Runaway rail maintenance vehicle at Bradford station

Grant Prior 7 years ago
Share

A safety investigation has been launched after a road-rail maintenance vehicle ran away towards Bradford Interchange terminal station.

The mobile elevating working platform involved in the incident
The mobile elevating working platform involved in the incident

The maintenance vehicle was a mobile elevating working platform that was equipped with both rubber wheels for road running and steel rail wheels for operation on the railway.

On the Friday night of the incident earlier this month it was intended to be used for examination work on a section of track which was under possession.

The runaway started at the Britannia Street road-rail access point, which provides a flat surface allowing road-rail vehicles to be manoeuvred on to the track.

This access point is on a section of railway which slopes downwards at a declared gradient of 1 in 50 towards the station before running onto level track as it enters the platforms.

Shortly after 01:30 hrs the MEWP was being transferred from its rubber-tyred road wheels onto its rail wheels.

During this manoeuvre, known as on-tracking, the machine operator was controlling the machine using a remote control unit which was connected to the machine by a cable.

As the rail wheels were lowered onto the track the MEWP started to run down the gradient towards the station where it stopped about 340 metres from the access point.

No-one was on board the MEWP as it started to run away. The machine operator and machine controller attempted to stop the runaway.

They were unable to do so, but they kept up with the machine during its travel to warn other staff working in the vicinity.

Initial evidence suggests that the runaway occurred because the on-tracking was not carried out correctly and the rail wheel brakes, intended to hold the vehicle on the gradient, provided insufficient brake force to do so.

The Rail Accident Investigation Board’s probe will identify:

  • the sequence of events that led to the runaway
  • the factors influencing the actions of those involved in the operation of the machine as it was being placed onto the track
  • the actual capability of the rail wheel brakes
  • the rail-conversion and maintenance history of the MEWP
  • the standards and design approval processes that were applied to this type of MEWP
  • any relevant management factors

Latest news

HS2 set for “fundamental reset” to lower construction costs

New chief executive promises action after latest project update
1 day ago

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
1 week ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
1 week ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
2 weeks ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
2 weeks ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
2 weeks ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
2 weeks ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
2 weeks ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
2 weeks ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
2 weeks ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
2 weeks ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
2 weeks ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
2 weeks ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
2 weeks ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
2 weeks ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
2 weeks ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
2 weeks ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
2 weeks ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
2 weeks ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
2 weeks ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
2 weeks ago

Mace to close construction logistics arm

Specialist business being wound down
2 weeks ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
2 weeks ago

Profits double at Barhale

Civils specialist sees order book top £1bn
2 weeks ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
2 weeks ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
2 weeks ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
2 weeks ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
2 weeks ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
2 weeks ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
2 weeks ago

Contractor services