Hospital building plan extended by a decade – full list

Aaron Morby 1 hour ago
Share

The government has allocated an annual average spend of £3bn for a rephased new hospital programme that will now take a decade longer to deliver.

Laing O'Rourke's Cambridge Cancer Research Hospital timetabled for construction start by 2026
Laing O'Rourke's Cambridge Cancer Research Hospital timetabled for construction start by 2026

Following a fresh review, the Government confirmed all previously planned hospitals will be delivered but over a longer time frame of start times extending to 2039.

Hospital projects will be delivered in three further phases, each lasting five years.

Starts on the biggest schemes have been pushed back beyond 2030, which was the original target date for the whole programme when first launched by Boris Johnson.

Schemes already in construction (Wave 0) will continue as planned. The remaining hospital projects will advance in three waves over 15 years.

Wave 1 starting this year includes seven hospitals constructed primarily using RAAC.

Revised hospital programme timeline
Wave 0: schemes already under construction
Scheme Started construction Cost estimate
Alumhurst Road Children’s Mental Health Unit, Dorset £500m or less
Royal Bournemouth Hospital, Dorset £500m or less
St Ann’s Hospital, Dorset £500m or less
Dorset County Hospital, Dorchester £500m or less
CEDAR Programme, North East tbc
Oriel Eye Hospital, London tbc
National Rehabilitation Centre tbc
Wave 1: schemes to start construction between 2025 and 2030
Scheme Expected start date Cost estimate
Poole Hospital, Dorset 2025 to 2026 £500m or less
Derriford Emergency Care Hospital, Plymouth 2025 to 2026 £500m or less
Cambridge Cancer Research Hospital 2025 to 2026 £500m or less
Shotley Bridge Community Hospital, Durham 2026 to 2027 £500m or less
Milton Keynes Hospital 2027 to 2028 £500m or less
Women and Children’s Hospital, Cornwall 2027 to 2028 £500m or less
Hillingdon Hospital, north-west London 2027 to 2028 £1bn to £1.5bn
North Manchester General Hospital 2027 to 2028 £1bn to £1.5bn
West Suffolk Hospital, Bury St Edmunds (RAAC) 2027 to 2028 £1bn to £1.5bn
Hinchingbrooke Hospital (RAAC) 2027 to 2028 £501m to £1bn
James Paget Hospital, Great Yarmouth (RAAC) 2027 to 2028 £1bn to £1.5bn
Queen Elizabeth Hospital, King’s Lynn (RAAC) 2027 to 2028 £1bn to £1.5bn
Leighton Hospital (RAAC) 2027 to 2028 £1bn to £1.5bn
Airedale General Hospital (RAAC) 2027 to 2028 £1bn to £1.5bn
Frimley Park Hospital (RAAC) 2028 to 2029 £1.5bn to £2bn
Brighton 3Ts Hospital 2026 to 2027 tbc
Wave 2: schemes (to start construction between 2030 and 2035
Leeds General Infirmary 2032 to 2034 £1.5bn to £2bn
Specialist Emergency Care Hospital, Sutton 2032 to 2034 £1.5bn to £2bn
Whipps Cross University Hospital, north-east London 2032 to 2034 £1bn to £1.5bn
Princess Alexandra Hospital, Harlow 2032 to 2034 £1.5bn to £2bn
Watford General Hospital 2032 to 2034 £1.5bn to £2bn
Leicester General Hospital Royal Infirmary 2032 to 2034 £1bn to £1.5bn
Kettering General Hospital 2032 to 2034 £1bn to £1.5bn
Musgrove Park Hospital, Taunton 2032 to 2034 £501m to £1bn
Torbay Hospital 2032 to 2034 £501m to £1bn
Wave 3: schemes to start construction between 2035 and 2039
Charing Cross Hospital and Hammersmith Hospital, London 2035 to 2038 £1.5bn to £2bn
North Devon District Hospital, Barnstaple 2035 to 2038 £1bn to £1.5bn
Royal Lancaster Infirmary 2035 to 2038 £1bn to £1.5bn
St Mary’s Hospital, north west London 2035 to 2038 £2bn or more
Royal Preston Hospital 2037 to 2039 £2bn or more
Queen’s Medical Centre and Nottingham City Hospital 2037 to 2039 £2bn or more
Royal Berkshire Hospital, Reading 2037 to 2039 £2bn or more
Hampshire Hospitals 2037 to 2039 £2bn or more
Eastbourne District General, Conquest Hospital and Bexhill Community Hospital 2037 to 2039 £1.5bn to £2bn

Hospital projects destined for later waves will be supported on their development to ensure that they are ready for main construction.

Wes Streeting, health and social care secretary, said the new plan was an “honest, funded, and deliverable programme” to rebuild the NHS.

