HS2 set for “fundamental reset” to lower construction costs

Grant Prior 18 seconds ago
Share

New HS2 Chief Executive Mark Wild said the project is facing “a very serious situation” and is need of a “fundamental reset” in a bid to keep costs down to complete the rest of the route.

His comments came as a construction update revealed the majority of the deep tunnel drives and earthworks needed for the high-speed railway have now been completed.

Figures show that 70% of twin-bore tunnels have been excavated to date, representing 38 of the 55 miles being built for the railway.

In all, five out of 12 tunnel drives have been completed.

The update revealed that 58% of earthworks for the railway’s cuttings, embankments, stations and landscaping have been completed representing almost 92 million cubic metres of material moved in total so far.

Additionally work has started on construction of 158 out of 227 viaducts and bridges – 70% – with 13 already built.

But Wild – who joined the project at the start of December said: “HS2 represents a significant investment in Britain’s future and in the last month I’ve been inspired by the hugely impressive feats of civil engineering taking shape right along the route. New railways provide better journeys and they boost economic growth by fuelling investment in communities and businesses.

“The prize is clear. However, the programme is in a very serious situation that requires a fundamental reset to enable it to be delivered to the lowest feasible cost. I am committed to delivering this reset over the coming year to ensure the railway can be brought into service safely and efficiently.”

 

Latest news

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
1 week ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
1 week ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
1 week ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
1 week ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
2 weeks ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
2 weeks ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
2 weeks ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
2 weeks ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
2 weeks ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
2 weeks ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
2 weeks ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
2 weeks ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
2 weeks ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
2 weeks ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
2 weeks ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
2 weeks ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
2 weeks ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
2 weeks ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
2 weeks ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
2 weeks ago

Mace to close construction logistics arm

Specialist business being wound down
2 weeks ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
2 weeks ago

Profits double at Barhale

Civils specialist sees order book top £1bn
2 weeks ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
2 weeks ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
2 weeks ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
2 weeks ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
2 weeks ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
2 weeks ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
2 weeks ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
2 weeks ago

Contractor services