Work has started on the installation of 2,000 piles for the foundations of Birmingham’s Curzon Street Station which will be the city’s HS2 rail hub.

Work is being led by main contractor Mace Dragados Joint Venture (MDJV) and piling specialist Keltbray.

A team of 80 people are delivering the foundations work using three 95 tonne, 30-metre-tall piling rigs on the site.

Piling is planned to be completed by mid-2025, with the installation of further foundations on top of the piling starting next year. The design of the station will also be finalised over the next year, focusing on the details of features including the roof and the internal fit-out of the station.

Since work started on the Station site in January, the MDJV team have been completing activities to prepare for the piling to start. This includes major earthworks, as well as installing temporary platforms for the piling rigs to work on. Piling will also enable the construction of a new retaining wall to support the existing Victorian Network Rail wall adjacent to the West Coast Main Line.

Martyn Woodhouse, Project Director for MDJV said: “The start of foundation works for Curzon Street Station means we’re now starting a crucial stage of construction. Since the beginning of the year, the team has worked hard to deliver the major earthworks to prepare for the big piling operation which will form the foundations of the station.

“Once the foundations are complete, we’re looking forward to starting construction of the station building, which will create more jobs, apprenticeships and supply chain opportunities on the project as work ramps up.”

A number of major procurement packages will be up for grabs for businesses over the next year to secure the remainder of the supply chain companies needed to build the station.

Latest news

University of Warwick advances £700m campus plan

Enabling works to get underway for main build works next year
3 hours ago

Go-ahead for £750m East London data centre

Urban 11-storey data centre to be built next to River Lea and A13 in Newham
16 hours ago

Keltbray Infrastructure Services buys Linbrooke rail arm

First deal since infrastructure business was bought by private equity this summer
19 hours ago

Elizabeth Line wins Stirling Prize for architecture

Infrastructure scheme wins premier design prize
2 hours ago

Winners named for Worcestershire and West Mids framework

Deal covers development work from design to construction
2 hours ago

Piling starts on HS2 Curzon Street Station

Mace Dragados Joint Venture and Keltbray working on Birmingham site
2 hours ago

M Group joins top seven as revenue jumps to £2.2bn

Infrastructure services specialist continues to hunt acquisitions
1 day ago

BlackRock to take control of Lanes Group

Takeover of leading water contractor to complete this month
1 day ago

Yorkshire and Lincolnshire builders’ merchant goes under

1928-founded Builders Merchant Company hit by winding up petition
1 day ago

Trio wins £170m West Country new build housing deal

Curo Enterprise, E.G. Carter and Speller Metcalfe Malvern
1 day ago

Roofer dies in fall from potato box on forklift

Court hears how victim fell 16ft from makeshift platform
1 day ago

Clancy bolsters senior management team

Skanska project director Jon Arnold joins as operations director of energy
1 day ago

High tech construction plant could save country £417bn

Costain report says kit which connects and drives itself will provide a massive economic boost
2 days ago

Concrete frame defects cost Bellway another £14m

Cost of repairing Greenwich scheme rises while £5.4m was spent on aborted Crest Nicholson chase
2 days ago

Green light for 52-storey Isle of Dogs resi tower

460 flats One East Point project will be built at 3-4 Harbour Exchange
2 days ago

Contractors urged to “hire now” as labour supply crunch looms

Vacancies rise and wages grow as fight for new workers intensifies
2 days ago

Kier confirmed for £20m Yasa Motors Bicester HQ

Developer Bicester Motion advances future mobility business park
3 days ago

Data centres and airport expansion to spur growth

Government hails £25bn data centre and £1.1bn Stansted Airport expansion plan
3 days ago

Hinkley Point second reactor unit build up to 30% faster

Engineering team lifts last giant steel ring onto reactor 2 yesterday
2 days ago

BAM reassures supply chain after winding-up petition

Firm's credit rating temporarily affected after dispute with supplier
3 days ago

Winvic secures Leeds build to rent scheme

Phase one of £500m Sweet Street South Bank regeneration starts
3 days ago

£60m turnover construction group sold to staff

Meldrum Construction Services Group becomes Employee Owned Trust
3 days ago

Starmer vows to “rip out” obstacles to investment

Prime Minister to make pledge at inaugural International Investment Summit
3 days ago

VolkerFitzpatrick starts prep-work for £210m M3 junction upgrade

Main works to begin in early 2025 on Winchester junction job
3 days ago

London super sewer turned on after eight years of construction

£4.5bn project starts protecting River Thames from pollution
3 days ago

Housing and office new work jump fuels output recovery

August new construction work rebounds 1.6% after early summer fall
6 days ago

£300m London City fringe office tower approved

Rocket's 27-storey One Fairchild Street job set for take-off
7 days ago

Consultants named for London Tube Bakerloo Line extension

Aecom and architect WW+P to work up designs for four new stations
6 days ago

15 giant bridge beams lifted into place at HS2 station

Balfour Beatty VINCI carries-out civils work for Solihull station: Video
7 days ago

Ballymore JV picked for £500m King’s Cross scheme

Camley Street scheme to consist of 350 homes and offices
7 days ago

Contractor services