Construction starts on more than 800 high-rise residential new-build and upgrade projects are being blocked by Building Safety Regulator design checks.

Frustrated developers warn the logjam in sign-offs to start building is now threatening to undermine the Government’s housing delivery and growth drive.

According to latest figures obtained from a Freedom of Information request from consultant Project4 over 90 major new-build projects are stuck in a bottleneck awaiting Gateway 2 design approval to start work.

Just 11 new-build jobs are reported to have cleared Gateway 2 checks, although only two of these are understood to have passed through the present checking regime.

The delays are also holding up retrofit works on over 600 existing High Risk Buildings (HRB) classified as over seven storeys or 18m.

The Building Safety Regulator (BSR) has come under fire for wasting time, increasing costs, and stalling important projects.

Developers complain they are having to grapple with unclear submission requirements, limited pre-submission consultation, and poor communication.

One developer told the Enquirer said: “We’re still waiting for sign-off on a scheme submitted 40 weeks ago, compared to the 12 weeks turnaround for applications quoted by the regulator.

“Frankly it’s a struggle to communicate with the regulator or the outsourced registered building control approver.

“We’re completely in the dark about what is happening.”

Another developer warned: “There is widespread confusion about what level of design is required for Gateway 2 applications. Some say RIBA 4 design, then we are told it must be full construction issue works detail.

“There is clearly no understanding of how the industry works. Industry procurement models would need a fundamental change to fall into line with these requirements. It basically means all specialist contractor detailed designs needs to be fixed at pre-construction.”

Some developers are now said to be looking at the possibility of reducing the height of planned projects to avoid the regulatory process.

Trade body, the Fire Industry Association, supports the thrust of the Building Safety Act, but is also deeply concerned about delays to HRB projects.

It describes processes as ‘overly complex and inefficient” and has called on the BSR immediately to review processes, procedures and guidance,

“This is an urgent issue, it is holding back commencement of construction of HRBs”, warns an FIA statement.

“This situation is counter to the accepted need for new housing stock and will significantly impact parts of the country where residential construction is predominantly HRB (rather than lower rise) such as cities.”

The association echoed calls for further guidance on the extent of design information required to reduce the wasted time and effort incurred by design teams and the BSR in submitting and reviewing designs that are at an inappropriate design stage.

The association also wants to see a stepped process of design submission to give developers confidence to develop full detailed designs for approval.

A spokesperson for the Building Safety Regulator said there had been an issue with the standard of applications being submitted.

“We are dedicated to working with industry to achieve timely approval of building control applications and safe and compliant HRB project completions.

“The new gateway processes brought in following the Grenfell Tragedy are a key control to raise safety standards in buildings. However the building regulations and requirements for building work have not changed in the new regime.

“We require developers to submit high-quality and clear building control applications which fully demonstrate compliance with building regulations to ensure a smooth approval process. This will also mitigate the risk of costly delays or potentially higher borrowing costs.

“We recognise that engaging with a new system and requirements is not something which can be achieved overnight and we’re continuing to work closely with industry to identify areas where we can strengthen our advice and guidance for applicants. This includes weekly discussions with partners including the Construction Leadership Council, Construction Industry Council, Build UK, Dept for Business and Trade and Home Builders Federation”.

Latest news

M&E specialist J S Wright files administration notice

Employee-owned Midlands specialist was established 135 years ago
1 day ago

£90m funding release for quartet of road upgrades

Government green lights schemes to improve journey times in Wiltshire, Leeds, Essex and Buckinghamshire.
1 day ago

Another month of repairs at McAlpine problem panel hotel

Road closure causes chaos as wind-hit cladding needs fixing above
1 day ago

Skanska lands design role on £1.25bn steelworks

Skanska team to work alongside main contractor McAlpine on Port Talbot project
2 days ago

Construction boss jailed for double Covid loan claim

Two-and-a-half years for building fraudster
1 day ago

Bleak January for construction buyers

Latest bellwether survey shows output down and costs up
2 days ago

Starmer rips up rules to ease building of nuclear reactors

Industry backs push for small modular reactors to be built where needed
2 days ago

McAlpine tops January work league with steelworks win

Port Talbot steelworks job dominates January orders haul
2 days ago

McLaren winning spree as £1bn turnover in sight

Major deals imminent as contractor posts stable set of results
2 days ago

Ring road builder wanted at £4bn Somerset gigafactory

Bidders wanted for £60m job. Latest video update from site
3 days ago

Kier seals HMP Glasgow super prison job at £684m

Deal finally signed to replace Scotland's notorious Barlinnie prison
3 days ago

Contract winners revealed for £332m Didcot infrastructure job

Construction set to start early next year
2 days ago

Fraudsters jailed after £22m construction tax scam

Gang sentenced after bogus payroll firm failed to pay VAT and CIS money to revenue
3 days ago

MPB clinches substructure for HS2 Curzon Street station

Contracts for station superstructure to be let in coming months
4 days ago

Flood defence spend rises to record £2.65bn over two-years

Key projects mapped as Government injects extra £250m to shore up defences
3 days ago

Turnaround strategy continues to pay off for Careys

Profits continue to rise as £50m investment plan in full swing
4 days ago

All change on £800m Eastern Highways Alliance

Octavius and Winvic sweep up all three lots in new line-up
3 days ago

Vinci bags first phase of £350m Stockport scheme

Contractor edges-out Willmott Dixon to start major mixed-used project
4 days ago

Crest Nicholson slumps to £144m loss

Incoming CEO review unearths further writedowns on fire remediation and closed divisions
4 days ago

Piling job cuts loom over safety regulator project delays

Bottleneck in high rise project approvals hits demolition and foundation firms
5 days ago

Developer Ghelamco swaps to self delivery for Battersea tower

John F Hunt no longer part of project team on 24-storey resi scheme
5 days ago

Pagabo starts renewal race for two mega frameworks

Contractors and developers asked for input on reshaping deals worth billions
4 days ago

Giant HS2 viaduct deck slide breaks records: Video

EKFB consortium oversees four-day installation
4 days ago

Ferrovial lands £230m National Grid tunnel

Work to start shortly on Grain to Tilbury electricity infrastructure upgrade
5 days ago

Tax-row tunnellers down tools on Balfour Hinkley job

Lodge allowance tax dispute hits tunnelling site
5 days ago

Go-ahead for Square Mile’s fifth tallest tower

Multiplex set to start 99 Bishopsgate job late next year
5 days ago

New £4.5bn funding model for stalled London rail schemes

Residential TIF funding offers key to unlock Bakerloo and DLR extensions
5 days ago

Speedy Hire latest to be hit by slow CP7 rail spending

Plant-hire firm flags issues with latest Network Rail spending round
5 days ago

FM Conway family chair steps away from business after Vinci deal

Joanne Conway steps away as Andrew Hansen becomes MD
5 days ago

Manchester Hotspur Press mill scheme rescued

37-storey student tower will now go-ahead
5 days ago

Contractor services