Gateway 2 approval delay pushes back Bristol student scheme

Aaron Morby 1 month ago
Share

The country’s biggest student accommodation developer has had to push back the opening of a £70m student scheme in Bristol because of delays caused by Gateway 2 approval from the fire safety watchdog.

Freestone Island development scheme
Freestone Island development scheme

The 500-bed Freestone Island development scheme in the Temple Meads area of Bristol was originally timetabled to open by September next year, but delays in gaining key Gateway 2 approval to start construction have now pushed the project back by around a year.

Joe Lister, Unite chief executive, said this morning that new supply of purpose built student accommodation had been hit by a perfect storm of planning delays, cost inflation and now fire safety regulator delay.

“New supply of PBSA is also down 60% on pre-pandemic levels, reflecting viability challenges created by higher costs of construction and funding as well as planning backlogs and time required to secure Building Safety Act approvals.

Planning timescales remain protracted due to limited planning resource for local authorities, resulting in longer delivery programmes which challenge viability.

“We expect the combination of complex planning, increasing regulation, and higher build and funding costs to restrict the delivery of new supply for several years,” he warned.

He added that even once the initial backlogs were cleared for fire safety regulator gateway approvals programmes would be extended by the Building Safety Act.

“We expect these gateways will add around six months to PBSA development programmes once embedded, putting pressure on returns and further slowing new supply. Our appraisals and delivery targets reflect the expected impact of the Act.”

Lister said that viability challenges meant that weekly rents now need to be at least £200 for new PBSA development outside of London, meaning there was presently little prospect of new supply in many markets.

Latest news

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
14 hours ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
13 hours ago

New rail property company to unlock land for 40,000 homes

First four sites released in Newcastle, Cambridge, Manchester, and Nottingham
23 hours ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
16 hours ago

Drainage specialist Subscan files administration notice

Specialist employing 131 people files court notice
23 hours ago

Four win Network Rail £300m engineering design deal

Eastern region deal will include design for Northern Powerhouse Rail
22 hours ago

Funding go-ahead for Banwell bypass after fresh cost hike

Galliford Try contract rises £14m to £64m after final design change
1 day ago

Graham wins Southport £75m Marine Lakes Centre

Firm replaces Kier which parted ways with backer Sefton Council
1 day ago

Chancellor unveils extra £2bn capital spend a year

Construction promised a defence dividend in military base and homes upgrade work
2 days ago

McLaren confirms subcontractor team on £135m warehouse job

Work starts on TN2 Gateway site in Kent.
2 days ago

Vistry profits slump after site costs reporting debacle

House builder launches internal whistle-blowing service in business culture review
2 days ago

Severfield chief to step down

Alan Dunsmore to leave structural steel group by end of June
2 days ago

Funding hurdle remains as Lower Thames Crossing gains consent

Government claims £9bn project may start in 2026 as private finance options explored
3 days ago

Mace wins £600m Euston Tower overhaul

1970s tower's foundations and core to be retained as floor plates extended
3 days ago

Summer start for main works on London green tower

Axa sanctions start at 50 Fenchurch Street 36-storey office block
2 days ago

Japan’s leading flats builder JVs with L&G for UK push

Partners plan to build over 1,000 rental homes in London
2 days ago

Wates submits plan for 1,000 homes Harrow council scheme

Former civic centre Poets' Corner site kicks off housing partnership
2 days ago

Morgan Sindall upgrades forecast for next 12 months

Overbury fit-out arm gets off to a flying start in 2025
3 days ago

Restructure underway at Henry Boot Construction

New management team restructures business after drop in turnover
3 days ago

Government pledges £2bn stop-gap funding for 18,000 homes

Funding avoids cliff-edge in social housing delivery before new grant programme agreed
3 days ago

Just two major new roads schemes to start this year

National Highways sets out one-year interim spending plan after RIS3 delay
3 days ago

Plans go in for £400m GRAHAM Manchester site

Demolition and enabling works underway with main construction set to start next year
3 days ago

Building safety levy rate set at up to £10,000 a home in London

Levy introduction pushed back a year to Autumn 2026 - list of new rates
4 days ago

BAM wins £100m revamp of Broadgate Tower in London

Front of tower 3-storey extension to use cross laminate time and re-used steel
4 days ago

£600m funding to train 60,000 construction workers

Government pledges massive cash injection to produce "site-ready" workers
5 days ago

Construction to start in May on £1bn port expansion

Work at London Gateway site will last four years
7 days ago

Utilities specialist Ipsum buys second power contractor

Acquisition of Wootton & Wootton strengthens service in Midlands and Wales
4 days ago

Councils will lose cash if they fail to fix potholes

Local authorities will have to publish road repair stats
4 days ago

Green light for London Euston Tower rebuild

British Land says nearly a third of original tower will be retained
7 days ago

Contractors struggling to keep-up with demand for data centres

More than half of clients fear supply chain will struggle
7 days ago

Contractor services