Soaring costs at London incinerator job force M&E rethink

Aaron Morby 8 months ago
Share

Spanish contractor Acciona’s massive incinerator project in North London has been hit by spiraling costs and delays.

Civils work packages have largely completed at the Edmonton energy from waste incinerator project
Civils work packages have largely completed at the Edmonton energy from waste incinerator project

The Energy Recovery Facility forms part of the wider North London Heat and Power Project in Edmonton where costs have soared from £1.2bn to £1.5bn, due to construction material and wage inflation.

The EFR project is now at a critical stage with steelworks due to start shortly and main M&E works to follow.

But supply chain problems have forced Acciona to rethink its procurement strategy for the critical M&E stage of works.

Client body, the North London Waste Authority, representing seven councils, has revealed that the project originally due to be commissioned in 2025 will now be completed in 2027.

While civils works have proceeded well, officials from NWLA are concerned the M&E phase works could hit out-turn costs further.

The programme director for NWLA revealed Acciona has faced problem securing and mobilising subcontractors for the mechanical and electrical sections of the ERF build.

He added that the contractor was reviewing its approach to packaging tasks, to respond to feedback from potential subcontractors. The NWLA is now demanding a ‘realistic schedule and delivery plan.’

He said: “Acciona have identified issues in their delivery of the next stages of the design, procurement, and construction of the ERF facility, namely the mechanical and electrical sections of the build, in what is a challenging period for the construction industry.

“Officers are in regular discussions with Acciona to understand both how on-site momentum can be restored and how future delays can be minimised.

“Acciona are considering as part of this revising their approach to packaging work to generate increased interest from the potential supply chain.”

He added: “Our contract with Acciona provides that delays in the programme are their risk, and they may be liable to pay damages if the new facility is not delivered on time.

“However, it is not in the Authority’s interest to be working with a contractor facing significant financial challenges.”

The value of work completed so far has hit £790m with a Resource Recovery Facility to receive and transfer  waste and EcoPark House visitor centre completed on budget.

The remaining cost to complete is forecast at £730m.

The programme director said: “Until officers are satisfied of the robustness of Acciona’ s schedule and delivery plan, caution must be applied to the certainty of the costs and contingency, although the figures above represent current best estimates.”

 

Latest news

Mace wins £600m Euston Tower overhaul

1970s tower's foundations and core to be retained as floor plates extended
6 hours ago

Funding hurdle remains as Lower Thames Crossing gains consent

Government claims £9bn project may start in 2026 as private finance options explored
10 hours ago

Morgan Sindall upgrades forecast for next 12 months

Overbury fit-out arm gets off to a flying start in 2025
15 hours ago

Restructure underway at Henry Boot Construction

New management team restructures business after drop in turnover
15 hours ago

Government pledges £2bn stop-gap funding for 18,000 homes

Funding avoids cliff-edge in social housing delivery before new grant programme agreed
15 hours ago

Just two major new roads schemes to start this year

National Highways sets out one-year interim spending plan after RIS3 delay
16 hours ago

Plans go in for £400m GRAHAM Manchester site

Demolition and enabling works underway with main construction set to start next year
15 hours ago

Building safety levy rate set at up to £10,000 a home in London

Levy introduction pushed back a year to Autumn 2026 - list of new rates
1 day ago

BAM wins £100m revamp of Broadgate Tower in London

Front of tower 3-storey extension to use cross laminate time and re-used steel
2 days ago

£600m funding to train 60,000 construction workers

Government pledges massive cash injection to produce "site-ready" workers
3 days ago

Construction to start in May on £1bn port expansion

Work at London Gateway site will last four years
4 days ago

Utilities specialist Ipsum buys second power contractor

Acquisition of Wootton & Wootton strengthens service in Midlands and Wales
2 days ago

Councils will lose cash if they fail to fix potholes

Local authorities will have to publish road repair stats
2 days ago

Green light for London Euston Tower rebuild

British Land says nearly a third of original tower will be retained
5 days ago

Contractors struggling to keep-up with demand for data centres

More than half of clients fear supply chain will struggle
5 days ago

Robert De Niro’s Nobu backs Manchester super tower

76-storey skyscraper will be tallest outside of London
5 days ago

PAC warns post-Grenfell policies threaten new homes goal

Watchdog MPs warn new build rates are being hit by diversion of funds to safety remediation
5 days ago

400 schools and hospitals to get rooftop solar panels

£180m investment is the first major project for Great British Energy
5 days ago

Legendre UK to convert Diageo HQ into hotel

Work to start this year transforming former home of drinks giant
5 days ago

Glencar wins phase 2 of Harwell tech scheme

Tech Foundry West will create 70,000 sq ft of lab and manufacturing space
5 days ago

Beard breaks company record with latest results

Family-owned firm posts best results for 133 years
5 days ago

United Living buys street lighting contractor

North West's Jones acquisition also strengthens power distribution offer
6 days ago

Deal to start £1.1bn British Library extension

Japanese developer takes control with aim to start construction next year
6 days ago

Fraud warning over bogus site supplies orders

Site temporary protection specialist sounds alarm after foiling scammers
6 days ago

Plan for world’s tallest energy-positive tower in Birmingham

£60m solar clad 29-storey tower will produce more energy than it consumes
6 days ago

Costain to lead on nuclear fuel site upgrade

Programme delivery partner role for upgrade to infrastructure at Capenhurst site
6 days ago

Willmott Dixon wins £32m Doncaster digital tech hub

Construction to start next month on Gateway One scheme
6 days ago

Pickstock to build Stratford resi tower

Construction set to start next year by modular builder owner
6 days ago

ISG accountants face investigation over audit

Watchdog launches probe into final accounts for collapsed contractor
7 days ago

Developer given suspended jail sentence for fire safety breaches

Director wrongly allowed residents to move into block before getting fire safety sign-off
7 days ago

Contractor services