Hospital building plan extended by a decade – full list

Aaron Morby 1 month ago
Share

The government has allocated an annual average spend of £3bn for a rephased new hospital programme that will now take a decade longer to deliver.

Laing O'Rourke's Cambridge Cancer Research Hospital timetabled for construction start by 2026
Laing O'Rourke's Cambridge Cancer Research Hospital timetabled for construction start by 2026

Following a fresh review, the Government confirmed all previously planned hospitals will be delivered but over a longer time frame of start times extending to 2039.

Hospital projects will be delivered in three further phases, each lasting five years.

Starts on the biggest schemes have been pushed back beyond 2030, which was the original target date for the whole programme when first launched by Boris Johnson.

Schemes already in construction (Wave 0) will continue as planned. The remaining hospital projects will advance in three waves over 15 years.

Wave 1 starting this year includes seven hospitals constructed primarily using RAAC.

Revised hospital programme timeline
Wave 0: schemes already under construction
Scheme Started construction Cost estimate
Alumhurst Road Children’s Mental Health Unit, Dorset £500m or less
Royal Bournemouth Hospital, Dorset £500m or less
St Ann’s Hospital, Dorset £500m or less
Dorset County Hospital, Dorchester £500m or less
CEDAR Programme, North East tbc
Oriel Eye Hospital, London tbc
National Rehabilitation Centre tbc
Wave 1: schemes to start construction between 2025 and 2030
Scheme Expected start date Cost estimate
Poole Hospital, Dorset 2025 to 2026 £500m or less
Derriford Emergency Care Hospital, Plymouth 2025 to 2026 £500m or less
Cambridge Cancer Research Hospital 2025 to 2026 £500m or less
Shotley Bridge Community Hospital, Durham 2026 to 2027 £500m or less
Milton Keynes Hospital 2027 to 2028 £500m or less
Women and Children’s Hospital, Cornwall 2027 to 2028 £500m or less
Hillingdon Hospital, north-west London 2027 to 2028 £1bn to £1.5bn
North Manchester General Hospital 2027 to 2028 £1bn to £1.5bn
West Suffolk Hospital, Bury St Edmunds (RAAC) 2027 to 2028 £1bn to £1.5bn
Hinchingbrooke Hospital (RAAC) 2027 to 2028 £501m to £1bn
James Paget Hospital, Great Yarmouth (RAAC) 2027 to 2028 £1bn to £1.5bn
Queen Elizabeth Hospital, King’s Lynn (RAAC) 2027 to 2028 £1bn to £1.5bn
Leighton Hospital (RAAC) 2027 to 2028 £1bn to £1.5bn
Airedale General Hospital (RAAC) 2027 to 2028 £1bn to £1.5bn
Frimley Park Hospital (RAAC) 2028 to 2029 £1.5bn to £2bn
Brighton 3Ts Hospital 2026 to 2027 tbc
Wave 2: schemes (to start construction between 2030 and 2035
Leeds General Infirmary 2032 to 2034 £1.5bn to £2bn
Specialist Emergency Care Hospital, Sutton 2032 to 2034 £1.5bn to £2bn
Whipps Cross University Hospital, north-east London 2032 to 2034 £1bn to £1.5bn
Princess Alexandra Hospital, Harlow 2032 to 2034 £1.5bn to £2bn
Watford General Hospital 2032 to 2034 £1.5bn to £2bn
Leicester General Hospital Royal Infirmary 2032 to 2034 £1bn to £1.5bn
Kettering General Hospital 2032 to 2034 £1bn to £1.5bn
Musgrove Park Hospital, Taunton 2032 to 2034 £501m to £1bn
Torbay Hospital 2032 to 2034 £501m to £1bn
Wave 3: schemes to start construction between 2035 and 2039
Charing Cross Hospital and Hammersmith Hospital, London 2035 to 2038 £1.5bn to £2bn
North Devon District Hospital, Barnstaple 2035 to 2038 £1bn to £1.5bn
Royal Lancaster Infirmary 2035 to 2038 £1bn to £1.5bn
St Mary’s Hospital, north west London 2035 to 2038 £2bn or more
Royal Preston Hospital 2037 to 2039 £2bn or more
Queen’s Medical Centre and Nottingham City Hospital 2037 to 2039 £2bn or more
Royal Berkshire Hospital, Reading 2037 to 2039 £2bn or more
Hampshire Hospitals 2037 to 2039 £2bn or more
Eastbourne District General, Conquest Hospital and Bexhill Community Hospital 2037 to 2039 £1.5bn to £2bn

Hospital projects destined for later waves will be supported on their development to ensure that they are ready for main construction.

Wes Streeting, health and social care secretary, said the new plan was an “honest, funded, and deliverable programme” to rebuild the NHS.

He added: “The New Hospital Programme we inherited was unfunded and undeliverable.

