Local pressure unblocks £240m Oxford sewage works upgrade

Aaron Morby 4 months ago
Share

Thames Water is finally advancing long-overdue plans for a major £240m upgrade of Oxford sewage treatment works after the local council blamed the water company for holding up thousands of new homes.

Aerial picture of Oxford sewage treatment works where big upgrade is due to progress
Aerial picture of Oxford sewage treatment works where big upgrade is due to progress

The water company has revealed it plans to invite tenders for the long-awaited capacity upgrade next month. Ahead of this, it will hold an online bidders briefing on 10 September to set out its plans to improve the quality of effluent released at the works and increase the site’s capacity.

Works will include trebling storm tank capacity, increasing sewage treatment flows by 80% and raising power supplies.

The decision to begin contractor selection comes as Oxford City Council launched a stinging attack against the embattled water company for holding up development across the county.

Councillor Susan Brown, leader of Oxford City Council, said: “We have long been raising the major problems created by the historic lack of investment by Thames Water in the Oxford Sewage Treatment Works, and its subsequent lack of capacity.

“This lack of investment has now led to the Environment Agency objecting to both the City Council’s proposed Local Plan 2040, and to housing and commercial planning applications coming forward in and around the city.

“This is a very significant environmental and economic issue for both Oxford and Oxfordshire.

She added: “Protecting and improving the water quality in our rivers and streams is fundamental, as is having adequate water supply and sewage capacity.

“We need to have the right infrastructure in place to do this. The fact that we do not, and that this is now also preventing or delaying the delivery of much-needed new homes and job opportunities, is a source of huge frustration and anger.

“We have been raising these issues locally for many years but have seen no action. While I am clear this is a failure of the previous government’s making, I have been greatly encouraged by the engagement shown by the current government on this issue.

“We are now engaged in active and constructive talks with Thames Water’s new chief executive, the EA, and the Water Services Regulation Authority.

“We have also entered a three-way agreement with Thames Water and the EA to work together to help address the planning issue as part of our draft Local Plan.

“It is clear from these discussions that there are shared objectives from all partners to support the sustainable development and growth of Oxford and the surrounding area; to focus on ensuring the necessary infrastructure is in place to protect and enhance the local environment; and to give assurance to the development community that the works will happen in a timely fashion to ensure we continue to deliver much-needed new homes and jobs.

“We also understand that Thames Water is working at pace with the relevant regulators to develop and put in place solutions that seek to address the situation.”

Email Thames Water for place at online teams supplier briefing.

Latest news

Morgan Sindall contracts league champion for second year

Kier ranks second in closely contested race between majors
5 hours ago

New Year layoffs as Scottish modular house builder collapses

East Ayrshire Connect Modular falls into administration
5 hours ago

Thames Water bidders day for £2.2bn reservoir scheme

Tenders to be invited in October for new Abingdon reservoir in Oxfordshire
5 hours ago

Buckingham Plant Hire quits heavy kit market

Firm to sell fleet and focus on lighter, sustainable plant
23 hours ago

Clients ‘ignoring building safety’ reforms

Clients still subjecting contractors to aggressive and sub-economic pricing
4 hours ago

Castleforge plans expansion after £100m data centre deal

Investor moves into booming data centre market
4 hours ago

Construction output growth drops to six-month low

Subcontractor rates rise at fastest rate for 18 months
1 day ago

Suir Engineering swoops for Scottish M&E contractor

Irish M&E firm launches UK expansion with Taylor & Fraser acquisition
1 day ago

Aggregates supply firm files administration notice

Ashville Aggregates and Concrete operates across London and South East
1 day ago

Plans in for 44-storey Manchester resi tower

Developer Glenbrook to appoint contractor this year
2 days ago

Briggs & Forrester names new engineering services MD

Will Newman replaces Ian Lawrence who steps down after eight years
1 day ago

Morgan Sindall bags Salford Uni acoustics building

Planning submitted for Acoustics Building at Crescent Innovation area
2 days ago

Lambeth to release six sites for £250m homes plan

Call for development partner to deliver 450 mixed tenure homes
1 day ago

Adrian Speller joins brother as joint MD of Midlands builder

Speller Metcalfe boosts senior leadership team
2 days ago

Winner unveiled for £2.9bn aqueduct revamp

Construction costs for Haweswater Aqueduct rise to £2.9bn from £1.75bn
5 days ago

Fortem and Equans face fight for £3bn housing upkeep deal

Birmingham City Council aims to sign new 10-year deals for four regions
2 days ago

Lendlease strikes deal to sell UK construction arm for £35m

US private equity firm Atlas to finalise purchase deal by summer
6 days ago

Hercules to offload suction excavator arm

Fleet of 30 trucks generates around £5m revenue a year
2 days ago

Tarmac trials new technique to cut concrete road noise

Quieter trips for drivers and longer-lasting roads
2 days ago

HS2 set for “fundamental reset” to lower construction costs

New chief executive promises action after latest project update
1 week ago

Solar panel installer fined £120,000 after roof fall

Court hears how employee broke his leg in fall
6 days ago

Network Rail chief Andrew Haines knighted

Thin pickings for construction in this year's New Year Honours
1 week ago

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
2 weeks ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
2 weeks ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
3 weeks ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
3 weeks ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
3 weeks ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
3 weeks ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
3 weeks ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
3 weeks ago

Contractor services