Watchdog MPs raise alarm over HS2 Euston station plan

Aaron Morby 4 months ago
Share

MPs on the Public Accounts Committee have lambasted the management of the HS2 project and raised grave concerns about the latest plan to deliver the Euston terminus in London.

Grand plans for Euston, but PAC questions when it will actually get built
Grand plans for Euston, but PAC questions when it will actually get built

Their report published today calls for “fundamental reset” of the project by the summer.

They warn that they remain sceptical about the Government’s ability to successfully deliver its revised programme following a litany of failures and unheeded warnings.

The report says that the HS2 programme has become a casebook example of how not to run a major project.

“It is unacceptable that over a decade into the programme we still do not know what it will cost, what the final scope will be, when it will finally be completed or what benefits it will deliver,” states their report.

Watchdog MPs also highlighted the significant challenges facing plans to build the Euston Station terminus using a third party development body.

As plans stand, HS2 will open with a terminus at Old Old Common. Despite plans to launch the TBM tunnel drive next year to Euston from Old Oak Common there are no detailed plans or timescale for delivering the Euston Terminus, warns the report.

The Government’s Euston plans currently rest on the £6bn cost being significantly underpinned by the private sector.

The PAC said it was concerned that there is no clear plan for this, and said it was sceptical the private sector would come forward to the level required.

The government confirmed that HS2 would terminate at London Euston in the Autumn 2024 budget.

However, the PAC warns the Department still does not yet have a plan for the work at Euston which includes: the HS2 station, the existing Network Rail station, the underground station, and the commercial and housing developments near the station.

“In addition, the Department intends the work to be sustantively privately funded, but it is unclear how achievable this goal is,” they warn.

Sir Geoffrey Clifton-Brown MP, Chair of the Committee, said: “Our Committee has not made recommendations in our report on delivering better outcomes for HS2’s future passengers.

“We are long past that point. It is time to deal with HS2 as what it is – a cautionary tale that should be studied by future Governments in how not to run a major project.

“We are sceptical of Government’s ability to successfully deliver even a curtailed scheme, one which we already know will on its face bring very poor value for money. The question has instead become: what possible benefit can the Government now salvage for the taxpayer, from a mess that presents real risks to the UK’s overall reputation?”

The Department for Transport’s present cost estimated set out in November 2023 is £45bn to £54bn compared with HS2 Ltd’s latest estimate of £54bn to £66bn in June 2024.

Both cost estimates are still in 2019 prices, once adjusted for inflation, the total programme costs might be close to £80bn, states the report.

 

Latest news

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
20 hours ago

New boss at Eric Wright Civil Engineering

Gavin Hulme takes top job as Diane Bourne moves to group role
5 hours ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
21 hours ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
21 hours ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
20 hours ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
2 days ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
2 days ago

Permasteelisa wins cladding deal on Bovis city tower

Facade specialist lands package at 60 Gracechurch Street
20 hours ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
2 days ago

Major Building Safety Regulator shake-up to end tower delays

HSE stripped of control and top fire chiefs brought in to fast-track stalled schemes
2 days ago

Hinkley trio sign Sizewell civils deal

Balfour,Bouygues and Laing O'Rourke form Civil Works Alliance for new power station
2 days ago

£3.9bn data centre plan for Ravenscraig steelworks

Green energy to power massive new steel to silicon AI campus
2 days ago

Breakthrough on HS2’s second longest tunnel

8.4 mile Northolt to Old Oak Common drive completes
2 days ago

Neilcott on fast-track to debt-free employee ownership

£22.5m loan nearly paid down after big profit year
2 days ago

TfL kicks off race for £700m Tube station upgrade

South Kensington and Elephant & Castle top the pipeline list
2 days ago

Corbyn Plant Hire fleet goes under the hammer

Kit to be sold off by sister firm to collapsed groundworks contractor
2 days ago

Government wields procurement stick on late payment

New rules would block slow payers from bidding on big public jobs
5 days ago

Hercules buys power line labour firm for £15.7m

Labour supply specialist snaps up Advantage NRG to tap booming electricity upgrade market
5 days ago

Universal bid to fast-track planning for theme park

Entertainment giant eyes 2026 start at Bedford site
5 days ago

Developer Breck to transform former Ibstock brick factory

Ravenhead works to become 300-home development
5 days ago

SP Energy Networks awards contracts worth £1.4bn

First round of awards under £5.4bn national electricity grid upgrade programme
6 days ago

Travelodge to convert Liverpool Street office building

Office-to-hotel conversion in City of London
5 days ago

Plans lodged for 1m sq ft City of London office

Barbican landmark building will reuse 40% of existing structure
6 days ago

PTSG acquires roofing specialist HD Sharman Group

Premier Technical Services Group expands building maintenance division
5 days ago

Balfour Beatty lands £833m carbon capture power plant job

Work to start later this year on Teesside carbon capture gas-fired power station
6 days ago

Svella agrees deal to save Cubby Construction

Solvent purchase set to save 214 jobs and protect supply chain
6 days ago

J Coffey holds line on margins despite £52m revenue slide

Pre-tax profit down 14% but firm eyes strong pipeline to bounce back
6 days ago

Consultants called up for £2.3bn NHS SBS panel reboot

Market asked for views ahead of next-gen procurement rollout
6 days ago

Hochtief launches new UK data centre division

German business model to be introduced for UK construction
7 days ago

Construction skills body launches with 100,000 worker target

Industry to work closer with Jobcentres to find new talent
6 days ago