Foundations complete at HS2 Old Oak Common station

Grant Prior 5 hours ago
Share

Foundations for the HS2 station at Old Oak Common in London have been completed.

The 850-metre-long underground station base, which will house six platforms for high-speed trains, has been constructed using 76,000 cubic metres of concrete and 17,000 tonnes of reinforced steel.

The base slab covers 45,000 square metres – equivalent to more than six football pitches – and reaches nearly two metres thick at its deepest point. Construction began in April 2023 and required 91 separate concrete pours to complete.

The station is being built by Balfour Beatty Vinci SYSTRA joint venture (BBVS). At peak construction, the base slab works employed up to 50 steel fixers and 20 joiners, supported by a team of engineers.

When complete, the station will be one of the best connected in the UK, with the six underground platforms allowing high-speed services to reach central London in one direction and the West Midlands in the other, with services running further north via the existing railway.

Additionally, eight surface-level platforms are being constructed to provide an interchange to the Great Western Railway, Elizabeth Line and Heathrow Express.

The excavation of the box was completed in the summer of 2024 with sub-contractor Expanded removing 1.3 million tonnes of London clay.

To create the base slab, the team installed blinding, layers of shingle for drainage before a matt could be laid on top. Then a 1.85 metre high reinforcement layer was installed– with the team fixing the steel by hand. Finally, concrete was poured to compete the slab, competing the foundations for the high-speed station area.

London Concrete, part of the Holcim Group, has supplied the concrete used to complete the base slab from a dedicated batching plant on site. In addition, low carbon ECOPact concrete has been used, contributing to the drive to reduce carbon used in construction.

Steve O’Sullivan, Project Director for Balfour Beatty VINCI SYSTRA, joint venture said: “With the completion of the base slab, we have achieved another significant milestone at Old Oak Common. In less than two years, we have carried out 91 concrete pours of between 600m3 and 1 000m3 each. Logistically, this has been a huge undertaking, requiring detailed planning and collaboration between HS2, Balfour Beatty VINCI SYSTRA and our supply chain partners.”

Work is now underway on the six HS2 service platform with wall frameworks being installed ready for concrete pouring. The high-speed platform slabs are currently being manufactured by Explore in Worksop and installation will begin this spring.

The team are also working above the base slab to construct the ground floor level of the station before the superstructure can be built, creating the vibrant station environment.

Tunnelling work to connect the station to the HS2 network is being done by HS2’s London tunnels contractor, Skanska Costain STRABAG JV. In the eastern section of the box, the team are preparing to launch two giant tunnelling machines towards Euston. In the western side of the box, the team will excavate the tunnel using the sprayed concrete lining method.

Latest news

Defibrillator saves worker’s life on Wates site

Machine operator saved after "dying" for 16 minutes on prison job
2 hours ago

Balfour leadership rejig to focus on three key growth sectors

Divisional CEO trio take lead roles for energy, defence and transport expansion
16 hours ago

ABP bidders day for £150m Humber ports pipeline

Nine projects in the pipeline to support automotive and energy transition schemes
5 hours ago

Funding deal for £125m Camden Roundhouse scheme

Developer Regal set to start 264-bed student scheme
5 hours ago

Hinkley Point C to create 3,000 jobs as work ramps up

Fitout surge to swell workforce to 15,000 in next 18 months
5 hours ago

Hercules sells suction excavator division for £2.4m

Loss making arm sold by labour hire specialist
5 hours ago

Foundations complete at HS2 Old Oak Common station

Station base completed using 76,000 cubic metres of concrete and 17,000 tonnes of reinforced steel
5 hours ago

Bids invited for £175m consultancy framework

Fusion21 inviting consultants to join latest four-year deal
5 hours ago

Regulator pledges to clear 122 project backlog by April

A third of applications failed to meet required standards says building safety regulator
1 day ago

Government opens bidding for new AI Growth Zones

Interest for sites in Scotland, Wales, the North East and North West
1 day ago

Vistry strikes deal for phase 3 of £1.2bn London estate rebuild

323-homes at giant Clapham Park scheme move to construction
1 day ago

Fire hits £31m student accommodation site

Blaze breaks out on Lancaster job where Bridgestone Construction is main contractor
2 days ago

Green light for £250m Salford data centre

Six acre plot to be transformed at Peel Waters site
1 day ago

Two in race for £269m HS2 people mover deal

Winner expected next year as hunt continues for infrastructure builder
1 day ago

M&E specialist J S Wright files administration notice

Employee-owned Midlands specialist was established 135 years ago
4 days ago

£90m funding release for quartet of road upgrades

Government green lights schemes to improve journey times in Wiltshire, Leeds, Essex and Buckinghamshire.
4 days ago

Another month of repairs at McAlpine problem panel hotel

Road closure causes chaos as wind-hit cladding needs fixing above
4 days ago

Skanska lands design role on £1.25bn steelworks

Skanska team to work alongside main contractor McAlpine on Port Talbot project
5 days ago

Construction boss jailed for double Covid loan claim

Two-and-a-half years for building fraudster
4 days ago

Bleak January for construction buyers

Latest bellwether survey shows output down and costs up
5 days ago

Starmer rips up rules to ease building of nuclear reactors

Industry backs push for small modular reactors to be built where needed
5 days ago

McAlpine tops January work league with steelworks win

Port Talbot steelworks job dominates January orders haul
5 days ago

McLaren winning spree as £1bn turnover in sight

Major deals imminent as contractor posts stable set of results
6 days ago

Ring road builder wanted at £4bn Somerset gigafactory

Bidders wanted for £60m job. Latest video update from site
6 days ago

Kier seals HMP Glasgow super prison job at £684m

Deal finally signed to replace Scotland's notorious Barlinnie prison
6 days ago

Contract winners revealed for £332m Didcot infrastructure job

Construction set to start early next year
5 days ago

Fraudsters jailed after £22m construction tax scam

Gang sentenced after bogus payroll firm failed to pay VAT and CIS money to revenue
6 days ago

MPB clinches substructure for HS2 Curzon Street station

Contracts for station superstructure to be let in coming months
7 days ago

Flood defence spend rises to record £2.65bn over two-years

Key projects mapped as Government injects extra £250m to shore up defences
6 days ago

Turnaround strategy continues to pay off for Careys

Profits continue to rise as £50m investment plan in full swing
7 days ago

Contractor services