Government infrastructure pipeline needs reality check

Aaron Morby 6 years ago
Share

A group of leading investors, contractors and consultants have called on Government to reform its vaunted £413bn infrastructure pipeline of projects.

Research by the Infrastructure Forum said less than 8% of the 276 projects included in the Infrastructure and Project Authority’s National Infrastructure and Construction Pipeline were sufficiently certain for contractors to invest to deliver them.

It also warned that lack of visibility of public sector projects was driving many of the unsustainable behaviours that led to the collapse of major government outsourcer Carillion and has left other major contractors in a fragile state.

The critical report published today calls on the Treasury to overhaul the whole project reporting system to set up a more certain Pledged Project List.

This would capture only those projects that have been approved for delivery by the relevant Government Department or public authority and will be procured in the short to medium term.

Of the pipeline’s total value of £413bn only £30.24bn constituted realistic potential investment for contractors therefore driving many of the unsustainable behaviours.

Graham Mather CBE, President of The Infrastructure Forum, said: “A smaller, more tightly defined list of projects that will definitely go ahead is much more valuable to the sector than an enormous list of projects some of which are already underway and some of which may never happen.”

Key recommendations set out by the Infrastructure Forum

  • HM Treasury should issue a Pledged Project List, capturing only projects approved for delivery that will be procured in the short to medium term
  • The IPA should develop a Contract Footprint Framework mapping all projects valued over £30m which have begun procurement and are under construction, acting as an early warning system on risk exposure to a contractor if they fall into financial difficulty
  • Both the public and private sectors must adopt a definition of ‘value for money’ that captures the wide range of factors that contribute to delivering social value
  • The cost of bidding for work must be reduced. Two-stage procurement frameworks offer an efficient tool to build partnerships between clients and contractors, and should be used more widely
  • All Government Department’s should accept proposals from the private sector for innovative projects and reimburse the proposer if adopted
  • The Cabinet Office should set up a mobile Procurement Team to support procurement in the public sector and develop expertise with Departments.

David Ferroussat, Development Procurement Director at Heathrow Airport Limited, chaired the cross-sector working group.

He said: “Infrastructure clients have a moral duty to provide a sustainable environment for their supply chain to deliver and operate within.

“A contract footprint framework will provide valuable information for clients by tracking its supply chain’s projects, resilience and capacity. Cross client sharing of this data would also benefit the UK construction industry as a whole.”

Latest news

Henry administrators chase £10m director payment

Cash frozen as legal action continues
1 day ago

Former Balfour regional MD dies before taking up new role

Lindsay McGibbon struck down by cancer
7 hours ago

One of Wales’ oldest contractors delivers record profit

Andrew Scott chairman says clients are now looking beyond lowest bid for jobs
6 hours ago

Warning after scammers pose as plant hire bosses

Flannery targeted by fraudsters trying to con customers
11 hours ago

Carey co-founder Tom Carey passes away

Contractor confirms death of second of three founding brothers
1 day ago

Robertson and Balfour win £333m schools deal

Contractors land work for five schools in Scotland
10 hours ago

Go-ahead for £125m Ealing leisure centre and homes scheme

Council seeks contractor to deliver flagship Gurnell development
10 hours ago

State of Englands local roads a ‘national embarrassment’

Spending watchdog urges Govt to tackle £15bn repair backlog
11 hours ago

Worker loses three fingers at timber frame factory

Construction supplier fined after panel saw accident
10 hours ago

Three in race for £20bn fusion power station

Balfour Beatty, Kier and Ferrovial head consortia in chase for 'star power' reactor
1 day ago

Office work drives 0.4% uptick in construction output

Activity in November grew four times faster than the UK economy as a whole.
1 day ago

Plans in for 34-storey Manchester student tower

Developer Vita plans 861-room tower in First Street district
1 day ago

Council quits homes joint venture to speed-up construction

Worthing Borough Council selling land to Roffey Homes
1 day ago

Kier signs £243m army barracks upgrade

Latest big defence optimisation deal signed off for Aldershot barracks
1 day ago

Winners revealed for £814m FM framework

Latest deal from Pagabo will provide roofing, mechanical and decorating work - see all 27 winners
2 days ago

Jackson signs £19m Sizewell C access roads deal

Latest contract takes work awarded to £2.5bn but concern mounts about final cost
1 day ago

Vistry slims down to three operating divisions

Delayed completions and lower sales push month-end debt to £535m
2 days ago

Business better than expected at bullish Galliford Try

Key work wins to power strong set of annual results
2 days ago

Refurb contractor went down owing supply chain £9.5m

Troy Central owed cash to more than 300 subcontractors
2 days ago

Morgan Sindall starts £90m Cambridge mixed-use job

Works starts on Mill Yard regeneration scheme two years after planning go-ahead
2 days ago

Cardo breaks into Scotland with fifth acquisition

Investor-backed building maintenance contractor continues expansion
2 days ago

Tilbury Douglas bags major Barbican Centre M&E upgrade

Barbican Arts Centre revamp could be worth up to £185m over 10 years
2 days ago

Former Keltbray site managers stand trial over contract “bribes”

Trio accused of taking kickbacks from labour supply specialist
3 days ago

Trio of tech giants unveil £14bn AI data centre hub building plans

Building bonanza beckons as total committed investment hits £39bn
3 days ago

Crest Nicholson delays results over £250m fire safety provision

Auditors request more time to confirm figures
3 days ago

Bid race for £55m London leisure centre and homes

Tower Hamlets advances St George's swimming pool and 29 homes plan
3 days ago

Winners revealed as NHS plans to spend £500m on decarbonisation

Refurb deal will help NHS become world’s first net zero national health service
4 days ago

Seven scoop £850m Yorkshire Water complex projects deal

Firms will deliver non-infrastructure clean and wastewater assets over the next five years
4 days ago

L&G submits plan for £350m Bristol Temple Island

520 homes, two office blocks and hotel plan for former diesel depot site
4 days ago

London Embankment scheme rebooted as student rooms

Urbanest plans Albert Embankment student towers
4 days ago

Contractor services