Sunderland council rebids Carillion Vaux brewery project

Aaron Morby 7 years ago
Share

Sunderland City Council and its development partner Siglion have confirmed they are now rebidding Carillion’s stalled Vaux brewery project.

Carillion's Vaux project was the first spec office scheme in Sunderland for many years
Carillion's Vaux project was the first spec office scheme in Sunderland for many years

Overlooking the River Wear at the northern edge of the city centre, the site is widely regarded as one of the North East’s most significant regeneration sites.

The council had to halt construction work on the regeneration scheme’s first building project following the collapse of Carillion Construction.

A tender process with other contractors has now begun with tenders due to be returned on the £16m project in mid-April.

Stockton-On-Tees contractor Hewitson Group was working on the key groundworks and RC packages for the phase one office project.

Councillor Harry Trueman, Leader of Sunderland City Council, said the Vaux regeneration project was crucial for the city’s future and a lot of work had been carried out behind the scenes on getting new tenders drafted as soon as possible.

He said: “Vaux has always been a flagship site and many have described it as a ‘once in a lifetime’ opportunity. This development is one about expanding the footprint of our city centre, and bringing more jobs and economic prosperity to Sunderland.”

Long-term plans remain to develop the former brewery site into a new business district to create more city centre jobs, offices and pedestrian traffic.

Vaux Brewery site’s longterm development plan

The City Council acquired the site from supermarket chain Tesco in 2011. In 2012 and 2013, the council prepared the Vaux site for development by removing contaminated materials and demolition.

In 2013 and 2015, a major re-shaping and re-modelling of the city centre was completed with the creation of the Keel Square and St Mary’s Boulevard.

John Seager, Chief Executive of Siglion, said: “The process to appoint a contractor for the final construction phase on site is underway, and we hope to be in a position to announce more details on that soon.”

Mr Seager added that the priority had been to ensure that the project would be delivered in a way that provides continuity, in terms of the subcontractors and ensuring minimal impact on the warranties and terms of the original contract.

He said: “It’s been a complex and very involved process to move this forward, but we have been resolute in our aim to fulfil the original vision for this stunning building.”

Latest news

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
1 week ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
1 week ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
1 week ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
1 week ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
2 weeks ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
2 weeks ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
2 weeks ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
2 weeks ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
2 weeks ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
2 weeks ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
2 weeks ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
2 weeks ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
2 weeks ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
2 weeks ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
2 weeks ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
2 weeks ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
2 weeks ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
2 weeks ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
2 weeks ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
2 weeks ago

Mace to close construction logistics arm

Specialist business being wound down
2 weeks ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
2 weeks ago

Profits double at Barhale

Civils specialist sees order book top £1bn
2 weeks ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
2 weeks ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
2 weeks ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
2 weeks ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
2 weeks ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
2 weeks ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
2 weeks ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
2 weeks ago

Contractor services