Sir Robert McAlpine walked off with the industry’s biggest haul of new order wins last year on the strength of its £1bn-plus contract for phase 3 of the Battersea Power Station redevelopment.

Battersea Power Station phase 3 contract represents a third of McAlpine's haul of order last year
Battersea Power Station phase 3 contract represents a third of McAlpine's haul of order last year

The contractor romped to the top of the 100-firm rankings after securing just over £3bn worth of projects over the year, nearly four times more than in 2016 when the firm ranked 19th in the league, according to contract data collected by Glenigan.

In a closely contested year, there was little to separate second placed Kier and third placed Balfour Beatty. Likewise Laing O’Rourke, Morgan Sindall and Galliford Try were tightly grouped with around £2.22bn worth of work.

Vinci returned to the top 10 rankings after a difficult 2016, a year when it took stock and bid more cautiously following several major legacy contracts.

The Top 10 saw their share of new orders secured by the 100 most successful contractors edge up from around 41% in 2016 to 43% this year, while total work won over 2017 soared 20% to £47bn compared with 2016.

Top 10 ranking by value of work won
2017 2016 2015
1 Sir Robert McAlpine 3.04bn Morgan Sindall £2.4bn Kier £2.7bn
2 Kier 2.41bn Kier £2.1bn Bouygues UK £2.4bn
3 Balfour Beatty 2.41bn Laing O’Rourke £2.0bn Laing O’Rourke £2.2bn
4 Laing O’Rourke 2.22bn Royal BAM £1.8bn Galliford Try £2.1bn
5 Morgan Sindall 2.22bn Galliford Try £1.7bn VINCI £2.0bn
6 Galliford Try 2.22bn Carillion £1.4bn Balfour Beatty £1.9bn
7 VINCI 1.98bn Balfour Beatty £1.35bn Morgan Sindall £1.8bn
8 Willmott Dixon 1.45bn Wates £1.3bn Skanska £1.75bn
9 Wates 1.34bn Willmott Dixon £1.2bn Carillion £1.7bn
10 Carillion 1.33bn Mace £1.0bn Royal BAM £1.4bn

 

Click for full 100 contractors league

Click for full 100 clients league

As a consolation Kier secured most work in December netting 38 contracts worth around £263m, helped by a £50m residential scheme in Leicester for the city council and a £20m warehouse/factory job for Rotork in Bath.

Mace secured the biggest contract in the closing month of 2017 with the £140m Paul Marshall Building project at Lincolns Inn Fields for the London School of Economics.

John Sisk capped a strong year of new orders with a £90m office scheme for Bruntwood in Circle Square in Manchester. 

McLaren Construction secured a £58m mixed development for Scottish Widows in Banbury. 

Latest news

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
5 days ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
5 days ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
1 week ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
1 week ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
1 week ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
1 week ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
1 week ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
1 week ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
1 week ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
1 week ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
1 week ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
1 week ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
1 week ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
1 week ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
1 week ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
2 weeks ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
1 week ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
1 week ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
1 week ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
2 weeks ago

Mace to close construction logistics arm

Specialist business being wound down
2 weeks ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
2 weeks ago

Profits double at Barhale

Civils specialist sees order book top £1bn
2 weeks ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
2 weeks ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
2 weeks ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
2 weeks ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
2 weeks ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
2 weeks ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
2 weeks ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
2 weeks ago