Speedy HS2 viaduct push cuts disruption for drivers

Grant Prior 1 week ago
Share

HS2 engineers completed the final operation to move two railway viaducts into place over the M42/M6 link roads in North Warwickshire more than six hours ahead of schedule this weekend.

The ‘push’ to move the 158-metre-long West Link Viaduct into its final position over both westbound and eastbound motorway link roads took a total of 11 hours.

Main works contractor Balfour Beatty VINCI (BBV) completed the work quicker than planned allowing the motorway link roads to be reopened 6.5 hours ahead of schedule.

The viaducts are part of a group of 13 which make up HS2’s triangular Delta Junction. This section of the railway enables high speed trains to travel between London, Interchange Station in Solihull and Birmingham Curzon Street Station.

In June, the first 84 metre section of the composite viaduct was moved to its halfway position. Since then, three further steel girders were welded to the back of the first section and 38 precast concrete slabs were installed to complete the 158-metre-long structure, which has now been moved over both link roads.

The parallel ‘East Link Viaduct’ was moved into place using an identical two-stage process during two weekend operations in February and April this year. This viaduct is currently being prepared to be brought into use as an internal haul road by the end of December, to move material from Bromford Tunnel to the Delta Junction, taking thousands of lorries off the local road network.

The four operations were delivered by a team of 25 people from specialist steelwork company Victor Buyck Steel Construction (VBSC), working on behalf of BBV, using a push-pull jacking system which gives greater flexibility during the launch operation.

JoseLuis Preciados, Senior Project Manager at Balfour Beatty VINCI said: “This final viaduct push is a significant milestone in our construction of HS2’s Delta Junction. I’m incredibly proud of the BBV team, who’ve worked tirelessly throughout this year to ensure each of these complex operations were planned and delivered with precision.

“Each viaduct deck was built offline and moved into position over a weekend closure of the highway, drastically reducing the impacts on road users. We’ve worked in collaboration with our partners National Highways throughout the entire process, to make sure that this activity was delivered safely and efficiently.”

Tibo Suvée, Project Manager at Victor Buyck Steel Construction added: “This has been a complex eight-month operation, and the first time our push-pull jacking system has been used in the UK.

“The technique provides greater flexibility during the launching operation by allowing the bridge to be moved backwards or both ways if needed.”

Latest news

Henry Boot looking to new boss to boost construction

Construction turnover down as division behind schedule winning work
49 mins ago

Billington to expand Shafton works as order book swells

Low steel prices tempt clients to bring stalled projects to the market
25 mins ago

Network Plus Services doubles profit to £32m

Turnover at private equity-backed business tops £500m
52 mins ago

Coroner in training call after scissor-lift tragedy

Practical rescue training needed after worker crushed to death
16 hours ago

Deal to re-start £37m Burnley flood defence job

VolkerStevin/Jacobs' Padiham scheme stalled when costs doubled
2 hours ago

Big public procurement shake-up put back to February

Government delays Procurement Act go-live date by four months
59 mins ago

Architecture boss joins Caddick as Design Director

Former DLA Architecture director Jason Clarke to boost contractor's design offering
11 hours ago

Vinci Building and FM arms rack up big losses for second year

Inaugural consolidated accounts for all Vinci UK operations slip into the red
1 day ago

Plan lodged for two Birmingham student towers

Sama plans nearly 2,000 student rooms in 48 and 41 floor buildings at Lancaster Circus
1 day ago

Galliford Try delays annual results announcement

Accountants want more time to go through books
1 day ago

CITB urged to give everyone a say over need for levy

Consensus process slammed as a "charade"
1 day ago

Subcontractors wanted across north London

Constructionline event to highlight work opportunities: Register now
1 day ago

Latest construction hotspots appear outside London

Research reveals fastest growing areas for contract awards
1 day ago

Bachy Soletanche rejigs business in new growth plan

Business split into two regional and a major projects division
1 day ago

BAM, Arup and Amey win £2bn Network Rail contract

Largest single contract by value ever awarded by Network Rail.
4 days ago

Luton airport £2.4bn expansion decision delayed

Application decision deadline pushed back 3 months to January 2025.
4 days ago

Plan in for 2m sq ft Hertfordshire data centre campus

Proposed £3.75bn construction project near M25 would sustain 500 jobs
4 days ago

Balfour Beatty wins £363m electricity grid upgrade job

Work to start next year on 29km Bramford to Twinstead high voltage project
4 days ago

Winchmore wins £10m brickwork package with Lovell

Specialist will lay nearly 1m bricks on Thamesmead job
4 days ago

Green light for £125m Camden student scheme

Work to start later this year on site next to iconic Roundhouse
4 days ago

Strong revenue and profit growth puts Kier on firm footing

Revenue recovers to £4bn again with profit ahead almost a third to £68m
5 days ago

Galliford Try steps-in to build £57m Banwell bypass

New contractor found after original winner Alun Griffiths walked-away from job
5 days ago

Hotel M&E specialist Gallant files administration notice

Gallant Building Services is working on hotel, flats and care home projects
5 days ago

Torsion to deliver £43m Leeds student scheme

Construction to start next month on latest project for joint venture
5 days ago

Go-ahead for London Barbican office to flats project

London developer Hub aims to create over 170 co-living homes
6 days ago

Traditional builders dominate £800m MMC framework

20 out of 22 places on modular housing deal go to local contractors
6 days ago

Dubai contractor sells 15% stake in Costain

ASGC sells stake for £38m after investing £25m in fund raise four years ago
6 days ago

Amazon to invest £8bn in hyperscale datacentres

Data centre sector heats up as cloud computing giant AWS unveils big expansion plans
6 days ago

Plan lodged for Square Mile’s fifth tallest tower

54-floor 99 Bishopsgate tower will provide 1 m sq ft of office space
6 days ago

Morgan Sindall pulls off contracts league double

Firm swoops to top monthly and 12-month contracts league rankings
6 days ago

Contractor services