He added: “The New Hospital Programme we inherited was unfunded and undeliverable.

“Not a single new hospital was built in the past five years, and there was no credible funding plan to build forty in the next five years.”

In May 2023, the previous Conservative government announced that the already revised programme was backed by over £20bn of investment – but this funding was never delivered, says the Labour Government.

Streeting said the New Hospital Programme team would continue to work closely with industry to support construction, develop relationships and secure investment within the supply chain to help deliver cost effectively with repeatable modular design.

Morag Stuart, chief programme officer for the New Hospital Programme, said: “This announcement by the Department of Health and Social Care provides certainty on the next steps for the New Hospital Programme.

“We will continue to work with local NHS organisations to deliver improvements to hospitals across England, including making best use of new technology and improving layouts – and ensuring future hospitals are designed to meet the needs of patients and staff.”

The New Hospital Programme is just one part of the government’s wider commitment to transforming the NHS estate.

Over £1bn has been set aside to make inroads into the existing backlog of critical maintenance, repairs and upgrades, while £102m has been dedicated for upgrades to GP surgeries across England as a first step towards transforming the primary care estate.

Latest news

Hospital building plan extended by a decade – full list

All planned projects retained with new start dates to provide industry certainty
1 hour ago

Kier launches £20m share buyback as debt cut

Steady first-half trading shrinks average month end debt to £38m from £137m
32 mins ago

Plans unveiled for £365m Heathrow data centre

Distrubution centre developer moves into data centre market
37 mins ago

Plan for 6.5m sq ft Greater Manchester industrial zone

Russell LDP and Harworth to submit ambitious Northern Gateway plan this Spring
10 mins ago

Building boss sold diggers still on HP

Court hears how building director sold rented machines to fund sports car and gambling habit
16 hours ago

Wates names new hard FM chief

Jack Prady joins from Thermic Technical FM
16 hours ago

Council steps-in at sites where developer failed

First Endeavour LLP went under while building new homes across Fife
18 hours ago

Mace confirmed for £93m weather centre HQ

Work to start on weather scientist hub at University of Reading
24 hours ago

Council starts £200m hunt to replace Balfour Beatty

Tender race begins after Herefordshire Council parts ways with contractor
1 day ago

St William gets go-ahead for 245-home Stratford scheme

Planning approved for Stratford Gasworks regeneration
1 day ago

Balfour Beatty to sell Omnicom to Hitachi Rail

Digital rail monitoring business employs over 100 engineers
1 day ago

Van Elle partners with Wood on power transmission jobs

Ground investigation and piling deal worth over £30m
1 day ago

Former Balfour regional MD dies before taking up new role

Lindsay McGibbon struck down by cancer
4 days ago

One of Wales’ oldest contractors delivers record profit

Andrew Scott chairman says clients are now looking beyond lowest bids for jobs
4 days ago

Henry administrators chase £10m director payment

Cash frozen as legal action continues
5 days ago

Warning after scammers pose as plant hire bosses

Flannery targeted by fraudsters trying to con customers
4 days ago

Carey co-founder Tom Carey passes away

Contractor confirms death of second of three founding brothers
5 days ago

Robertson and Balfour win £333m schools deal

Contractors land work for five schools in Scotland
4 days ago

Go-ahead for £125m Ealing leisure centre and homes scheme

Council seeks contractor to deliver flagship Gurnell development
4 days ago

State of Englands local roads a ‘national embarrassment’

Spending watchdog urges Govt to tackle £15bn repair backlog
4 days ago

Worker loses three fingers at timber frame factory

Construction supplier fined after panel saw accident
4 days ago

Three in race for £20bn fusion power station

Balfour Beatty, Kier and Ferrovial head consortia in chase for 'star power' reactor
5 days ago

Office work drives 0.4% uptick in construction output

Activity in November grew four times faster than the UK economy as a whole.
5 days ago

Plans in for 34-storey Manchester student tower

Developer Vita plans 861-room tower in First Street district
5 days ago

Council quits homes joint venture to speed-up construction

Worthing Borough Council selling land to Roffey Homes
5 days ago

Kier signs £243m army barracks upgrade

Latest big defence optimisation deal signed off for Aldershot barracks
5 days ago

Winners revealed for £814m FM framework

Latest deal from Pagabo will provide roofing, mechanical and decorating work - see all 27 winners
6 days ago

Jackson signs £19m Sizewell C access roads deal

Latest contract takes work awarded to £2.5bn but concern mounts about final cost
5 days ago

Vistry slims down to three operating divisions

Delayed completions and lower sales push month-end debt to £535m
6 days ago

Business better than expected at bullish Galliford Try

Key work wins to power strong set of annual results
6 days ago

Contractor services