Oil and gas terminal design and build specialist Petrofac has warned it is facing a massive loss on the Laggan-Tormore gas plant in the Shetland Islands.

In February, the engineering contractor revealed it had booked a loss of £154m on the Sullom Voe Oil Terminal job after agreeing final completion terms with client Total.

But bad weather conditions and its decision to ramp up manpower to rectify poor works and finish the job in the third quarter of this year will see losses soar by a further £130m.

The London Stock Exchange quoted international engineering firm blamed the extent of its losses on having to take on direct construction risk after it claimed subcontractors failed to deliver to standard on the job.

Ayman Asfari, Petrofac’s Group Chief Executive, said: “We had to take on this level of direct construction responsibility when some of our subcontractors failed to deliver in line with their agreed scopes.

“Our lack of experience of operating a direct construction model in a wholly new geography for our onshore engineering and construction business, particularly in a location where labour costs are much higher and productivity much lower than we are used to, has cost us dearly.

“We have already affirmed that we will no longer take construction risk on large lump-sum projects within the UK to avoid a similar experience to Laggan-Tormore moving forward.”

cs-laggan-tormore-3

Morrison Construction was managing the building and civil engineering works for the new Laggan Tormore gas plant under a £110m contract.

Balfour Beatty Engineering Services has been one the engineering construction subcontractors.

The project has involved over 3,500 separate reinforced concrete foundations, offices, workshops, warehouses and 33 other industrial buildings and 4km of roads as well as excavation and backfilling for 1,000km of cables and 30km of pipes up to 6m deep in Shetland granite.

French oil company Total awarded Petrofac an £500m lump-sum engineering, procure and construct contract to develop the new Shetland gas plant back in October 2010.

When Petrofac announced results for 2014 it booked the £154m loss in an attempt to draw a line under the troubled project assuring shareholder that there would be no further losses on the project over the remainder of the contract.

During late March and early April, activity on the Laggan-Tormore site was ramped up substantially as it shifted into the final construction and commissioning phases of the project.

Continued adverse weather conditions during March on Shetland and industrial action delayed this mobilisation by almost a month.

It said that as the activity levels have increased, it became apparent that significantly more man-hours were needed to complete the project as a result of low manpower productivity levels as the project nears completion and a greater level of rectification and reinstatement work than expected from the failure of one of its subcontractors to deliver in line with their agreed scope.

Latest news

Green light for £250m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
55 minutes ago

Four jailed after Keltbray corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
11 hours ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
13 minutes ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
12 minutes ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
7 minutes ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
16 minutes ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
8 hours ago

Bowmer & Kirkland boosts margins as profits surge to £69m

Revenue nudges up towards £1.3bn in year of expansion
1 day ago

Offshore construction starts on £4bn windfarm

Foundations for first of 95 turbines installed: Watch video
24 hours ago

AECOM buys civils consultant Allen Gordon

Global giant acquires Scottish water and energy specialist
23 hours ago

Plans in for £1bn Northern Gateway site in Manchester

Plan for 500-acre manufacturing and logistic park advance
23 hours ago

RED wins £31m London Shoreditch student digs job

Two extra floors will be added to Willen House scheme
1 day ago

Deconstruct handed £12m Grenfell demolition

Firm maintaining building awarded job without bid race to speed process
1 day ago

Sizewell site workers get made to measure PPE

Bespoke fitting service on offer at new Bryson branch
1 day ago

Comment: Gateway is acting like a barricade

Contractors left banging their heads on an (unbuilt) brick wall
4 days ago

Final phase of £1.5bn Elephant and Castle revamp hits planning

Get Living submits revised plan for 500 homes and 450-bed student block
5 days ago

Ealing backs final phase of £1.3bn estate rebuild

Friary Park estate rebuild in Acton reaches end stage
4 days ago

Green light for scaled-down Nottingham student tower

Glasshouse Street scheme will deliver 247 student rooms
4 days ago

Aston Villa to revamp North Stand

Club to reuse existing structure rather than complete rebuild
5 days ago

Mace signs ex-ISG director to lead Euro health and tech push

Gary Sweeney to head up healthcare and life sciences consultancy arm
4 days ago

Sir Robert McAlpine claws way back into profit

Firm says return to profit and strong cash balance validates new strategy
5 days ago

Severfield to cut staff by 6% amid pricing pressure

Steelwork contractor warns of extended tighter pricing due to project delays
5 days ago

JRL completes sale of 50% stake to Malaysian giant IJM

Deal boosts balance sheet and kicks starts growth plan
5 days ago

Green light for £100m Liverpool Baltic station build

Enabling highway works to start in the autumn
6 days ago

First live tests for flying construction robots

Drones can lay construction materials at height on site
5 days ago

Three firms land £170m Gentoo Sunderland housing deal

PHS Solutions, Esh and RE:GEN to deliver 10-year home upgrade plan
6 days ago

Gateway gridlock hits build-to-rent delivery as starts nosedive

Build to rent starts plunge 18% in the capital
6 days ago

Call to shift Gateway 2 checks to end building bottleneck

"The current system isn't working but we all want to see safe buildings"
6 days ago

GBN launches £600m bid race for SMR engineer roles

Owner engineers to provide technical and assurance services
6 days ago

Wates hires ex-Homes England chief to head public sector push

Robert Stone to spearhead its public sector and national frameworks strategy
6 days ago

Contractor services