Terry Morgan expects Crossrail problems to cost him HS2 job

Aaron Morby 6 years ago
Share

Acclaimed engineer Sir Terry Morgan is bracing himself to be dismissed from both his Crossrail and HS2 chairman jobs.

Chairman of Crossrail and HS2 expects to hear fate in days
Chairman of Crossrail and HS2 expects to hear fate in days

Sir Terry revealed that he expected to be forced from his HS2 job by Government because of concerns about ballooning costs at Crossrail.

Speaking to the BBC Radio 4 PM programme on Saturday after leaks to the Financial Times about reports of his looming dismissal, he said: “I did get confirmation late yesterday afternoon that that was a leak.

“As far as I’m concerned, I’m expecting that to be confirmed more formally in the next few days.”

Sir Terry went on to claim that he had told London Mayor Sadiq Khan that Crossrail would be delayed more than a month before it was finally announced at the end of August.

He also said train commissioning, which was not the responsibility of Crossrail, was also well behind programme, inferring this too would have caused delays

On his dismissal, he said that he had mixed feelings.

“I do feel a sense of responsibility for contributing to the position on Crossrail. On HS2, I have a lot of experience and knowledge to give to that programme but disappointed that now I will not have the opportunity to do this.”

On Crossrail, he said he remained very disappointed there were so many challenges so late in the programme, particularly on system integration.

“And that’s because there are some tremendously gifted engineers who built what I know will be a fantastic programme,” he added.

Sir Terry challenged accounts of when delays were first reported to the London Mayor, claiming Crossrail red-flagged the need to delay completion from 2018 to 2019 a month before this was revealed to the public.

“There’s been some unfortunate comment about who knew what and when about whether the programme on Crossrail was running late.

“I’m very confident that Crossrail behaved properly. There will be and there are plenty of documents that set out exactly what happened and when.

“And I do hope that these documents will be released soon for others to understand. I don’t understand why all the comments that have been made, have been made as they are, because some of them are just factually not correct.

”Obviously it’s insinuation that says in the detail, although the station build did run a little late, what most people don’t realise is that the rolling stock, the trains, are a contract that is not a Crossrail contract, they’re a Transport for London contract, I’m not responsible for the rolling stock and nor are any of the executive.

“I personally now realise that TfL were advised that this train contract was running 18 months late and had known that for at least eight months and that to me, today, still feels to be the case.

“We still have not got train testing underway.”

TfL maintains that it was not until 29 August that they were told that the opening of central section would be definitely delayed until Autumn 2019.

Latest news

Buyers flag fears over civil engineering slowdown

All sectors in reverse during "challenging" March
1 hour ago

Torsion and Khalbros to build new Leeds £1bn neighbourhood

Eastgate Quarter site acquired from Hammerson
21 hours ago

Winners named for £380m Scottish council housing upkeep deal

PfH Scotland names 38 firms for social housing landlord deal
5 hours ago

Kier wins first phase of £700m Warwick Uni campus build

Firm to start work on science and engineering precinct last this year
21 hours ago

JCB to double size of US factory in wake of Trump tariffs

$500m Texas factory under construction to expand to 1m sq ft
22 hours ago

Green light for £2.4bn Luton Airport expansion

Government go-ahead to transform airport
22 hours ago

Mivan looks to boost supply chain network

Subcontractors and suppliers invited to meet the buyer event: Book places now
6 hours ago

Diversification pays off for concrete frame specialist Statom

Strong results as £180m turnover firm expands into infrastructure sector
24 hours ago

Cardo in talks to buy Breyer roofing arm

More than 100 jobs could be saved at Breyer Roofing
1 day ago

Quartet win £750m Wales & Western railway deal

Network Rail confirms partners for Reactive and Minor Works framework
1 day ago

Plans in for £350m London Bridge life sciences hub

Snowsfields Quarter will consist of three buildings containing labs
1 day ago

Surging labour costs push tender price forecast up

Pick-up in tender prices despite weak growth
1 day ago

Permasteelisa wins cladding deal on Multiplex city tower

Facade specialist wins work on Fenchurch Street ‘hanging gardens’ tower
1 day ago

Wates wins fit-out for Manchester First Street Hub

Smartspace arm secures another Government hub deal
2 days ago

Peel Ports reveals winners for £750m framework

18 firms win places on deal: Full list
2 days ago

Big trade names dropped in M Group rebrand

Acquisitive group formed from Morrison Utility services in 2016
2 days ago

Breyer Group files administration notice

Staff hope rival firm could buy assets and save jobs
2 days ago

Former Severfield director takes helm at Embrace Steel

New CEO Martin Kelly aims to step up expansion of steelwork contractor
2 days ago

£302m upgrade funding awarded to FE colleges – list

Cash shared out between England’s 179 college groups
2 days ago

FK Facades thrives but construction arm hit by ISG row

Dispute with failed contractor costs specialist £5.5m
2 days ago

Galliford Try gets go-ahead for Milton Keynes PRS tower

33-storey tower needs gateway 2 approval before work can start
3 days ago

Small house builders get £150m funding for green homes

Developers will have to meet-up to ten new criteria to benefit from interest rate discounts
2 days ago

Lendlease Construction renamed Bovis

US private equity firm completes £35m purchase of UK contracting business and rebrands
3 days ago

Breyer Group battles for survival as rivals circle

Housing maintenance firm fights three winding up petitions in a month
3 days ago

Careys facing £2.4m claim by developer over demolition cartel

Giant Hong Kong developer claims it was overcharged on Lots Road Power Station job
3 days ago

Multiplex profit drops a third as revenue rises to £780m

Spate of new orders sets contractor up for three years of work
3 days ago

Galliford Try and Breheny land latest Sizewell C road deals

More infrastructure deals for new nuclear power station
4 days ago

Worker trapped in collapsed septic tank pit

Contractor and director fined after worker suffers multiple fractures
3 days ago

Homes England buys stalled Broad Marsh site

Demolition to finally be completed as developer hunt begins
4 days ago

Vistry go-ahead for 353 homes at Rochester Riverside

Work to start on next phase of Kent town regeneration at end of this year
4 days ago

Contractor services