165 tonnes of steel needed to fix botched Liverpool hospital

Grant Prior 6 years ago
Share

More than 220 cubic metres of new concrete and 165 tonnes of fabricated steelwork will be needed to fix structural faults at the mothballed Royal Liverpool Hospital.

CGI of structural interventions on the ward
CGI of structural interventions on the ward

The scale of the repair work to rectify mistakes by original contractor Carillion has been revealed by the Royal Liverpool NHS Trust.

Replacement contractor Laing O’Rourke will start structural repairs this month after stripping out great swathes of the hospital to uncover the extent of the problem.

O’Rourke has been working with Arup to assess the original concrete frame with extensive structural repairs now needed across three floors.

Cladding and exterior finishes will also be stripped off the building this summer.

Arup director Jim Bell said: “Our structural review looked at the building as it is now and the building at its peak use, once the hospital is open and fully operational.

“The solutions to address these issues involve using tried and tested methods to strengthen existing beams, reduce loads that are causing structural issues and putting in place additional support.

“The works are highly complex and are necessary to ensure the building is finished to the high standards required.”

The structural interventions will require over 220 cubic metres of new concrete and 165 tons of new fabricated steelwork.

Andy Thomson, project director, Laing O’Rourke said: “Control measures are already in place to ensure there are no immediate risks to workers in the building.

“Fixing the structural issues is a complex programme of work, with the added challenge of protecting the existing hi-tech fixtures and fittings in the hospital.

Above ward prior to Laing O’Rourke strip out and below how it looks now after preparation for structural intervention

“This requires heating the building and maintaining water flow to prevent deterioration, which would lead to costly replacements if it was not diligently carried out.”

Work on the structural interventions will begin later this month.

To create access, to help transport materials like concrete and steelwork into the building, some of the cladding and exterior of the building will be removed over the summer.

Dr Peter Williams, chief executive of the Trust said: “Whilst work on these structural interventions is underway, the programme to complete the new Royal will be finalised.

“Once the programme is finalised and the costs are all accounted for we’ll confirm timescales and costs. We owe it to everyone to not raise expectations with speculation, until everything is signed, sealed and delivered.”

Latest news

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
3 days ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
3 days ago

Miller Homes buys St Modwen Homes for £215m

Scottish house builder snaps up £368m turnover rival
6 days ago

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
6 days ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
6 days ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
7 days ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
1 week ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
7 days ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
7 days ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
7 days ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
7 days ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
1 week ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
1 week ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
1 week ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
1 week ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
1 week ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
1 week ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
1 week ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
1 week ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
1 week ago

Mace to close construction logistics arm

Specialist business being wound down
1 week ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
1 week ago

Profits double at Barhale

Civils specialist sees order book top £1bn
1 week ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
1 week ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
1 week ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
1 week ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
1 week ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
1 week ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
1 week ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
1 week ago

Contractor services