Network Rail warned over management of future projects

Aaron Morby 8 years ago
Share

The Government’s spending watchdog is raising grave concerns about Network Rail’s ability to manage future projects after ‘appalling wastes of money’ on the Great Western Railway track upgrade.

A new report published this morning by the Public Accounts Committee blasts Network Rail and the Government for significant failings in the design, planning and cost-estimating of the programme.

These have cast doubt about Network Rail’s management of future projects.

Network Rail’s estimated cost of the Great Western Railway track upgrade rose by £1.2bn to £2.8bn in the space of a year.

The report doubts whether this project can even now be delivered to the revised target and budget.

The spending watchdog has now called for an urgent review  — not just on the different sections of the Great Western route, but also on the Midland Main Line and TransPennine electrification routes.

The committee is demanding that Network Rail improve its ability to produce realistic cost estimates and make sure that robust and detailed plans are in place for infrastructure projects before starting construction.

Meg Hillier MP, Chair of the PAC, said: “Mismanagement of the Great Western programme has hit taxpayers hard and left many people angry and frustrated.

“This is a stark example of how not to run a major project, from flawed planning at the earliest stage to weak accountability and what remain serious questions about the reasons for embarking on the work in the first place.

“The sums of public money wasted are appalling—not least the £330 million additional costs the Department for Transport will have to pay to keep the trains running because of delays to electrification.”

She added that the Department for Transport failed to adequately challenge Network Rail’s plans to carry out the infrastructure work and questioned whether electrification work on this and other lines was even necessary.

“Government accepts it got this project badly wrong and must now demonstrate it has learned the lessons.

“Network Rail admits there are still very significant risks in the Great Western scheme and it is vital these are fully identified and carefully managed.

“It must work with the Department to ensure this information is properly factored into the whole rail modernisation programme.

“For its part, the Department should urgently review its plans for electrification—not just on the different sections of the Great Western route, but also on the Midland Main Line and TransPennine routes.”

Latest news

Demolition giant John F Hunt Group sold to staff

Chairman John Hall to remain at helm
17 hours ago

University of Warwick advances £700m campus plan

Enabling works to get underway for main build works next year
22 hours ago

Go-ahead for £750m East London data centre

Urban 11-storey data centre to be built next to River Lea and A13 in Newham
1 day ago

Keltbray Infrastructure Services buys Linbrooke rail arm

First deal since infrastructure business was bought by private equity this summer
2 days ago

Elizabeth Line wins Stirling Prize for architecture

Infrastructure scheme wins premier design prize
22 hours ago

Winners named for Worcestershire and West Mids framework

Deal covers development work from design to construction
21 hours ago

Piling starts on HS2 Curzon Street Station

Mace Dragados Joint Venture and Keltbray working on Birmingham site
22 hours ago

M Group joins top seven as revenue jumps to £2.2bn

Infrastructure services specialist continues to hunt acquisitions
2 days ago

BlackRock to take control of Lanes Group

Takeover of leading water contractor to complete this month
2 days ago

Yorkshire and Lincolnshire builders’ merchant goes under

1928-founded Builders Merchant Company hit by winding up petition
2 days ago

Trio wins £170m West Country new build housing deal

Curo Enterprise, E.G. Carter and Speller Metcalfe Malvern
2 days ago

Roofer dies in fall from potato box on forklift

Court hears how victim fell 16ft from makeshift platform
2 days ago

Clancy bolsters senior management team

Skanska project director Jon Arnold joins as operations director of energy
2 days ago

High tech construction plant could save country £417bn

Costain report says kit which connects and drives itself will provide a massive economic boost
3 days ago

Concrete frame defects cost Bellway another £14m

Cost of repairing Greenwich scheme rises while £5.4m was spent on aborted Crest Nicholson chase
3 days ago

Green light for 52-storey Isle of Dogs resi tower

460 flats One East Point project will be built at 3-4 Harbour Exchange
3 days ago

Contractors urged to “hire now” as labour supply crunch looms

Vacancies rise and wages grow as fight for new workers intensifies
3 days ago

Kier confirmed for £20m Yasa Motors Bicester HQ

Developer Bicester Motion advances future mobility business park
4 days ago

Data centres and airport expansion to spur growth

Government hails £25bn data centre and £1.1bn Stansted Airport expansion plan
4 days ago

Hinkley Point second reactor unit build up to 30% faster

Engineering team lifts last giant steel ring onto reactor 2 yesterday
3 days ago

BAM reassures supply chain after winding-up petition

Firm's credit rating temporarily affected after dispute with supplier
4 days ago

Winvic secures Leeds build to rent scheme

Phase one of £500m Sweet Street South Bank regeneration starts
4 days ago

£60m turnover construction group sold to staff

Meldrum Construction Services Group becomes Employee Owned Trust
4 days ago

Starmer vows to “rip out” obstacles to investment

Prime Minister to make pledge at inaugural International Investment Summit
4 days ago

VolkerFitzpatrick starts prep-work for £210m M3 junction upgrade

Main works to begin in early 2025 on Winchester junction job
4 days ago

London super sewer turned on after eight years of construction

£4.5bn project starts protecting River Thames from pollution
4 days ago

Housing and office new work jump fuels output recovery

August new construction work rebounds 1.6% after early summer fall
7 days ago

£300m London City fringe office tower approved

Rocket's 27-storey One Fairchild Street job set for take-off
1 week ago

Consultants named for London Tube Bakerloo Line extension

Aecom and architect WW+P to work up designs for four new stations
7 days ago

15 giant bridge beams lifted into place at HS2 station

Balfour Beatty VINCI carries-out civils work for Solihull station: Video
1 week ago

Contractor services