Rayner ultimatum to fix all unsafe tall buildings by 2029

Aaron Morby 4 months ago
Share

Deputy Prime Minister Angela Rayner has set out the Government acceleration plan to rid the country of unsafe buildings seven years after the Grenfell disaster.

Owners of unsafe 18m+ residential buildings are being ordered to start recladding works by 2027 to meet a fresh target to make all the country’s at-risk high-rise flats safe by 2029.

Also under the new Remediation Acceleration Plan, owners of the thousands of 11m+ buildings with flammable cladding will need to have completed or at least set a date for completion of remediation works to avoid severe financial penalties.

The plan is backed by further investment in enforcement – so that local authorities, fire and rescue authorities and the Building Safety Regulator have the capacity to tackle hundreds of cases per year.

Also the government will publish a joint action plan with developers to accelerate their work to fix buildings for which they are responsible.

At least 29 developers, covering over 95% of the buildings which developers are remediating themselves, have committed to more than doubling the rate at which they have been assessing and starting to fix unsafe buildings, meaning work on all their buildings will start by summer 2027.

To date, 95% of buildings with the same type of cladding used on Grenfell have been remediated.

But only 30% of identified buildings in England have been remediated, with potentially thousands more buildings yet to be identified.

Since July, the Government has engaged with Mayors, local enforcement agencies and developers to address the unacceptably slow pace of remediation and will now set out its plan to speed it up.

Remediation Acceleration Plan objectives


  1. Fix buildings faster: Speed-up remediation of high-risk buildings with clear deadlines and penalties for non-compliance.
  2. Identify all unsafe buildings: Identify all buildings with unsafe cladding to create a comprehensive building register.
  3. Support residents: Protect residents from financial burdens of remediation and improve their experience during the process.

Rayner said: “More than seven years on from the Grenfell tragedy, thousands of people have been left living in homes across this country with dangerous cladding.

“The pace of remediation has been far too slow for far too long. We are taking decisive action to right this wrong and make homes safe.

Latest news

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
10 hours ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
9 hours ago

New rail property company to unlock land for 40,000 homes

First four sites released in Newcastle, Cambridge, Manchester, and Nottingham
19 hours ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
12 hours ago

Drainage specialist Subscan files administration notice

Specialist employing 131 people files court notice
19 hours ago

Four win Network Rail £300m engineering design deal

Eastern region deal will include design for Northern Powerhouse Rail
18 hours ago

Funding go-ahead for Banwell bypass after fresh cost hike

Galliford Try contract rises £14m to £64m after final design change
1 day ago

Graham wins Southport £75m Marine Lakes Centre

Firm replaces Kier which parted ways with backer Sefton Council
1 day ago

Chancellor unveils extra £2bn capital spend a year

Construction promised a defence dividend in military base and homes upgrade work
1 day ago

McLaren confirms subcontractor team on £135m warehouse job

Work starts on TN2 Gateway site in Kent.
2 days ago

Vistry profits slump after site costs reporting debacle

House builder launches internal whistle-blowing service in business culture review
2 days ago

Severfield chief to step down

Alan Dunsmore to leave structural steel group by end of June
2 days ago

Funding hurdle remains as Lower Thames Crossing gains consent

Government claims £9bn project may start in 2026 as private finance options explored
3 days ago

Mace wins £600m Euston Tower overhaul

1970s tower's foundations and core to be retained as floor plates extended
2 days ago

Summer start for main works on London green tower

Axa sanctions start at 50 Fenchurch Street 36-storey office block
2 days ago

Japan’s leading flats builder JVs with L&G for UK push

Partners plan to build over 1,000 rental homes in London
2 days ago

Wates submits plan for 1,000 homes Harrow council scheme

Former civic centre Poets' Corner site kicks off housing partnership
2 days ago

Morgan Sindall upgrades forecast for next 12 months

Overbury fit-out arm gets off to a flying start in 2025
3 days ago

Restructure underway at Henry Boot Construction

New management team restructures business after drop in turnover
3 days ago

Government pledges £2bn stop-gap funding for 18,000 homes

Funding avoids cliff-edge in social housing delivery before new grant programme agreed
3 days ago

Just two major new roads schemes to start this year

National Highways sets out one-year interim spending plan after RIS3 delay
3 days ago

Plans go in for £400m GRAHAM Manchester site

Demolition and enabling works underway with main construction set to start next year
3 days ago

Building safety levy rate set at up to £10,000 a home in London

Levy introduction pushed back a year to Autumn 2026 - list of new rates
3 days ago

BAM wins £100m revamp of Broadgate Tower in London

Front of tower 3-storey extension to use cross laminate time and re-used steel
4 days ago

£600m funding to train 60,000 construction workers

Government pledges massive cash injection to produce "site-ready" workers
5 days ago

Construction to start in May on £1bn port expansion

Work at London Gateway site will last four years
6 days ago

Utilities specialist Ipsum buys second power contractor

Acquisition of Wootton & Wootton strengthens service in Midlands and Wales
4 days ago

Councils will lose cash if they fail to fix potholes

Local authorities will have to publish road repair stats
4 days ago

Green light for London Euston Tower rebuild

British Land says nearly a third of original tower will be retained
7 days ago

Contractors struggling to keep-up with demand for data centres

More than half of clients fear supply chain will struggle
7 days ago

Contractor services