Balfour’s £127m Midland Metro opening delayed again

Aaron Morby 9 years ago
Share

The planned opening of Midland Metro services to Birmingham’s New Street station has been delayed again – this time for essential track realignment works.

A Midland Metro tram undergoing testing arrives at New Street station
A Midland Metro tram undergoing testing arrives at New Street station

The latest delay follows extensive safety checks by Centro, the delivery arm of the West Midlands Integrated Transport Authority, on the eve of the planned opening.

Centro’s Midland Metro programme director Phil Hewitt said: “It is bitterly disappointing as everything else is in place and ready to go but, as we have said right from the start, safety is paramount.

“A stringent testing programme has identified minor anomalies in some of the track alignment which need to be addressed.

“These are exactly the sort of issues the tests were designed to identify.

“However remedial work is relatively straightforward. Once that is complete, on-street driver training can begin and we will soon have passenger services running.”

Balfour Beatty won the £127m contract to deliver the 1.2km extension from Snow Hill to New Street back in August 2013 .

At the time the 1.2km Midland Metro extension through Birmingham city centre was programmed to finish late last year.

This had to be put back to May due to technical issues caused by difficulties associated with existing utilites during construction.

Trams returned to the streets of Birmingham for the first time in more than 60 years last December when the Metro started running to the new stop in Bull Street.

Latest news

Planning Bill to have “seismic” impact on construction

Building-boosting reforms go before Parliament
15 hours ago

Man Utd confirm plan for £2bn ‘super-tent’ stadium

Club to press ahead with 100,000-seat 'Wembley of the North'
18 hours ago

Government spending keeps profits edging-up at Kier

91% of work now with public sector and regulated companies
21 hours ago

Costain on track for step change to 5% margin

Alex Vaughan says order book has jumped £1.5bn to £5.4bn
20 hours ago

Mace tops February contracts league

Confirmation of £300m London Victoria Street project lifts firm to pole position
20 hours ago

Wates raids Laing O’Rourke for new construction operations chief

George Mosey leaves Laing O'Rourke after 16 years
1 day ago

Travis Perkins CEO Pete Redfern steps down due to ill health

Redfern joined builders' merchant last year after 14 years at Taylor Wimpey
2 days ago

Morgan Sindall wins £61m Liverpool lab scheme

Construction to start this Autumn on latest Knowledge Quarter project
21 hours ago

Glencar to build timber-framed office block

Work to start next month on 79,200 sq ft scheme in Maidenhead
2 days ago

Shed specialist Marbank files administration notice

£67m turnover portal-framed building specialist files court notice
2 days ago

Birmingham council submits £1bn Druids Heath plan

High rise estate to be replaced by-3,500 home eco village
2 days ago

Cannabis farm gang posed as utilities contractor

Gang jailed for 28 years after diverting power to more than 100 cannabis farms
4 days ago

Firm fined after workers climb scaffold without ladder

HSE investigation prompted by death on Liverpool site
2 days ago

Clancy renews £250m Southern Water deal

Contractor vows to maximise value for money and minimise disruption
2 days ago

McLaren go-ahead for 314 flats Watford scheme

Police station and magistrates court to be demolished
2 days ago

Former Liverpool mayor charged in building contracts probe

Construction bosses also charged as part of Operation Aloft
5 days ago

Bidding to start for £700m Irish sea interconnector work

Work includes converter stations at Hunterston and Kilroot near Belfast
5 days ago

Muse to redevelop Durham County Hall HQ site

Morgan Sindall regen specialist seals another major development deal
5 days ago

Mace to transform Imperial College Great Hall

Work to start next month on ambitious refit
5 days ago

£100m plan to regenerate former Digbeth ironworks

Hartwell unveils 260,000 sq ft office and 240 homs plan
5 days ago

Legendre UK wins £21m London homes job for Clarion

Tower Hamlets building to be replaced due to building and fire safety issues
5 days ago

Construction buyers report fastest downturn since 2020

Double whammy of decreasing new orders and delayed projects
6 days ago

Bidders day for £15bn schools alliance framework

Online event to set out details of DfE alliancing framework procurement plan
6 days ago

MPs told safety regulator delays forcing industry job cuts

Industry chief warns housing select committee that BSR is now a main block on meeting housing targets
6 days ago

£600m delivery partner named for new hospital programme

Mace/T&T JV named programme delivery partner for £37bn new hospital plan
6 days ago

£230m Southampton waterfront scheme approved

Town Quay includes trio of 25 storey towers around new marina
6 days ago

Planning green light for £10bn Northumberland data centre

Blackstone-backed project will create 1,200 construction jobs
7 days ago

Bauhaus block above Southwark Station gets green light

Student accommodation and affordable housing scheme replaces original office plan
6 days ago

Police arrest plant hire fraud gang

Nine arrests after kit hired "with no intent of ever returning the machines"
7 days ago

Balfour Beatty boss Leo Quinn to step down

Group Chief Executive to be replaced by consultant AtkinsRéalis chief Philip Hoare
7 days ago

Contractor services