“Not a single new hospital was built in the past five years, and there was no credible funding plan to build forty in the next five years.”

In May 2023, the previous Conservative government announced that the already revised programme was backed by over £20bn of investment – but this funding was never delivered, says the Labour Government.

Streeting said the New Hospital Programme team would continue to work closely with industry to support construction, develop relationships and secure investment within the supply chain to help deliver cost effectively with repeatable modular design.

Morag Stuart, chief programme officer for the New Hospital Programme, said: “This announcement by the Department of Health and Social Care provides certainty on the next steps for the New Hospital Programme.

“We will continue to work with local NHS organisations to deliver improvements to hospitals across England, including making best use of new technology and improving layouts – and ensuring future hospitals are designed to meet the needs of patients and staff.”

The New Hospital Programme is just one part of the government’s wider commitment to transforming the NHS estate.

Over £1bn has been set aside to make inroads into the existing backlog of critical maintenance, repairs and upgrades, while £102m has been dedicated for upgrades to GP surgeries across England as a first step towards transforming the primary care estate.

Latest news

Administrators take control at Acheson Construction

40 staff made redundant at South West regional contractor
10 hours ago

34 secure spots on £1bn NEPO civils framework

Balfour Beatty, Graham, Taylor Woodrow and Winvic signed up for first time
10 hours ago

Bouygues claims net zero construction goal at Welsh project

Llanelli leisure centre and health campus achieves green construction target
11 hours ago

Manchester civil service digital campus approved

Two Government office blocks totaling 900,000sq ft to cost £310m to build
10 hours ago

New mobile charging vans crack electric plant downtime anxiety

FM Conway trials new service that recharges small plant in one hour
10 hours ago

Build to rent deal kick starts 3,500-home Dagenham scheme

Deal secures 935-home first phase of Ford Dagenham plant redevelopment
20 hours ago

RSK adds another 110 staff with N-Able Group deal

Consultant and construction services group makes latest acquisition
11 hours ago

JRL Malaysian backers plan 580-home Wheat Quarter scheme

Plans in for Welwyn Garden City Shredded Wheat factory redevelopment
1 day ago

Recycled aggregate firms blast new waste crime levy

10% levy on all recycled aggregate producers to fund policing waste crime
1 day ago

£110m Liverpool Metalworks resi scheme gets nod

Legacie Contracts tipped for 16-storey Pumpfields project
1 day ago

Building products firm fined £1m after double accident

Scaffolder hurt in fall and worker caught in machinery at Norbord factory
1 day ago

Graham lands £42m Woking road upgrade

A320 upgrade will unlock new housing schemes along route
1 day ago

Dandara 300 homes High Wycombe project approved

Firm to demolish Chilterns Shopping Centre for build to rent job
1 day ago

Three Keltbray managers took £600,000 in bribes

Site managers convicted for taking kickbacks from labour supply specialist
2 days ago

Bidding starts for £1bn YORcivil major works deal

Eight firms face fight to renew places on big civils framework
2 days ago

ECF clinches deal for Hull 850-home urban village

East Bank waterside village plan advances
3 days ago

Maintenance firm Cardo in second Scottish acquisition

North Lanarkshire property maintenance firm Rodgers & Johnston bought
2 days ago

Kier confirms £41m Salford Uni health building job

Work starts on specialist three storey teaching building
2 days ago

Passenger train derailed after hitting track left by Colas workers

Contractor and Network Rail asked to make improvements after accident
3 days ago

Bryson signs £6m safety products deal with Skanska

Safety specialist becomes sole supplier to contracting giant
3 days ago

Murphy wins St Fergus gas compressor project

Three low emission compressor units to be installed for National Gas
3 days ago

Blenheim House payout hopes fade as claims hit £33m

Suggested 10p in the £1 payout for subcontractors now unlikely
3 days ago

£1.3bn decarbonising and fire safety deals out for bid

South East Consortium starts hunt for firms for housing upgrade work prize
3 days ago

£30m turnover M&E contractor files administration notice

TNA Electrical makes administration application
3 days ago

Plan for first big offices at £1.7bn Manchester innovation hub

500,000 sq ft of offices planned at renamed Sister development
3 days ago

Murphy starts work on £2.5bn Eastern Green Link 1

Giant subsea electricity cable project will take three years to build
3 days ago

Subcontractors wanted for work across Birmingham

Latest Constructionline event: Register now
3 days ago

Acheson Construction files administration notice

£53m turnover South West contractor lodges court notice
4 days ago

Hunt for 10 firms to deliver £37bn new hospital plan

Race starts for mega-framework with pledge to spread work among all firms
4 days ago

Springfield to build homes for army of green energy workers

Scottish house builder sells 2,480 plots to Barratt Redrow in strategy switch
4 days ago

Contractor services