Laing O’Rourke to restart stalled Royal Liverpool Hospital

Aaron Morby 6 years ago
Share

Laing O’Rourke has secured the management contract to finish the Royal Liverpool Hospital project, which stalled in January when Carillion collapsed.

Work could restart within the next few weeks
Work could restart within the next few weeks

The firm has been hovering around the project since work stopped while the hospital trust sought to find a way to restart the project.

The Trust has now formally terminated its existing PFI agreement with The Hospital Company (Liverpool) and key lenders, the European Investment Bank and Legal and General.

The Government, and regulator NHS Improvement, will be working with the Trust to ensure that construction works are restarted as soon as possible.

It is hoped that this could be as early as next month, with construction work on the new Royal expected to be completed in 2020.

The Government is now finalising details of a new funding package that will enable the Trust to complete the project.

Taken together with earlier payments made by the Trust, the total cost to the public sector of the new hospital is expected to be lower than envisaged when the project agreement was signed.

Paul McNerney, director at Laing O’Rourke, said: “Laing O’Rourke is delivering the Clatterbridge Cancer Centre next door to the new Royal and had been working closely with the team there already.

“The business now looks forward to partnering with the Trust directly to re-start this important works for the local community.”

PFI termination and transfer arrangement

Under the terms of the original 2013 contract, the funders will receive a £42m termination payment from the Trust – funded by the public purse – as well as all funding held by The Hospital Company at the time of its winding up.

This is required to cover PFI unitary payments that The Hospital Company will no longer receive and deducts the cost of the remaining construction work, and the projected cost of maintaining the hospital – both of which will now fall to the Trust.

The key lenders have spent £180m on the project. In line with the risk transfer arrangements agreed in the original contract, they will lose most of this funding.

In addition, the equity funders  – Carillion Private Finance and Pensions Infrastructure Platform – will lose all their investment.

The Trust is now responsible for completing and operating the hospital. THC will now transfer their contracts to the Trust, which include a deal with Laing O’Rourke to become management contractor.

Once the new Royal has opened, the current hospital will be demolished and landscaped to provide underground car parking and space for the creation of the Liverpool Health Campus

Aidan Kehoe, chief executive of the Royal Liverpool and Broadgreen University Hospitals NHS Trust said: “We are delighted to announce that we, The Hospital Company, lenders and the Government have all signed up to this agreement, that means construction can restart soon and that the new Royal will now be publicly funded.

“The agreement provides significant savings to the public sector and represents good value for money for the taxpayer.

“All parties have worked extremely hard to resolve the issues caused by the collapse of Carillion. The lenders in particular have shown considerable goodwill in reaching this agreement.

“Our priority now is for Laing O’Rourke to get work restarted as soon as possible. We hope to be able to continue working with the existing subcontractors so that work can be completed quickly.”

Background to construction delay

Construction work began under a £335m contract on 3 February 2014 and was originally scheduled to be completed by March 2017. This was delayed, according initially to Carillion, due to issues regarding the removal of asbestos from the ground and strong winds affecting the use of cranes.

It later emerged that Carillion also knew about major structural defects in transfer beams in the hospital back in November 2016. At the time Carillion said remedial works to eight cracked transfer beams would put the project opening back to June 2017.

But it became clear the faults required full remodelling of the building’s concrete frame and would cost £20m to fix.

As these works were getting underway a new revised completion date of February 2018 was provided by Carillion.

At the end of November 2017 Carillion informed the Trust that they would be unable to meet this date as work was still ongoing fixing the crack beams.

According to a survival business plan put to Government in a last roll of the dice for a taxpayer bail-out, the board believed it could claim £43m on the delayed Royal Liverpool Hospital PFI contract, including recovery of claims from third parties of £34m following problems with the concrete beams.

A new date had not been provided prior to Carillion finally entering into liquidation in January 2018.

Latest news

Breyer Group files administration notice

Staff hope rival firm could buy assets and save jobs
4 hours ago

Peel Ports reveals winners for £750m framework

18 firms win places on deal: Full list
2 hours ago

Wates wins fit-out for Manchester First Street Hub

Smartspace arm secures another Government hub deal
1 hour ago

Former Severfield director takes helm at Embrace Steel

New CEO Martin Kelly aims to step up expansion of steelwork contractor
4 hours ago

£302m upgrade funding awarded to FE colleges – list

Cash shared out between England’s 179 college groups
4 hours ago

FK Facades thrives but construction arm hit by ISG row

Dispute with failed contractor costs specialist £5.5m
5 hours ago

Galliford Try gets go-ahead for Milton Keynes PRS tower

33-storey tower needs gateway 2 approval before work can start
23 hours ago

Small house builders get £150m funding for green homes

Developers will have to meet-up to ten new criteria to benefit from interest rate discounts
4 hours ago

Lendlease Construction renamed Bovis

US private equity firm completes £35m purchase of UK contracting business and rebrands
1 day ago

Breyer Group battles for survival as rivals circle

Housing maintenance firm fights three winding up petitions in a month
1 day ago

Careys facing £2.4m claim by developer over demolition cartel

Giant Hong Kong developer claims it was overcharged on Lots Road Power Station job
1 day ago

Multiplex profit drops a third as revenue rises to £780m

Spate of new orders sets contractor up for three years of work
1 day ago

Galliford Try and Breheny land latest Sizewell C road deals

More infrastructure deals for new nuclear power station
2 days ago

Worker trapped in collapsed septic tank pit

Contractor and director fined after worker suffers multiple fractures
1 day ago

Homes England buys stalled Broad Marsh site

Demolition to finally be completed as developer hunt begins
2 days ago

Vistry go-ahead for 353 homes at Rochester Riverside

Work to start on next phase of Kent town regeneration at end of this year
2 days ago

M&E firm J S Wright collapsed owing £19m

Trade creditors hit for £11.4m by employee-owned Midlands firm
2 days ago

Right to work checks to be extended to self-employed

Government plans crackdown on illegal working and rogue employers
2 days ago

Midlands developer turns to London with £1bn resi schemes trio

SevenCapital plans 1,000 flats in Kensington, Islington and the Isle of Dogs projects
2 days ago

Deck falls off huge scissor lift at Winvic site

Two men seriously injured as platform plunges to the ground
5 days ago

Weston targets Build to Rent with new division

Weston Partnerships signs first deals with asset managers and councils
2 days ago

Bouygues seals deal for £119m Cardiff college campus

Construction to start in June on two new buildings
5 days ago

£140m cash injection to speed-up flood defence schemes

Funding part of £2.65bn investment over the next two years
2 days ago

Bid race starts for £15bn schools framework refresh

DfE throws framework open to more contractors
5 days ago

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
6 days ago

London Mayor calls in blocked 600-bed student scheme

Refused 20-storey London PBSA block may still be built
5 days ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
6 days ago

Arrest after pedestrian death on construction site

Tragedy during site preparation works for new Wigan car park
5 days ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
6 days ago

Planning green light for Sheffield warehouse site

Existing factories to be demolished in new scheme for Rula Developments
5 days ago

Contractor services