Carillion fall-out hits Van Elle and Speedy

Aaron Morby 7 years ago
Share

Piling specialist Van Elle has joined a growing list of contractors and hirers to reveal the extent of their exposure to Carillion’s collapse.

The firm said this morning that its expected to take a hit of £1.6m on unpaid rail improvement and maintenance work.

Van Elle said it had applied for payment for work during December which had not yet been received, and work has continued on some of these contracts into January. 

It said: “The group will engage with Carillion and its advisers to determine the status of outstanding payments, but shareholders should note that, in the event that Van Elle is unable to recover any monies owed,  there would be an adverse financial impact on the Group.”

Van Elle’s order book includes further expected work with Carillion worth £2.5m.

Chief executive Jon Fenton added”It is too early to say whether there will be any effect on the commencement or completion dates of contracted work with Carillion, or what impact these developments will have on future work programmes, either in the rail sector or elsewhere, but the Group will monitor the situation closely and make further announcements as necessary.”

Plant and tool hirer Speedy said it was owed £2m from a total revenue of £12m with Carillion in the last 12 months.

A proportion of the group’s revenue and debt relates to joint venture arrangements involving third parties which are expected to continue unaffected. 

It added the impact was not expected to be material to the group which had net debts of £88.9m at the end of the year. 

Building services specialist T Clarke said it expected to take a hit of less than £100,000

T Clarke’s main project was on a Carillion joint venture project with KBR as part of the Aspire Defence Contract at Tidworth, Bulford and Perham Down.

It has been advised by the joint venture partner that there would be a transition for this contract but it could expect “business as usual”.

Among other firms understood to have taken hit are Heyrod Construction, which was working on several contract frames for Carillion in Manchester and plant hirer Hawk which has carried out several muck shifting jobs.

Yesterday Balfour Beatty and Galliford Try revealed they were each braced to take hits of around £40m for work on the Aberdeen Western Peripheral Route where they were in joint venture with Carillion.

Latest news

Caddick Construction targets £400m turnover

Regional shake-up pays off at contracting arm
5 hours ago

Redrow chief steps down after Barratt merger

Matthew Pratt leaving after 22 years
2 hours ago

Scores of M&E firms win places on £400m CHIC framework

Axis Europe and Seddon secured spots on social housing deal
16 hours ago

Coroner hears how worker was crushed under digger

Inquest opens into tragedy at Rose Builders site
19 hours ago

Billington lowers 2025 forecast amid pricing pressure

Tender prices under pressure due to project delays and cancellations
7 hours ago

Willmott Dixon lands Dover town centre revamp

Alliance agreed to regenerate several key council sites
1 day ago

Go-ahead for London City office-to-flats scheme

Hub's 150 Minories job in Aldgate to create 280 co-living homes
1 day ago

Wates mobilises as £200m Middlesbrough scheme approved

Gresham Street scheme includes a hotel, 240 flats and over 400 student rooms
1 day ago

Crashed M&E contractor TNA owed supply chain £7m

Sister company buys assets including company vans
1 day ago

Renaker eyes bumper 2025 despite Gateway 2 concern

Strong construction pipeline to support another record year
1 day ago

Wessex Water picks civils firms for £65m framework

Over 40 smaller firms will support AMP8 civils spending programme
1 day ago

Green light for nearly 400 flats at Leeds scheme

Three blocks up to 18 storeys approved at Armley Road
1 day ago

Subcontractors wanted across South London

Work up for grabs from main contractors and clients: Register now for Constructionline event
1 day ago

Heavy lorry ban on Severn Bridge as cables deteriorate

Crossing "not designed and built for today’s levels or weight of traffic"
1 day ago

Muse submits Oldham town centre regeneration plan

Plan advances for six sites to deliver 2000 homes, an hotel and office space
4 days ago

Construction returns to growth after two tough months

Concern grows Trump turmoil is spooking property investors
4 days ago

Skanska wins £43m Clifton Bridge deal

Contractors says scheme is a "complex project that will be delivered to tight timescales"
4 days ago

Green light for 44-storey Manchester resi tower

Developer Glenbrook to start hunt for main contractor
5 days ago

Ten win £670m Network Rail eastern region small works deal

CK Rail, QTS, Colt and Construction Marine pick up two lots
5 days ago

Mears aims to dominate in compliance and housing upkeep

Firm hails 100% rebid success on a slew of major contract renewals
5 days ago

Investigation after two track workers hit by wagon

Accident in Glasgow during engineering possession
4 days ago

Durkan finance chief joins house builder Thakeham

Paul Kimber confirmed as new Chief Financial Officer
4 days ago

Water win sees Mott MacDonald Bentley hunt for new staff

Recruitment event for the South of England: Register now
5 days ago

Labour master VAT fraudsters target subcontractors

Tax authorities looking to clamp down on payroll fraud
5 days ago

Domis to start this year on £350m Nobu towers

Developer Salboy gains planning for Viadux second phase in Manchester
4 days ago

Phoenix ME rides out ISG collapse with record 74% turnover surge

Pre-tax profit up after Phoenix re-engaged on all former ISG jobs
5 days ago

£200m Viking onshore pipeline project approved

55km underground pipeline to be built from Immingham to Theddlethorpe
5 days ago

Plans in for Bristol Brabazon over-station office block

YTL Construction UK to build 8-storey office block
5 days ago

Mace confirmed for £200m London City office retrofit

Four upper floors to be added to 65 Gresham Street
5 days ago

Lindum profit jumps 28% as turnover nears £200m

507 staff shareholders share in strong year as pre-tax profit hits £10.4m
6 days ago