Watchdog MPs raise alarm over HS2 Euston station plan

Aaron Morby 2 months ago
Share

MPs on the Public Accounts Committee have lambasted the management of the HS2 project and raised grave concerns about the latest plan to deliver the Euston terminus in London.

Grand plans for Euston, but PAC questions when it will actually get built
Grand plans for Euston, but PAC questions when it will actually get built

Their report published today calls for “fundamental reset” of the project by the summer.

They warn that they remain sceptical about the Government’s ability to successfully deliver its revised programme following a litany of failures and unheeded warnings.

The report says that the HS2 programme has become a casebook example of how not to run a major project.

“It is unacceptable that over a decade into the programme we still do not know what it will cost, what the final scope will be, when it will finally be completed or what benefits it will deliver,” states their report.

Watchdog MPs also highlighted the significant challenges facing plans to build the Euston Station terminus using a third party development body.

As plans stand, HS2 will open with a terminus at Old Old Common. Despite plans to launch the TBM tunnel drive next year to Euston from Old Oak Common there are no detailed plans or timescale for delivering the Euston Terminus, warns the report.

The Government’s Euston plans currently rest on the £6bn cost being significantly underpinned by the private sector.

The PAC said it was concerned that there is no clear plan for this, and said it was sceptical the private sector would come forward to the level required.

The government confirmed that HS2 would terminate at London Euston in the Autumn 2024 budget.

However, the PAC warns the Department still does not yet have a plan for the work at Euston which includes: the HS2 station, the existing Network Rail station, the underground station, and the commercial and housing developments near the station.

“In addition, the Department intends the work to be sustantively privately funded, but it is unclear how achievable this goal is,” they warn.

Sir Geoffrey Clifton-Brown MP, Chair of the Committee, said: “Our Committee has not made recommendations in our report on delivering better outcomes for HS2’s future passengers.

“We are long past that point. It is time to deal with HS2 as what it is – a cautionary tale that should be studied by future Governments in how not to run a major project.

“We are sceptical of Government’s ability to successfully deliver even a curtailed scheme, one which we already know will on its face bring very poor value for money. The question has instead become: what possible benefit can the Government now salvage for the taxpayer, from a mess that presents real risks to the UK’s overall reputation?”

The Department for Transport’s present cost estimated set out in November 2023 is £45bn to £54bn compared with HS2 Ltd’s latest estimate of £54bn to £66bn in June 2024.

Both cost estimates are still in 2019 prices, once adjusted for inflation, the total programme costs might be close to £80bn, states the report.

 

Latest news

Comment: Gateway is acting like a barricade

Contractors left banging their heads on an (unbuilt) brick wall
16 hours ago

Final phase of £1.5bn Elephant and Castle revamp hits planning

Get Living submits revised plan for 500 homes and 450-bed student block
2 days ago

Ealing backs final phase of £1.3bn estate rebuild

Friary Park estate rebuild in Acton reaches end stage
15 hours ago

Green light for scaled-down Nottingham student tower

Glasshouse Street scheme will deliver 247 student rooms
16 hours ago

Aston Villa to revamp North Stand

Club to reuse existing structure rather than complete rebuild
1 day ago

Mace signs ex-ISG director to lead Euro health and tech push

Gary Sweeney to head up healthcare and life sciences consultancy arm
15 hours ago

Sir Robert McAlpine claws way back into profit

Firm says return to profit and strong cash balance validates new strategy
2 days ago

Severfield to cut staff by 6% amid pricing pressure

Steelwork contractor warns of extended tighter pricing due to project delays
2 days ago

JRL completes sale of 50% stake to Malaysian giant IJM

Deal boosts balance sheet and kicks starts growth plan
2 days ago

Green light for £100m Liverpool Baltic station build

Enabling highway works to start in the autumn
2 days ago

First live tests for flying construction robots

Drones can lay construction materials at height on site
2 days ago

Three firms land £170m Gentoo Sunderland housing deal

PHS Solutions, Esh and RE:GEN to deliver 10-year home upgrade plan
2 days ago

Gateway gridlock hits build-to-rent delivery as starts nosedive

Build to rent starts plunge 18% in the capital
3 days ago

Call to shift Gateway 2 checks to end building bottleneck

"The current system isn't working but we all want to see safe buildings"
3 days ago

GBN launches £600m bid race for SMR engineer roles

Owner engineers to provide technical and assurance services
3 days ago

Wates hires ex-Homes England chief to head public sector push

Robert Stone to spearhead its public sector and national frameworks strategy
3 days ago

Acheson Construction collapse costs suppliers £8.5m

One frustrated creditor seized a telehandler after contractor went into administration
3 days ago

Dominus wins go-ahead for 173-bed Glasgow scheme

Old Wynd Street job expected to cost around £25m to build
3 days ago

Safety Regulator misses deadline to clear Gateway 2 backlog

Investors pulling out of funding high rise buildings
4 days ago

CITB still sitting on £95m cash pile

Staff numbers jump from 666 to 763 as training body wage bill soars
4 days ago

£500m road surfacing framework market call

NEPO goes out to consultation on north east regional highways deal
4 days ago

Two share £220m Scottish rail repairs and minor works deal

AmcoGiffen and CPMS win civils and building repair deals
4 days ago

Builder wanted for £60m London leisure and flats job

Tower Hamlets aims to replace St George’s Leisure Centre in Shadwell
4 days ago

Contractor confirmed for business park expansion

Roe Developments to start on next phase of Castle Donington scheme
4 days ago

Driver escapes injury as scaffold collapses onto van

Major three-lift scaffold fall blocks north London high street
1 week ago

Gilbert Ash to be sold to staff

£267m turnover contractor to transition to an Employee Ownership Trust
1 week ago

M Group seals biggest-ever deal with Telent takeover

Digital infrastructure specialist deal lifts turnover to £3bn
1 week ago

Aggregates firm Ashville went down owing more than £3m

Debts revealed in Companies House update
1 week ago

Cardo saves 100 jobs at Breyer roofing arm

Private equity-backed Welsh maintenance group continues to expand
1 week ago

Excavator knocked off lorry going under bridge

Traffic Commissioner inquiry after accident in south London
1 week ago

Contractor services