Brookfield Multiplex in the City’s tallest tower team

Aaron Morby 10 years ago
Share

Plans have been lodged with the Corporation of London for the Square Mile’s tallest tower at 22 Bishopsgate.

The 1.3m sq ft skyscraper will replace the ditched Pinnacle scheme and fill an obvious gap at the centre of the City’s cluster of tall buildings.

Contractor Brookfield Multiplex is part of the client consultant team for the 62-floor building and submitted the construction plan for the £500m construction job.

Under the submitted programme concrete core work will resume in March next year after the existing core stump has been removed.

Work stopped in 2012 on the previous Pinnacle building scheme with only the foundations, basements and the lift core up to level nine having been completed.

Of the existing structure, the foundations and basements will be retained, helping minimise the disruption from the new proposal, although new piles will be drilled to support the new building layout.

Construction will involve an off-site consolidated delivery centre to minimise vehicle movements to the site – reducing pollution, improving security and diminishing the number of cyclist accidents with HGVs.

Supplies to and waste from the building will be delivered to a consolidation centre outside central London and energy efficient vehicles will then make far fewer deliveries to the site outside peak pedestrian movement and rush hour times.

22 Bishopsgate

View of City’s future skyline topped out with 22 Bishopsgate skyscraper and several new towers now under construction.

Developers AXA Real Estate and Lipton Rogers are behind the plans drawn up by architect PLP for the 278m building – 10m lower than the previously approved consent.

Consultant team on 22 Bishopsgate

Access: Peter Connell Associates
Architect: PLP Architecture
CDM: PLP Architecture
Construction advice: Brookfield Multiplex
Cost Management, Areas, BBD: Alinea
District Surveyor: City of London
Employer’s Representative/ Employer’s Agent: Aecom
Façade Access and Maintenance: WSP Parsons Brinckerhoff
Façade Engineers: Emmer Pfenninger Partners AG
Façade Advice: Josef Gartner
Fire: WSP Parsons Brinckerhoff
Logistics: Wilson James
MEP: WSP Parsons Brinckerhoff
Structure: WSP Parsons Brinckerhoff
Sustainability: WSP Parsons Brinckerhoff
Transport: WSP Parsons Brinckerhoff
Vertical Transportation: VT Studio
Well (Delos): Arup

At the top of the building will be a double-height public viewing gallery, which will have dedicated lifts, be free to the public and sit alongside a two-storey public restaurant and bar.

22 Bishopsgate

The plans include spaces for meeting and collaboration, as well as a range of cafés, food outlets and a conference centre, complimented with amenities such as a medical centre, library, a wellness suite, and specialised sports facilities.

It will be the first building in London to adopt the new Delos WELL Building Standard.  The Delos standard is the world’s first building standard focused exclusively on human health and wellness and assesses people using the building to measure, certify and monitor features that impact health and wellbeing.

In addition to its exceptional accessibility by public transport, 22 Bishopsgate, will achieve a BREEAM Excellent sustainability certification and a 25% carbon saving compared to the previous scheme, partly due to the triple glazed ultra-efficient façade.

Latest project news

Plans in for nearly 900 homes at Manchester Mayfield

First homes at £1.4bn regeneration site will be built over four blocks
1 month ago

Pellikaan wins £25m Wiltshire leisure centre job

Work to start next month on Trowbridge swimming pool and gym
1 month ago

Lendlease OK’d to start Birmingham’s £1.9bn Smithfield scheme

First phase of 400 build to rent homes at Manor Square approved
1 month ago

Fresh plan for £170m Newcastle resi tower and hotel

Gainford Group scales down New Bridge Street scheme to 29 storeys
1 month ago

Mace confirmed for £140m Gatwick Airport Pier 6 extension

Contractor PJ Hegarty has started enabling works in middle of busy airport
1 month ago

Graham takes on ISG £45m Coventry cultural hub job

Firm will start conversion work in the Spring on former IKEA store
1 month ago

JRL Malaysian backers plan £150m London city office refurb

Ardmore set to deliver landmark 25 Finsbury Circus building overhaul
1 month ago

500-home block to replace 19 storey Sutton office tower

Landmark project to deliver 312 Build to rent and 195 co-living homes
1 month ago

Man Utd confirm plan for £2bn ‘super-tent’ stadium

Club to press ahead with 100,000-seat 'Wembley of the North'
1 month ago

Morgan Sindall wins £61m Liverpool lab scheme

Construction to start this Autumn on latest Knowledge Quarter project
1 month ago

Glencar to build timber-framed office block

Work to start next month on 79,200 sq ft scheme in Maidenhead
1 month ago

Birmingham council submits £1bn Druids Heath plan

High rise estate to be replaced by-3,500 home eco village
2 months ago

McLaren go-ahead for 314 flats Watford scheme

Police station and magistrates court to be demolished
2 months ago

Mace to transform Imperial College Great Hall

Work to start next month on ambitious refit
2 months ago

£100m plan to regenerate former Digbeth ironworks

Hartwell unveils 260,000 sq ft office and 240 homs plan
2 months ago

Legendre UK wins £21m London homes job for Clarion

Tower Hamlets building to be replaced due to building and fire safety issues
2 months ago

£230m Southampton waterfront scheme approved

Town Quay includes trio of 25 storey towers around new marina
2 months ago

Planning green light for £10bn Northumberland data centre

Blackstone-backed project will create 1,200 construction jobs
2 months ago

Green light for 1,000-home Wolverhampton city centre regen

Phase one of ECF Smithgate scheme to start this year
2 months ago

Regal submits plan to revive stalled London resi tower

Swiss Cottage project redesigned with second staircase and 237 flats
2 months ago

Muse signs up to £3.2bn Solihull health campus district

Ambitious Arden Cross scheme next to HS2 Interchange advances
2 months ago

Watkin Jones wins over £50m student digs campus upgrade

Work to start next month on phase 714-bed south London campus
2 months ago

Costain start date for £67m Romford flyover replacement

Work to start this summer on Gallows Corner bridge rebuild
2 months ago

Work starts on tyres to jet fuel recycling plant

£100m Sunderland plant will produce around 30,000t of liquid fuel
2 months ago

Funding deal for £237m Tide Construction student tower

48-storey project will be first major student scheme on Canary Wharf
2 months ago

McLaren wins £29m south east London industrial job

Crayford urban logistics hub starts construction
2 months ago

Green light for £100m A47 road junction upgrade

Long-awaited A47/A11 Thickthorn junction will support over 40,000 homes
2 months ago

Sisk starts remediation work for 1,600-home Birkenhead scheme

Wirral council has secured £52m for Hind Street Urban Village infrastructure
2 months ago

Plans unveiled for 50-storey plus Liverpool tower

Planning submission later this year for £1bn King Edward project
2 months ago

Galliford Try wins £45m high security prison fire safety retrofit

HMP Wakefield provides upgrade challenges in secure environments
2 months ago

Contractor services