Bad weather delays opening of Queensferry Crossing

Grant Prior 8 years ago
Share

Contractors building the new £790m Queensferry Crossing have confirmed they need more time to complete the project.

Bad weather has hampered the final stages of the scheme
Bad weather has hampered the final stages of the scheme

Bad weather and windy conditions have hampered work by the Forth Road Crossing Bridge Constructors – who consist of Hochtief, American Bridge, Dragados and Galliford Try.

Economy Secretary Keith Brown confirmed the expected opening date will be achieved in a window between mid-July and the end of August – approximately 4 to 10 weeks later than predicted on a six year construction programme.

The contractor has reported there have been fewer clear weather windows than expected, particularly in relation to wind.

This has delayed weather dependent activities causing them to bunch together at the end of the programme to a much greater degree than was anticipated in May 2016.

This means that a lot of construction activity is underway simultaneously and careful planning is required to ensure that this can be done safely, so that one activity does not impact on another.

At this stage of the project all remaining activities are vulnerable to weather conditions.

The tower cranes can only be removed in wind speeds of less than 25 mph and when this is happening, it is not possible to safely work within a 50 metre radius of the crane itself.

Work on cable stays is sensitive to wind, waterproofing the bridge deck is sensitive to rain and road surfacing is sensitive to both rain and low temperatures.

Brown said: “Today there are only nine weeks remaining to the end of May and the review has concluded that even with the best weather this date is not now safely achievable.

“I fully recognise the effort of the workforce in building this amazing new bridge. Over 13 million hours have gone into building the Queensferry Crossing over the past six years.

“There is no additional cost to the public purse and the Forth Road Bridge continues to carry traffic over the Forth during these final weeks of construction.

“While its clearly very disappointing the new bridge won’t be ready ahead of the contractual completion date, I believe it is important to take the time to make sure the bridge is built in the safest possible circumstances to the highest possible standards.”

Sally Cox, chair of the Board for the Forth Road Crossing Bridge Constructors said: “FCBC acknowledge that the uniqueness of this project and the onerous weather conditions it has experienced, particularly working at height crossing the Forth have created more challenges than we anticipated.

“FCBC have always been and remain ambitious about completing this challenging project at the earliest possible date and share Transport Scotland and the public’s frustration over this delay.

“We have assured Transport Scotland that every endeavour is and will continue to be made, to safely complete the project at the earliest opportunity.”

Latest news

HS2 awards £3bn of track contracts

Ferrovial BAM and Colas Rail among 'rail systems' winners
11 hours ago

Severfield finds weld problems on nine HS2 bridges

Steelwork specialist slumps to a loss after £20m hit to fix installed structures
19 hours ago

Wates wins Middlesbrough Gresham regen scheme

Firm will build 230 rental flats, hotel and student 450 student beds
15 hours ago

Scottish Water launches £9bn bid race

Delivery Vehicle 4 is company's largest ever procurement programme
19 hours ago

Multiplex signs off £400m Westminster barracks resi job

Super prime 179 flats to be built at former home of Royal Horse Artillery
1 day ago

Road worker dies after crash on A30

Collision involving two highways maintenance vehicles and a lorry in Cornwall
2 days ago

Vp launches dedicated rail division

Launch comes as equipment rental specialist posts latest results
20 hours ago

Kori Construction lands £21m Leicester care home

Work to start next month with local supply chain
20 hours ago

Kier in line for £70m Bishop’s Stortford town centre job

Developer Cityheart recommits to regeneration of Old River Lane site
19 hours ago

Kier and Bam star in two Welsh frameworks worth £1.4bn

Welsh hospitals and South West Wales building frameworks awarded
2 days ago

Developer GPE targets 40% of reused building materials

Subcontractors will be asked for suggestions on how to cut use of virgin materials
2 days ago

95 secure spots on major consultants framework

Host of firms win places on Procure Partnerships deal
2 days ago

Arup restructures board to create new CEO role

Group chair Jerome Frost takes new role at consultant
2 days ago

Winners revealed for £5.4bn electricity grid upgrade

SP Energy Networks unveils 19 winners - full list
5 days ago

Balfour and Flannery hit training milestone

1,000th student trained at Operator Skills Hub
2 days ago

Fast-track skills hubs to train 5,000 extra apprentices

Plan for network of 32 skills hubs to train construction apprentices in half the time
5 days ago

Malaysian property giant to buy 50% stake in JRL

IJM Land to buy into diversified £800m turnover south east contractor
5 days ago

Luxury house builder files administration notice

£31m turnover Octagon Developments Ltd lodges court notice
5 days ago

Morgan Sindall takes on £22m stalled ISG Cardiff school job

Workplan is being drawn up ahead of restart on Penarth school
5 days ago

Walker Modular wins bathroom pod deal on student tower

Sealant-free construction method helps supplier dominate student market
5 days ago

Over £600m awarded for decarbonisation projects – full lists

Over 240 public building energy upgrade projects secure cash
5 days ago

Enabling works to start on £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
6 days ago

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
6 days ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
6 days ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
6 days ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
6 days ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
6 days ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
6 days ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
7 days ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
7 days ago

Contractor services