Speedy HS2 viaduct push cuts disruption for drivers

Grant Prior 5 months ago
Share

HS2 engineers completed the final operation to move two railway viaducts into place over the M42/M6 link roads in North Warwickshire more than six hours ahead of schedule this weekend.

The ‘push’ to move the 158-metre-long West Link Viaduct into its final position over both westbound and eastbound motorway link roads took a total of 11 hours.

Main works contractor Balfour Beatty VINCI (BBV) completed the work quicker than planned allowing the motorway link roads to be reopened 6.5 hours ahead of schedule.

The viaducts are part of a group of 13 which make up HS2’s triangular Delta Junction. This section of the railway enables high speed trains to travel between London, Interchange Station in Solihull and Birmingham Curzon Street Station.

In June, the first 84 metre section of the composite viaduct was moved to its halfway position. Since then, three further steel girders were welded to the back of the first section and 38 precast concrete slabs were installed to complete the 158-metre-long structure, which has now been moved over both link roads.

The parallel ‘East Link Viaduct’ was moved into place using an identical two-stage process during two weekend operations in February and April this year. This viaduct is currently being prepared to be brought into use as an internal haul road by the end of December, to move material from Bromford Tunnel to the Delta Junction, taking thousands of lorries off the local road network.

The four operations were delivered by a team of 25 people from specialist steelwork company Victor Buyck Steel Construction (VBSC), working on behalf of BBV, using a push-pull jacking system which gives greater flexibility during the launch operation.

JoseLuis Preciados, Senior Project Manager at Balfour Beatty VINCI said: “This final viaduct push is a significant milestone in our construction of HS2’s Delta Junction. I’m incredibly proud of the BBV team, who’ve worked tirelessly throughout this year to ensure each of these complex operations were planned and delivered with precision.

“Each viaduct deck was built offline and moved into position over a weekend closure of the highway, drastically reducing the impacts on road users. We’ve worked in collaboration with our partners National Highways throughout the entire process, to make sure that this activity was delivered safely and efficiently.”

Tibo Suvée, Project Manager at Victor Buyck Steel Construction added: “This has been a complex eight-month operation, and the first time our push-pull jacking system has been used in the UK.

“The technique provides greater flexibility during the launching operation by allowing the bridge to be moved backwards or both ways if needed.”

Latest news

Network Rail fined £3.75m after double track worker death

Michael Lewis and Gareth Delbridge were killed while working on rail line in Wales
1 day ago

Local contractor Castle lands £60m South Shields campus

Work to start this summer on new home for South Tyneside College and South Shields Marine School
1 day ago

GRAHAM wins £100m deal after safety regulator approval

Dyecoats scheme in Leeds becomes one of first to receive Building Safety Act Gateway 2 green light
2 days ago

London Super Sewer now fully connected

10-year construction programme draws to a close
2 days ago

McLaren signs off £125m London Bank over-station job

Developer Helical secures funding deal for 8-storey office job
2 days ago

Work on Labour’s new towns to start by 2029

More than 100 sites put forward for a dozen new town locations
2 days ago

Unite hails 12 years without a site accident at Battersea

More than 4,000 union members have worked on the redevelopment without a single serious accident
2 days ago

Housing orders surge offers hope after 5.2% new work fall last year

Housing orders surged 24% in final quarter of 2024 as developers release schemes
2 days ago

McLaren Property gets new Construction Director

Jon Mangham joins from Equans
2 days ago

BAM Construction suffers £40m loss after Co-op Live setback

Civils business profit surges 24% to £80m
3 days ago

Over 150 jobs axed as J S Wright goes under

Insolvency specialist FRP Advisory goes in at Birmingham M&E specialist
3 days ago

Extra cash found to speed-up safety regulator

Government to spend extra £2m to clear backlog of high rise approvals
3 days ago

Galliford Try lands £63m RAF accommodation deal

Work to start within months at RAF Digby in Lincolnshire
3 days ago

Balfour Beatty wins Trent arched bridge job

Briton Fabricators will build the £13m bridge from prefabricated sections
3 days ago

Goldbeck to build new £50m Cardiff County Hall

German-owned contractor vowing to be a "disrupter in the UK market"
3 days ago

Laing O’Rourke chairman to step down

Ray O'Rourke to take over chair from Sir John Parker
3 days ago

Farrans lands Leeds Bradford Airport phase 2 upgrade

Contractor takes follow-on refurb job after terminal extension
3 days ago

ISG built Bristol housing block to be torn down

Contractor's collapse sinks Bristol flats remediation claim
4 days ago

RSK revenue nears £2bn as losses soar to £132m

Refinancing last summer puts group on course for more growth this year
4 days ago

Bridge design wind error adds £20m to construction costs

Completion of £148m Grantham Southern Relief Road delayed by a year
4 days ago

Rayner pledges extra £350m for social house building

More than 3,000 homes could be built with cash injection
4 days ago

City’s biggest retrofit tower scheme approved

Triple-fronted 70 Gracechurch Street building will rise to 33 storeys
4 days ago

Defibrillator saves worker’s life on Wates site

Machine operator saved after "dying" for 16 minutes on prison job
4 days ago

Funding deal for £125m Camden Roundhouse scheme

Developer Regal set to start 264-bed student scheme
5 days ago

Balfour leadership rejig to focus on three key growth sectors

Divisional CEO trio take lead roles for energy, defence and transport expansion
5 days ago

ABP bidders day for £150m Humber ports pipeline

Nine projects in the pipeline to support automotive and energy transition schemes
5 days ago

Hinkley Point C to create 3,000 jobs as work ramps up

Fitout surge to swell workforce to 15,000 in next 18 months
5 days ago

Hercules sells suction excavator division for £2.4m

Loss making arm sold by labour hire specialist
5 days ago

Foundations complete at HS2 Old Oak Common station

Station base completed using 76,000 cubic metres of concrete and 17,000 tonnes of reinforced steel
5 days ago

Bids invited for £175m consultancy framework

Fusion21 inviting consultants to join latest four-year deal
5 days ago

Contractor services