Giant HS2 viaduct deck slide breaks records: Video

Grant Prior 1 month ago
Share

HS2 has released new timelapse footage showing engineers completing the heaviest and longest single-stage viaduct deck slide on the project so far.

The four-day operation – which was completed on Sunday – involved sliding the 4,500 tonne deck across a road and railway line near Wendover in Buckinghamshire.

Stretching for 345m, the Small Dean viaduct is one of 50 major viaducts on the HS2 project.

Its concrete and steel deck was assembled to its full length before the slide began with most of the precast concrete deck slabs installed in advance of the launch. This increased the weight of the slide but will save time during the later stages of the project.

The whole operation was the heaviest and longest slide of a signal-stage viaduct deck on the HS2 project so far. The A413 was reopened at around 8.30pm on Friday, nine hours ahead of schedule.

During the slide, special pads covered in PTFE – a Teflon-like material usually found on the surface of a non-stick frying pan – were used to minimise friction between the deck and the temporary steel bearings on top of each of the piers. A cable system was used to slide the deck forward at speeds of up to 10 metres per hour.

HS2 Ltd Project Manager, Jason Bicknell said: “Small Dean is the longest continuous deck slide on the project and an amazing engineering achievement. But it would not have been possible without the huge amount of preparatory work put in over the last few years and I’d like to thank everyone involved. Two years ago, we set a target to install the deck in summer 2025 and it’s great that we came in ahead of schedule.”

Before the slide could begin, the team spent four years preparing the site, diverting utilities, realigning the road, building the abutments and six piers that support the viaduct and assembling the deck.

With the deck now in position, engineers can begin the challenging job of lowering it by 60cm onto the permanent bearings which will support the full weight of the viaduct. The two-month long operation will see it carefully lowered by 20cm at a time, pier-by pier, until the whole deck settles into its final position.

The viaduct is one of only two places in the Chilterns where the HS2 route will be above ground level, with the underside of the viaduct just 6m above the road, supported by the huge Y-shaped piers.

Like the nearby Wendover Dean viaduct, Small Dean’s enormous deck is made from weathering steel, which naturally ages to a characteristically dark russet finish to echo the natural tones of the surrounding landscape.

Both viaducts have innovative ‘double composite’ structures, with layers of reinforced concrete on the top and bottom to create a much more structurally efficient box-like span which dramatically cuts the amount of embedded carbon in the design.

In a nod to the great railway bridges of the Victorian age, the side of the Small Dean beam features prominent deck stiffeners which help to manage the structural forces while allowing for a more structurally efficient span.

The viaduct is being delivered by HS2 Ltd’s main works contractor, EKFB – a team made up of Eiffage, Kier, Ferrovial Construction and BAM Nuttall – working with their design partner, ASC (a joint venture between Arcadis Setec and COWI). They worked closely with a team from Network Rail to plan and deliver work close to the railway.

Martin Gamble, EKFB’s Senior Project Manager said: “The team at Small Dean Viaduct has worked tirelessly over a number of years to prepare for this momentous event. Through careful planning and by implementing time-saving measures, we’ve accelerated the bridge and support construction, bringing the launch date forward.

“The complexity of the interfaces with the road and railway have provided a real challenge which, with the assistance of Network Rail and Buckinghamshire Council, we have risen to and overcome, while keeping disruption to the surrounding area to a minimum.”

Latest news

Planning Bill to have “seismic” impact on construction

Building-boosting reforms go before Parliament
14 hours ago

Man Utd confirm plan for £2bn ‘super-tent’ stadium

Club to press ahead with 100,000-seat 'Wembley of the North'
18 hours ago

Government spending keeps profits edging-up at Kier

91% of work now with public sector and regulated companies
21 hours ago

Costain on track for step change to 5% margin

Alex Vaughan says order book has jumped £1.5bn to £5.4bn
20 hours ago

Mace tops February contracts league

Confirmation of £300m London Victoria Street project lifts firm to pole position
20 hours ago

Wates raids Laing O’Rourke for new construction operations chief

George Mosey leaves Laing O'Rourke after 16 years
1 day ago

Travis Perkins CEO Pete Redfern steps down due to ill health

Redfern joined builders' merchant last year after 14 years at Taylor Wimpey
2 days ago

Morgan Sindall wins £61m Liverpool lab scheme

Construction to start this Autumn on latest Knowledge Quarter project
20 hours ago

Glencar to build timber-framed office block

Work to start next month on 79,200 sq ft scheme in Maidenhead
2 days ago

Shed specialist Marbank files administration notice

£67m turnover portal-framed building specialist files court notice
2 days ago

Birmingham council submits £1bn Druids Heath plan

High rise estate to be replaced by-3,500 home eco village
2 days ago

Cannabis farm gang posed as utilities contractor

Gang jailed for 28 years after diverting power to more than 100 cannabis farms
4 days ago

Firm fined after workers climb scaffold without ladder

HSE investigation prompted by death on Liverpool site
2 days ago

Clancy renews £250m Southern Water deal

Contractor vows to maximise value for money and minimise disruption
2 days ago

McLaren go-ahead for 314 flats Watford scheme

Police station and magistrates court to be demolished
2 days ago

Former Liverpool mayor charged in building contracts probe

Construction bosses also charged as part of Operation Aloft
5 days ago

Bidding to start for £700m Irish sea interconnector work

Work includes converter stations at Hunterston and Kilroot near Belfast
5 days ago

Muse to redevelop Durham County Hall HQ site

Morgan Sindall regen specialist seals another major development deal
5 days ago

Mace to transform Imperial College Great Hall

Work to start next month on ambitious refit
5 days ago

£100m plan to regenerate former Digbeth ironworks

Hartwell unveils 260,000 sq ft office and 240 homs plan
5 days ago

Legendre UK wins £21m London homes job for Clarion

Tower Hamlets building to be replaced due to building and fire safety issues
5 days ago

Construction buyers report fastest downturn since 2020

Double whammy of decreasing new orders and delayed projects
6 days ago

Bidders day for £15bn schools alliance framework

Online event to set out details of DfE alliancing framework procurement plan
6 days ago

MPs told safety regulator delays forcing industry job cuts

Industry chief warns housing select committee that BSR is now a main block on meeting housing targets
6 days ago

£600m delivery partner named for new hospital programme

Mace/T&T JV named programme delivery partner for £37bn new hospital plan
6 days ago

£230m Southampton waterfront scheme approved

Town Quay includes trio of 25 storey towers around new marina
6 days ago

Planning green light for £10bn Northumberland data centre

Blackstone-backed project will create 1,200 construction jobs
7 days ago

Bauhaus block above Southwark Station gets green light

Student accommodation and affordable housing scheme replaces original office plan
6 days ago

Police arrest plant hire fraud gang

Nine arrests after kit hired "with no intent of ever returning the machines"
7 days ago

Balfour Beatty boss Leo Quinn to step down

Group Chief Executive to be replaced by consultant AtkinsRéalis chief Philip Hoare
7 days ago

Contractor services