Soaring costs at London incinerator job force M&E rethink

Aaron Morby 6 months ago
Share

Spanish contractor Acciona’s massive incinerator project in North London has been hit by spiraling costs and delays.

Civils work packages have largely completed at the Edmonton energy from waste incinerator project
Civils work packages have largely completed at the Edmonton energy from waste incinerator project

The Energy Recovery Facility forms part of the wider North London Heat and Power Project in Edmonton where costs have soared from £1.2bn to £1.5bn, due to construction material and wage inflation.

The EFR project is now at a critical stage with steelworks due to start shortly and main M&E works to follow.

But supply chain problems have forced Acciona to rethink its procurement strategy for the critical M&E stage of works.

Client body, the North London Waste Authority, representing seven councils, has revealed that the project originally due to be commissioned in 2025 will now be completed in 2027.

While civils works have proceeded well, officials from NWLA are concerned the M&E phase works could hit out-turn costs further.

The programme director for NWLA revealed Acciona has faced problem securing and mobilising subcontractors for the mechanical and electrical sections of the ERF build.

He added that the contractor was reviewing its approach to packaging tasks, to respond to feedback from potential subcontractors. The NWLA is now demanding a ‘realistic schedule and delivery plan.’

He said: “Acciona have identified issues in their delivery of the next stages of the design, procurement, and construction of the ERF facility, namely the mechanical and electrical sections of the build, in what is a challenging period for the construction industry.

“Officers are in regular discussions with Acciona to understand both how on-site momentum can be restored and how future delays can be minimised.

“Acciona are considering as part of this revising their approach to packaging work to generate increased interest from the potential supply chain.”

He added: “Our contract with Acciona provides that delays in the programme are their risk, and they may be liable to pay damages if the new facility is not delivered on time.

“However, it is not in the Authority’s interest to be working with a contractor facing significant financial challenges.”

The value of work completed so far has hit £790m with a Resource Recovery Facility to receive and transfer  waste and EcoPark House visitor centre completed on budget.

The remaining cost to complete is forecast at £730m.

The programme director said: “Until officers are satisfied of the robustness of Acciona’ s schedule and delivery plan, caution must be applied to the certainty of the costs and contingency, although the figures above represent current best estimates.”

 

Latest news

Network Rail fined £3.75m after double track worker death

Michael Lewis and Gareth Delbridge were killed while working on rail line in Wales
13 hours ago

Local contractor Castle lands £60m South Shields campus

Work to start this summer on new home for South Tyneside College and South Shields Marine School
19 hours ago

GRAHAM wins £100m deal after safety regulator approval

Dyecoats scheme in Leeds becomes one of first to receive Building Safety Act Gateway 2 green light
2 days ago

London Super Sewer now fully connected

10-year construction programme draws to a close
1 day ago

McLaren signs off £125m London Bank over-station job

Developer Helical secures funding deal for 8-storey office job
1 day ago

Work on Labour’s new towns to start by 2029

More than 100 sites put forward for a dozen new town locations
1 day ago

Unite hails 12 years without a site accident at Battersea

More than 4,000 union members have worked on the redevelopment without a single serious accident
1 day ago

Housing orders surge offers hope after 5.2% new work fall last year

Housing orders surged 24% in final quarter of 2024 as developers release schemes
2 days ago

McLaren Property gets new Construction Director

Jon Mangham joins from Equans
1 day ago

BAM Construction suffers £40m loss after Co-op Live setback

Civils business profit surges 24% to £80m
2 days ago

Over 150 jobs axed as J S Wright goes under

Insolvency specialist FRP Advisory goes in at Birmingham M&E specialist
2 days ago

Extra cash found to speed-up safety regulator

Government to spend extra £2m to clear backlog of high rise approvals
2 days ago

Galliford Try lands £63m RAF accommodation deal

Work to start within months at RAF Digby in Lincolnshire
2 days ago

Balfour Beatty wins Trent arched bridge job

Briton Fabricators will build the £13m bridge from prefabricated sections
2 days ago

Goldbeck to build new £50m Cardiff County Hall

German-owned contractor vowing to be a "disrupter in the UK market"
2 days ago

Laing O’Rourke chairman to step down

Ray O'Rourke to take over chair from Sir John Parker
3 days ago

Farrans lands Leeds Bradford Airport phase 2 upgrade

Contractor takes follow-on refurb job after terminal extension
3 days ago

ISG built Bristol housing block to be torn down

Contractor's collapse sinks Bristol flats remediation claim
3 days ago

RSK revenue nears £2bn as losses soar to £132m

Refinancing last summer puts group on course for more growth this year
3 days ago

Bridge design wind error adds £20m to construction costs

Completion of £148m Grantham Southern Relief Road delayed by a year
3 days ago

Rayner pledges extra £350m for social house building

More than 3,000 homes could be built with cash injection
3 days ago

City’s biggest retrofit tower scheme approved

Triple-fronted 70 Gracechurch Street building will rise to 33 storeys
4 days ago

Defibrillator saves worker’s life on Wates site

Machine operator saved after "dying" for 16 minutes on prison job
4 days ago

Funding deal for £125m Camden Roundhouse scheme

Developer Regal set to start 264-bed student scheme
4 days ago

Balfour leadership rejig to focus on three key growth sectors

Divisional CEO trio take lead roles for energy, defence and transport expansion
5 days ago

ABP bidders day for £150m Humber ports pipeline

Nine projects in the pipeline to support automotive and energy transition schemes
4 days ago

Hinkley Point C to create 3,000 jobs as work ramps up

Fitout surge to swell workforce to 15,000 in next 18 months
4 days ago

Hercules sells suction excavator division for £2.4m

Loss making arm sold by labour hire specialist
4 days ago

Foundations complete at HS2 Old Oak Common station

Station base completed using 76,000 cubic metres of concrete and 17,000 tonnes of reinforced steel
4 days ago

Bids invited for £175m consultancy framework

Fusion21 inviting consultants to join latest four-year deal
4 days ago

Contractor services