Stretch of Aberdeen bypass delayed almost a year

Aaron Morby 8 years ago
Share

A crucial section of the Aberdeen by-pass could be delayed by as much as a year because contractors have failed to finish earthworks before a winter weather shutdown in Scotland.

Tipperty section of the project
Tipperty section of the project

A consortium of Balfour Beatty, Carillion and Galliford Try are working on the £550m stretch of route between Balmedie-Tipperty on the vast Aberdeen Western Peripheral Route project.

This 12km route was due to be completed by the spring. But failure to complete key earthworks before a poor weather shutdown has pushed the expected completion date back to Winter 2017/18, Scottish economy secretary Keith Brown has admitted.

This section, which will see the existing A90 road upgraded to a dual carriageway, will be linked to the northern leg of the AWPR at Blackdog.

The delay was revealed in an update ahead of the meeting of the Scottish parliament’s rural economy and connectivity committee tomorrow.

Brown wrote that the contractors formally advised Transport Scotland last month that they were no longer planning or able to open the Balmedie-Tipperty section in spring 2017.

“The contractor confirmed that it had not completed key earthworks prior to the current winter period, resulting in a consequential impact on the programme for that section.”

He added: “Continuing those earthworks throughout the winter period may give rise to certain environmental risks connected with the control of run-off from the site and issues around the protection of weather susceptible materials.

“We have been working closely with the contractor and all relevant agencies to monitor the environmental effects of the construction works.”

Brown added that Transport Scotland’s technical advisors have also conducted a full independent programme review and challenged the builders to ensure that they were mitigating the environmental effects where possible.

“Having considered the outstanding earthworks, the onset of the winter periods and the risks referred to above, the contractor has revised its programme for the Balmedie to Tipperty section of the project from spring 2017 to winter 2017/18.”

The set back comes after phase 1 of the Northern Leg of the project at Aberdeen Airport opened in August this year, ahead of the contractor’s planned autumn target.

Latest news

Wates wins fit-out for Manchester First Street Hub

Smartspace arm secures another Government hub deal
18 hours ago

Big trade names dropped in M Group rebrand

Acquisitive group formed from Morrison Utility services in 2016
16 hours ago

Breyer Group files administration notice

Staff hope rival firm could buy assets and save jobs
20 hours ago

Peel Ports reveals winners for £750m framework

18 firms win places on deal: Full list
18 hours ago

Former Severfield director takes helm at Embrace Steel

New CEO Martin Kelly aims to step up expansion of steelwork contractor
21 hours ago

£302m upgrade funding awarded to FE colleges – list

Cash shared out between England’s 179 college groups
20 hours ago

FK Facades thrives but construction arm hit by ISG row

Dispute with failed contractor costs specialist £5.5m
21 hours ago

Galliford Try gets go-ahead for Milton Keynes PRS tower

33-storey tower needs gateway 2 approval before work can start
2 days ago

Small house builders get £150m funding for green homes

Developers will have to meet-up to ten new criteria to benefit from interest rate discounts
21 hours ago

Lendlease Construction renamed Bovis

US private equity firm completes £35m purchase of UK contracting business and rebrands
2 days ago

Breyer Group battles for survival as rivals circle

Housing maintenance firm fights three winding up petitions in a month
2 days ago

Careys facing £2.4m claim by developer over demolition cartel

Giant Hong Kong developer claims it was overcharged on Lots Road Power Station job
2 days ago

Multiplex profit drops a third as revenue rises to £780m

Spate of new orders sets contractor up for three years of work
2 days ago

Galliford Try and Breheny land latest Sizewell C road deals

More infrastructure deals for new nuclear power station
3 days ago

Worker trapped in collapsed septic tank pit

Contractor and director fined after worker suffers multiple fractures
2 days ago

Homes England buys stalled Broad Marsh site

Demolition to finally be completed as developer hunt begins
2 days ago

Vistry go-ahead for 353 homes at Rochester Riverside

Work to start on next phase of Kent town regeneration at end of this year
3 days ago

M&E firm J S Wright collapsed owing £19m

Trade creditors hit for £11.4m by employee-owned Midlands firm
3 days ago

Right to work checks to be extended to self-employed

Government plans crackdown on illegal working and rogue employers
3 days ago

Midlands developer turns to London with £1bn resi schemes trio

SevenCapital plans 1,000 flats in Kensington, Islington and the Isle of Dogs projects
3 days ago

Deck falls off huge scissor lift at Winvic site

Two men seriously injured as platform plunges to the ground
5 days ago

Weston targets Build to Rent with new division

Weston Partnerships signs first deals with asset managers and councils
3 days ago

Bouygues seals deal for £119m Cardiff college campus

Construction to start in June on two new buildings
6 days ago

£140m cash injection to speed-up flood defence schemes

Funding part of £2.65bn investment over the next two years
3 days ago

Bid race starts for £15bn schools framework refresh

DfE throws framework open to more contractors
6 days ago

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
6 days ago

London Mayor calls in blocked 600-bed student scheme

Refused 20-storey London PBSA block may still be built
6 days ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
6 days ago

Arrest after pedestrian death on construction site

Tragedy during site preparation works for new Wigan car park
6 days ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
7 days ago

Contractor services