Interserve waste project black hole deepens to £160m

Aaron Morby 8 years ago
Share

Interserve this morning revealed the cost of exiting its troubled energy from waste projects has soared from £70m to £160m.

Interserve is presently looking for a new chief executive to replace Adrian Ringrose who is stepping down
Interserve is presently looking for a new chief executive to replace Adrian Ringrose who is stepping down

Most of the revised hit comes from the Glasgow Recycling & Renewable Energy project, where its contract was terminated in November after project delays.

The cash outflow from problem energy from waste projects has sent Interserve’s average net debt into a spiral.

This has soared from the previously reported £280m to £390m in 2016 and is expected to climb to £450m this year.

The latest revelation of deeper problems at the waste division come as the board searches for a new chief executive.

Interserve announced existing chief executive Adrian Ringrose was leaving to pursue the next phase of his career at the end of 2016.

Ringrose will continue at the helm until his replacement is found.

In a statement this morning, Interserve said that it had further considered the implications of the Glasgow scheme with its legal advisers and the expected lengthy period of litigation.

“Alongside this exercise we have continued to undertake a detailed review of operational developments on the other contracts in our exited EfW business, including the impact of the entering into administration by our principal gasification subcontractor, Energos, together with the likelihood and timing of potential recoveries and claims from third parties.

“In the light of these developments and of the continuing uncertainties in relation to the final conclusion of our EfW contracts, the board has concluded that the exceptional provision of £70m announced in May 2016 is no longer adequate to reflect the incurred and anticipated losses associated with this business. 

“Consequently the board has determined that it is appropriate to increase the exceptional provision for exiting this market and the associated contracts to £160m.”  

Interserve expects to complete substantially the construction and commissioning of the projects during 2017, but contractual obligations regarding warranties, and resolving claims would drag on.

The firm added that that it remained focussed on managing the challenges of exiting energy from waste projects and pursuing claims from third parties.

Interserve said it had negotiated new banking facilities with existing and new lenders for an additional £66m.

This gave Interserve a total secured, committed debt facility of £573m, which the board considered adequate to meet existing and future commitments.

Latest news

Winners revealed for £5.4bn electricity grid upgrade

SP Energy Networks unveils 19 winners - full list
1 day ago

Malaysian property giant to buy 50% stake in JRL

IJM Land to buy into diversified £800m turnover south east contractor
2 days ago

Fast-track skills hubs to train 5,000 extra apprentices

Plan for network of 32 skills hubs to rain construction apprentices in half the time
1 day ago

Luxury house builder files administration notice

£31m turnover Octagon Developments Ltd lodges court notice
2 days ago

Morgan Sindall takes on £22m stalled ISG Cardiff school job

Workplan is being drawn up ahead of restart on Penarth school
2 days ago

Walker Modular wins bathroom pod deal on student tower

Sealant-free construction method helps supplier dominate student market
2 days ago

Over £600m awarded for decarbonisation projects – full lists

Over 240 public building energy upgrade projects secure cash
2 days ago

Enabling works to start on £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
3 days ago

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
3 days ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
3 days ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
3 days ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
3 days ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
3 days ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
3 days ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
3 days ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
4 days ago

House builder Camstead goes into administration

Work stopped on three current sites
4 days ago

Death of piling legend Roger Bullivant

Industry innovator dies after long illness aged 85
4 days ago

ESS Modular went down owing suppliers £7m

Modular specialist owned by ISG owner Cathexis
4 days ago

Builders back farmers in inheritance tax protest

"A rethink is desperately needed" say National Federation of Builders
4 days ago

Willmott Dixon wins £36m leisure centre upgrade

Work to start on historic Westminster 1930s Grade II listed Seymour Centre
4 days ago

Graham wins £100m Cardiff Crossrail phase 1

Work on route to Cardiff Bay to start before end of next year
5 days ago

Laing O’Rourke appoints new European MD

Peter Lyons to take-up new role in February
5 days ago

Profits dip at Stepnell ahead of demerger

Turnover and secured workloads up ahead of restructure
5 days ago

HS2 green bridge deck takes shape

100m-wide wildlife bridge to carry hedgerows and country lane over HS2
5 days ago

1,000-home Wolverhampton city centre scheme in for planning

ECF and council advance City Centre West build to rent scheme
5 days ago

Sisk clinches £54m North London council HQ revamp

Haringey's iconic Grade II listed civic centre to be brought back into use
6 days ago

Ofgem approves £2.5bn Eastern Green Link 1

Work to start next Spring on cable project from Scotland to the north of England
6 days ago

Anglian Water hunts for £1bn delivery partner

Programme delivery partner wil integrate with client team over 15-year plan
6 days ago

Hadden collapse costs supply chain £6.7m

"Highly unlikely" subcontractors will receive anything for their unpaid invoices
6 days ago

Contractor services