof 20,000 homes around Heathrow

Eight-year programme will involve new windows, doors, loft insulation and upgrade ceilings
8 hours ago

Caddick to build £42m Schneider Electric factory

New facility at Scarborough Business Park will open next year
1 day ago

Record turnover but inflation hits profits at HG Construction

Revenue tops £400m for first time but fixed-price contracts hit bottom line
9 hours ago

Speedy HS2 viaduct push cuts disruption for drivers

Balfour Beatty VINCI and Victor Buyck move 158 metre structure over roads in 11 hours: Video
8 hours ago

Morris & Spottiswood expands after M&E acquisition success

Fit-out and refurb specialist lifts revenue over a quarter to £128m
9 hours ago

Barratt, Lloyds and Homes England form JV for large housing schemes

Master developer JV to advance schemes of up to 10,000 homes
1 day ago

Eric Wright Construction books best profit for 12 years

Construction drives growth in more challenging year for group profitability
1 day ago

National Grid fined £3.2m after pylon accident

Worker suffers 40% burns from 33,000 volt shock
1 day ago

Civils contractor Glenevin goes into administration

All staff made redundant at £38.2m turnover broadband infrastructure specialist
1 day ago

Fusion go-ahead for 700-bed Cardiff student scheme

Building works to get underway at the start of 2025
2 days ago

Go-ahead for Salford 568 flat co-living scheme

Contractor talks underway for 42-storey residential tower
2 days ago

McAlpine healthcare MD joins BAM as Northern chief

Mark Gibson joins as Northern regional director
5 days ago

HS2 Align JV completes Britain’s longest rail bridge – video

Final deck segment sees HS2 viaduct break 137-year old record held by Tay Bridge
5 days ago

Green light for major London city fringe office retrofit

Overhaul of 30 Finsbury Square to start next Summer
4 days ago

John Lewis submits plan for £80m Reading rental flats scheme

Construction hoped to start on 215 flats scheme at the start of 2026
4 days ago

Balfour Beatty lands £27m Highlands flood defence scheme

Work to start imminently building river walls in Comrie
4 days ago

Buyers believe construction has “turned a corner”

Residential rebounds, commercial still strong but civils slows
5 days ago

Vistry unseats Barratt as Britain’s biggest house builder

Partnership homes specialist on track to build 18,000 homes this year
5 days ago

23 jobs axed as Lincolnshire contractor goes under

C G Godfrey provided civils and M&E services in Eastern England
5 days ago

Winvic first to use remote-control tower crane on site

Crane driver sits in ground floor command centre at Birmingham 33-storey tower
6 days ago

Starmer vows to ban Grenfell firms from public contracts

Prime Minister to write to named and shamed construction firms
6 days ago

Grenfell Inquiry calls for uber construction regulator

Shake-up must include licensing of main contractors taking on high rise projects
6 days ago

Robertson to restore historic Newcastle market

Work to revamp Grainger Market to start by the end of this month
5 days ago

Three bidders chase £1.4bn Midlands rail hub alliance

Balfour, Skanska, Bam and Laing O'Rouke in bidding for eight-year rail upgrade
6 days ago

Barratt profit nosedives as margin slumps to 4.2%

Fire safety provisions jump by an extra £126m to total £628m
6 days ago

First viaduct completed on HS2: Video site report

Eiffage, Kier, Ferrovial Construction and Bam Nuttall finish 163m long Highfurlong Brook Viaduct
6 days ago

Bouygues bags £28m Oxfordshire school job

St John’s Academy to be at heart of Wellington Gate Development
6 days ago

Willmott Dixon wins £49m Wigan college expansion

New campus for Wigan & Leigh College to be net zero in operation
6 days ago

Contractor services