Southwark Crown Court heard that, on 15 January 2016, a pipe fitter working for Fascel Group Limited was working on the transfer of a pump set from its pallet to a raised platform in Goodman’s Fields.
The pump set fell on him. As a result, the worker was pinned beneath the unit, and he sustained serious injuries including multiple fractures and dislocations.
An HSE investigation found that Fascel Group Limited had been contracted to do mechanical and engineering works on the project that included the installation of the pump set.
The company had failed to ensure that a safe system of work for the moving and positioning of the pump set was communicated to the operatives undertaking the work.
Fascel Group Limited of Luton pleaded guilty to breaching CDM regulations and were fined £36,000 with £34,235.45 costs.
Speaking after the hearing, HSE inspector Gabriella Dimitrov said: “Those in control of work have a responsibility to devise safe methods of working and to provide the necessary information, instruction, and training to their workers.
“Companies should be aware that HSE will not hesitate to take appropriate enforcement action against those that fall below the required standards.”