Piling job cuts loom over safety regulator project delays

Aaron Morby 3 months ago
Share

Hold-ups on gaining safety regulator approvals for high rise building projects are starting to put workers jobs at risk deep in the supply chain.

Specialist demolition and foundation contractors are warning job cuts loom as work dries up because developers are struggling to get clearance to start construction.

Since the introduction of the new regulatory framework in April 2024, only a handful of high risk building (HRBs) projects have cleared the approval system known as Gateway 2.

Now the Federation of Piling Specialists has added its voice to calls on government to urgently address delays being caused by the Building Safety Regulator approval process.

Around 92 new build high risk building projects are in the system awaiting approval. A further 18 applications have been invalidated or rejected by the Building Safety Regulator.

Just two new build projects are understood to have cleared the Gateway 2 hurdle in the last year.

The logjam is most acute in London and other urban areas, where projects over seven storeys are stalled, creating a ripple effect across the geotechnical, demolition, and construction supply chains.

The regulator is supposed to clear applications in 12 weeks although project timelines are extending as far a 40 weeks, particularly on big new build schemes.

The Building Safety Regulator argues approval times are coming down and are now on average taking 18 weeks, although the average includes many smaller refurb and retrofit projects.

FPS chair, Malcolm O’Sullivan, said many members were now being forced to consider reducing staff numbers and scaling back investment—actions that threaten to erode core teams and exacerbate existing skills shortages once projects eventually gain approval.

He said: “While we recognise the importance of the BSR’s role in improving building safety, the reality is that approval times of six months or more are simply not viable.

“These delays are undermining investment, recruitment, and the wider stability of the sector.

“More critically, they are jeopardising the Government’s ability to deliver its target of 1.5 million new homes over the next five years. Without urgent reform, these ambitions will remain out of reach.”

The regulator has blamed delays on a surge of applications last year and poor quality submissions that fail to meet requirements.

The Government and the BSR are being urged to review the process.

Firms want to see clearer and consistent guidance to ensure a streamlined approval process.

They also want more resources channelled into to accelerating approvals and closer working with industry stakeholders to develop practical solutions.

Latest news

Comment: Gateway is acting like a barricade

Contractors left banging their heads on an (unbuilt) brick wall
16 hours ago

Final phase of £1.5bn Elephant and Castle revamp hits planning

Get Living submits revised plan for 500 homes and 450-bed student block
2 days ago

Ealing backs final phase of £1.3bn estate rebuild

Friary Park estate rebuild in Acton reaches end stage
15 hours ago

Green light for scaled-down Nottingham student tower

Glasshouse Street scheme will deliver 247 student rooms
16 hours ago

Aston Villa to revamp North Stand

Club to reuse existing structure rather than complete rebuild
1 day ago

Mace signs ex-ISG director to lead Euro health and tech push

Gary Sweeney to head up healthcare and life sciences consultancy arm
15 hours ago

Sir Robert McAlpine claws way back into profit

Firm says return to profit and strong cash balance validates new strategy
2 days ago

Severfield to cut staff by 6% amid pricing pressure

Steelwork contractor warns of extended tighter pricing due to project delays
2 days ago

JRL completes sale of 50% stake to Malaysian giant IJM

Deal boosts balance sheet and kicks starts growth plan
2 days ago

Green light for £100m Liverpool Baltic station build

Enabling highway works to start in the autumn
2 days ago

First live tests for flying construction robots

Drones can lay construction materials at height on site
2 days ago

Three firms land £170m Gentoo Sunderland housing deal

PHS Solutions, Esh and RE:GEN to deliver 10-year home upgrade plan
2 days ago

Gateway gridlock hits build-to-rent delivery as starts nosedive

Build to rent starts plunge 18% in the capital
3 days ago

Call to shift Gateway 2 checks to end building bottleneck

"The current system isn't working but we all want to see safe buildings"
3 days ago

GBN launches £600m bid race for SMR engineer roles

Owner engineers to provide technical and assurance services
3 days ago

Wates hires ex-Homes England chief to head public sector push

Robert Stone to spearhead its public sector and national frameworks strategy
3 days ago

Acheson Construction collapse costs suppliers £8.5m

One frustrated creditor seized a telehandler after contractor went into administration
3 days ago

Dominus wins go-ahead for 173-bed Glasgow scheme

Old Wynd Street job expected to cost around £25m to build
3 days ago

Safety Regulator misses deadline to clear Gateway 2 backlog

Investors pulling out of funding high rise buildings
4 days ago

CITB still sitting on £95m cash pile

Staff numbers jump from 666 to 763 as training body wage bill soars
4 days ago

£500m road surfacing framework market call

NEPO goes out to consultation on north east regional highways deal
4 days ago

Two share £220m Scottish rail repairs and minor works deal

AmcoGiffen and CPMS win civils and building repair deals
4 days ago

Builder wanted for £60m London leisure and flats job

Tower Hamlets aims to replace St George’s Leisure Centre in Shadwell
4 days ago

Contractor confirmed for business park expansion

Roe Developments to start on next phase of Castle Donington scheme
4 days ago

Driver escapes injury as scaffold collapses onto van

Major three-lift scaffold fall blocks north London high street
1 week ago

Gilbert Ash to be sold to staff

£267m turnover contractor to transition to an Employee Ownership Trust
1 week ago

M Group seals biggest-ever deal with Telent takeover

Digital infrastructure specialist deal lifts turnover to £3bn
1 week ago

Aggregates firm Ashville went down owing more than £3m

Debts revealed in Companies House update
1 week ago

Cardo saves 100 jobs at Breyer roofing arm

Private equity-backed Welsh maintenance group continues to expand
1 week ago

Excavator knocked off lorry going under bridge

Traffic Commissioner inquiry after accident in south London
1 week ago

Contractor services