Bridge design wind error adds £20m to construction costs

Grant Prior 2 hours ago
Share

Lincolnshire County Council has warned that its £148m Grantham Southern Relief Road could cost an extra £20m to build following a bridge design error.

The issues with the rollout of the bridge over the River Witham and the East Coast Main Line will also delay completion of the route by a year to 2026.

Cllr Richard Davies, executive member for highways, said: “This mistake related to the how the bridge was to be installed and us being told it couldn’t be pushed into place as intended due to concerns relating to specific wind conditions.

“Safety comes first, so the work was halted so our designers and contractors could address the problem.”

Galliford Try is main contractor on the current third phase and also built the second phase which was completed in 2022.

A Galliford Try spokesperson said: “Galliford Try continues to work in a collaborative manner with all the stakeholders on Grantham Southern Relief Road to ensure the safe and timely delivery of this vital piece of infrastructure.

“The challenges that have led to the reported delays relate to the design of the bridge across the River Witham and the East Coast Main Line and Galliford Try is contracted on a construct-only basis on the project.”

Cllr Davies added: “The complexities of designing and constructing this relief road, particularly this bridge, are far beyond what we as a council can do directly.

“That’s why top international engineering companies and experienced contractors were entrusted to handle the project. Although we oversee the scheme as a whole, we rely on our suppliers’ combined expertise.

“When undertaking a project of the magnitude, all design work also undergoes a mandatory, additional layer of independent checking. Unfortunately, despite all of this, a mistake was made along the way that’s led to this new delay.”

Once underway the bridge push over the 293-metre span will take several months as it crosses the rail line during overnight periods when trains have stopped running.

The rest of the structure will then be built on the east side of site, including lifting new steel beams into place.

Several more months will then be spent concreting the decks, installing safety barriers, and laying road surfacing.

Cllr Davies said: “The important thing is that the details of the solution are nearly finalised, meaning we can start pushing the bridge into place in the coming months.”

Latest news

ISG built Bristol housing block to be torn down

Contractor's collapse sinks Bristol flats remediation claim
2 hours ago

RSK revenue nears £2bn as losses soar to £132m

Refinancing last summer puts group on course for more growth this year
2 hours ago

Bridge design wind error adds £20m to construction costs

Completion of £148m Grantham Southern Relief Road delayed by a year
2 hours ago

Rayner pledges extra £350m for social house building

More than 3,000 homes could be built with cash injection
1 hour ago

City’s biggest retrofit tower scheme approved

Triple-fronted 70 Gracechurch Street building will rise to 33 storeys
19 hours ago

Defibrillator saves worker’s life on Wates site

Machine operator saved after "dying" for 16 minutes on prison job
23 hours ago

Funding deal for £125m Camden Roundhouse scheme

Developer Regal set to start 264-bed student scheme
1 day ago

Balfour leadership rejig to focus on three key growth sectors

Divisional CEO trio take lead roles for energy, defence and transport expansion
2 days ago

ABP bidders day for £150m Humber ports pipeline

Nine projects in the pipeline to support automotive and energy transition schemes
1 day ago

Hinkley Point C to create 3,000 jobs as work ramps up

Fitout surge to swell workforce to 15,000 in next 18 months
1 day ago

Hercules sells suction excavator division for £2.4m

Loss making arm sold by labour hire specialist
1 day ago

Foundations complete at HS2 Old Oak Common station

Station base completed using 76,000 cubic metres of concrete and 17,000 tonnes of reinforced steel
1 day ago

Bids invited for £175m consultancy framework

Fusion21 inviting consultants to join latest four-year deal
1 day ago

Regulator pledges to clear 122 project backlog by April

A third of applications failed to meet required standards says building safety regulator
2 days ago

Government opens bidding for new AI Growth Zones

Interest for sites in Scotland, Wales, the North East and North West
2 days ago

Vistry strikes deal for phase 3 of £1.2bn London estate rebuild

323-homes at giant Clapham Park scheme move to construction
2 days ago

Fire hits £31m student accommodation site

Blaze breaks out on Lancaster job where Bridgestone Construction is main contractor
3 days ago

Green light for £250m Salford data centre

Six acre plot to be transformed at Peel Waters site
2 days ago

Two in race for £269m HS2 people mover deal

Winner expected next year as hunt continues for infrastructure builder
2 days ago

M&E specialist J S Wright files administration notice

Employee-owned Midlands specialist was established 135 years ago
5 days ago

£90m funding release for quartet of road upgrades

Government green lights schemes to improve journey times in Wiltshire, Leeds, Essex and Buckinghamshire.
5 days ago

Another month of repairs at McAlpine problem panel hotel

Road closure causes chaos as wind-hit cladding needs fixing above
5 days ago

Skanska lands design role on £1.25bn steelworks

Skanska team to work alongside main contractor McAlpine on Port Talbot project
6 days ago

Construction boss jailed for double Covid loan claim

Two-and-a-half years for building fraudster
5 days ago

Bleak January for construction buyers

Latest bellwether survey shows output down and costs up
6 days ago

Starmer rips up rules to ease building of nuclear reactors

Industry backs push for small modular reactors to be built where needed
6 days ago

McAlpine tops January work league with steelworks win

Port Talbot steelworks job dominates January orders haul
6 days ago

McLaren winning spree as £1bn turnover in sight

Major deals imminent as contractor posts stable set of results
6 days ago

Ring road builder wanted at £4bn Somerset gigafactory

Bidders wanted for £60m job. Latest video update from site
7 days ago

Kier seals HMP Glasgow super prison job at £684m

Deal finally signed to replace Scotland's notorious Barlinnie prison
7 days ago

Contractor services