Queensferry Crossing to open five months late

Aaron Morby 8 years ago
Share

The Scottish Government has admitted the £1.4bn Queensferry Crossing will now open in May 2017 – five months later than planned.

Forth Crossing Bridge Constructors, the consortium building the bridge, has told ministers that ongoing effects of weather on construction mean it will require more time to complete the bridge.

The joint venture of Dragados, Hochtief, American Bridge International and Morrison Construction said the new opening deadline remained challenging but achievable.

Since last September the downtime due to strong winds has been 40% compared to the 25% anticipated by the contractor.

Until May, the bridge builders thought they could make up lost time.  But in April and May an unprecedented 13 days and 12 days were lost to bad weather scuppering plans to deliver the December 2016 target.

FCBC has taken on an extra 100 workers, increased working hours, altered construction methodologies where possible and challenged critical construction sequences to identify where any programme efficiencies could be found.

But the contractors are now warning they have now reached the stage where further extra resources will not bring the delivery date forward due to the complex technical nature of the construction work.

Screen Shot 2016-06-08 at 17.23.32

Specifically the bridge deck and the cable installation process, which began in September 2015, is particularly sensitive to wind and this increases as the cables used become longer and are installed at a greater height .

FCBC have confirmed this creates an unavoidable knock-on effect for subsequent activities, road surfacing and wind barriers which will now take place in wet and cold conditions during autumn and winter 2016/2017.

The builders contract runs until June 2017, meaning the project will still technically be on time even though completion was brought forward to December this year.

Cabinet Secretary for Economy, Jobs and Fair Work Keith Brown said: “We will continue to work closely with the contractors and I will personally ensure that every pressure and every resource is brought to bear to deliver or even better the revised target date of May 2017

“Going forward, in order to ensure that this project remains on track, I have implemented enhanced governance procedures from Transport Scotland senior management and will receive twice weekly updates from the project team.

“We have always been ambitious about this project and have always worked towards a deliberately ambitious target. However, It is important to recognise that FCBC still fully expects the project to complete within the timeframe of their contract. This project is not late and there will be no impact on the public purse.”

“The December 2016 target date was set to address concerns about the long term condition of the Forth Road bridge where it was originally believed that it would be restricted as early as 2017.

“These concerns have proven to be less immediate and the recently installed structural health monitoring system is providing assurance on the ability of the FRB to sustain traffic.”

Latest news

Over £600m awarded for decarbonisation projects – full lists

Over 240 public building energy upgrade projects secure cash
7 hours ago

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
17 hours ago

Enabling works to start on £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
17 hours ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
17 hours ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
16 hours ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
17 hours ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
17 hours ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
16 hours ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
1 day ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
2 days ago

House builder Camstead goes into administration

Work stopped on three current sites
2 days ago

Death of piling legend Roger Bullivant

Industry innovator dies after long illness aged 85
2 days ago

ESS Modular went down owing suppliers £7m

Modular specialist owned by ISG owner Cathexis
2 days ago

Builders back farmers in inheritance tax protest

"A rethink is desperately needed" say National Federation of Builders
2 days ago

Willmott Dixon wins £36m leisure centre upgrade

Work to start on historic Westminster 1930s Grade II listed Seymour Centre
2 days ago

Graham wins £100m Cardiff Crossrail phase 1

Work on route to Cardiff Bay to start before end of next year
3 days ago

Laing O’Rourke appoints new European MD

Peter Lyons to take-up new role in February
3 days ago

Profits dip at Stepnell ahead of demerger

Turnover and secured workloads up ahead of restructure
3 days ago

HS2 green bridge deck takes shape

100m-wide wildlife bridge to carry hedgerows and country lane over HS2
3 days ago

1,000-home Wolverhampton city centre scheme in for planning

ECF and council advance City Centre West build to rent scheme
3 days ago

Sisk clinches £54m North London council HQ revamp

Haringey's iconic Grade II listed civic centre to be brought back into use
3 days ago

Ofgem approves £2.5bn Eastern Green Link 1

Work to start next Spring on cable project from Scotland to the north of England
4 days ago

Anglian Water hunts for £1bn delivery partner

Programme delivery partner wil integrate with client team over 15-year plan
4 days ago

Hadden collapse costs supply chain £6.7m

"Highly unlikely" subcontractors will receive anything for their unpaid invoices
4 days ago

Management buyout at M&E specialist

£25m turnover Kimpton in second MBO in its 60-year history
4 days ago

BAM finalises £71m deal to replace first major RAAC school

Work to start on new St Leonards Catholic School in Durham
4 days ago

Scaffolder hit by two tonne weight at nuclear plant

Court hands out £633,000 in fines after Dungeness B decommissioning incident
4 days ago

Go-ahead for 860,000 sq ft East London medical campus

Whitechapel Road scheme of six new and repurposed buildings
4 days ago

Site labour rates hit record high as cost inflation returns

Industry's biggest payroll firm says rates rose nearly 5% last month in London
7 days ago

Morris & Spottiswood acquires part of ISG fit-out division

ISG Cathedral acquisition saves 111 jobs and expands presence across England
1 week ago

Contractor services