Scottish inquiry urges widespread checks on fire stopping

Aaron Morby 7 years ago
Share

The chairman of the inquiry into construction failings at a flagship leisure centre in Dumfries has urged local authorities to double-check fire stopping on existing and new buildings nearing completion.

Repair and rebuild costs at Dumfries building soar to £18m
Repair and rebuild costs at Dumfries building soar to £18m

Prof John Cole was commissioned by Dumfries and Galloway Council to investigate a catalogue of building failures at the DG One leisure centre.

The centre opened in 2008 at a cost of £17m but was forced to shut permanently six years later for repair work, which will cost more than the original construction project carried out by Kier.

Repair and rebuild contractor McLaughlin and Harvey is now expected to complete the project at an extra cost of £18m in the latter half of 2019.

Cole, who also led the investigation into building failures at Edinburgh’s schools, said the contractor was “unquestionably” responsible for the shoddy work identified in DG One.

The recommendations from his report also raise concerns about the state of the Scottish building market.

In it he states: “It would be inappropriate in considering the failure of the contractor to adequately supervise and inspect the quality of the construction work not to draw parallels with the findings of the 2016-17 Edinburgh Schools Inquiry.

He said among all the identified failures in the construction of DG One there were widespread inadequacies in the structural integrity of the external masonry walls and in the failure to incorporate effectively, or to incorporate at all, essential fire-stopping throughout the building.

“It is the view of the Inquiry that the widespread presence of these same failures in the DG One building lends further support to the finding of the Edinburgh Schools Inquiry that these failures are indicative of systemic problems in the quality of work provided by the construction industry.”

External masonry walls to the main rotunda have been demolished

Investigations uncovered widespread defects in the walls of the building. This necessitated remedial works to walls, and the need to virtually demolish the complete three-storey high walls surrounding the large rotunda.

The inquiry report recommended that local authorities and other interested public-sector organisations cooperate in the production and sharing of a list of those aspects of the construction of new buildings in which defects are seen to frequently occur, such as is the case with external masonry wall construction and fire-stopping.

Finally, Cole writes: “In light of the risk associated with the inadequate installation of fire-stopping, it is recommended that public authorities should undertake appropriately informed inspections of existing buildings and new buildings nearing completion to ensure the adequacy of the fire-stopping installed.”

Latest news

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
6 days ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
6 days ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
1 week ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
1 week ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
1 week ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
2 weeks ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
2 weeks ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
2 weeks ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
2 weeks ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
2 weeks ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
2 weeks ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
2 weeks ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
2 weeks ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
2 weeks ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
2 weeks ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
2 weeks ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
2 weeks ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
2 weeks ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
2 weeks ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
2 weeks ago

Mace to close construction logistics arm

Specialist business being wound down
2 weeks ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
2 weeks ago

Profits double at Barhale

Civils specialist sees order book top £1bn
2 weeks ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
2 weeks ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
2 weeks ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
2 weeks ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
2 weeks ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
2 weeks ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
2 weeks ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
2 weeks ago

Contractor services