Spending watchdog demands greater HS2 scrutiny

Aaron Morby 5 years ago
Share

Parliament’s spending watchdog has demanded far greater scrutiny of HS2 costs and programme delivery in a damning report that accuses the transport department of hiding details of overspending and hold-ups.

Meg Hillier, the MP who chairs the PAC, says MPs are concerned about how open the Department and HS2 Ltd executives have been in their account of HS2
Meg Hillier, the MP who chairs the PAC, says MPs are concerned about how open the Department and HS2 Ltd executives have been in their account of HS2

The powerful public accounts committee slams the Department for Transport and HS2 for lack of transparency, warning it has undermined public confidence in the programme.

The critical report highlights serious concerns about the early failure to report that the project had gone badly off-course as the budget soared from £56bn to £88bn.

Committee MPs also said they were concerned that several years into the programme, huge uncertainty remained with the design and delivery of Euston station.

The report calls for DfT within six months to set out its plan for Euston, including how it will be delivered and how it will ensure effective working between all stakeholders.

They also questioned whether DfT and HS2 Ltd had the skills and capability they need now or in the future.

“A lack of capability continues to be an issue; HS2 Ltd recently assessed that while it had improved its capabilities in most areas, it still has gaps in key areas such as risk management and assurance, project management and project controls.

“Now that it is bearing more of the risk of cost increases, HS2 Ltd also needs to ensure that it has the right commercial skills to manage its revised contractual arrangements with its main construction contractors,” says the report.

In its recommendations to Government, the Committee is seeking new, formal assurances that DfT and HS2 Ltd have the capability to manage the programme and its supply chain, into construction and through to completion.

Committee chair Meg Hillier MP said: “In the six-monthly reports the Department has now agreed to give us, we want to see an honest, open account, and evidence of learning from past mistakes being applied to bring this project under control, to deliver it within the timeline and budget that have been agreed in justifying the project.”

Committee’s Deputy Chair Sir Geoffrey Clifton-Brown MP said: “This PAC report on HS2 is one of the most critical, in both the transparency of Government and the handling of a project, that I have seen in my nine years in total on the committee.

“The Permanent Secretary appeared before the committee in October 2018 and again in May 2019.

“In March 2019 HS2 Ltd formally told the Department it had breached the terms of the Development Agreement, and would be unable to deliver the programme to cost and schedule – yet the Permanent Secretary did not inform the committee on either appearance that the programme was in trouble.

“This is a serious breach of the department’s duty to Parliament and hence to the public, which as the report says, will undermine confidence.

“Furthermore, the PAC was in the dark about serious cost overruns and was therefore unable to do its duty to inform Parliament that value for money on the project was at risk.

“The cost overruns have been blamed partly on the speed that the hybrid Bill committee for Phase One proceeded with. I was a member of that committee, which lasted for 20 months: this is complete nonsense.”

Latest news

Wates boss returns after collapse of his own contractor

Paul Nicholls was head of the failed Real construction group
6 hours ago

New Fair Payment Code goes live today

Latest bid to get subcontractors and suppliers paid within 30 days
10 hours ago

Lincolnshire concrete supplier files administration notice

Ever Readymix Concrete & Screed operates three depots and a fleet of 20 trucks
10 hours ago

Graham lands first deal on Liverpool’s largest brownfield site

Contractor bags infrastructure package on 10.5 hectare site
1 day ago

Bouygues UK boss to step down

Fabienne Viala to leave after eight years at the helm
1 day ago

Galliford Try scoops £87m brace of London jobs

Firm will redevelop a prominent corner building on Sloane Street in Chelsea
10 hours ago

New HS2 boss Mark Wild starts amid prep for final TBM drives

Former Crossrail CEO starts with a sharp focus on controlling costs
1 day ago

Ten consultants land Thames Water major upgrade places

Firms will share £400m of fee work over next five years
1 day ago

Rayner ultimatum to fix all unsafe tall buildings by 2029

Recladding work must start on all 18m+ resi buildings by 2027
1 day ago

ISG administrator finds just £35m to pay down £1.1bn debt

Failed firm was set to report £148m blackhole from legacy jobs
1 day ago

Redesign needed on Colas “bridge to nowhere”

Technical challenges continue as £38m scheme faces further delays
1 day ago

Skanska UK shakes-up boardroom team

Four new board appointments as two directors step down
1 day ago

Ultra rich clamour for Mace super prime resi scheme

Topping out at £2bn 1 Mayfair scheme where homes start at £35m
1 day ago

Watkin Jones wins £48m St Helen’s affordable homes deal

Firm to build nearly 300 homes for housing association
1 day ago

Barratt sets start date for High Barnet station scheme

Latest scheme to be delivered by the £1.9bn West London Partnership
1 day ago

Investors lose £26m after M&E contractor goes under

78 private investors hit by Gallant Building Services collapse
4 days ago

First contractor call for £80bn Government mega-framework

Seven-year deal will cover construction work across all departments
5 days ago

Transport Secretary quits Cabinet

Louise Haigh resigns over stolen mobile phone revelations
4 days ago

NHS modular specialist looks to strike deal with creditors

Catfoss Group Manufacturing applies for Company Voluntary Arrangement
4 days ago

Kier bags £23m Cheadle Eco Business park job

Contractor beats rival Galliford Try to deliver Stockport council's green business park
4 days ago

Willmott Dixon wins £24m Leeds council housing scheme

Firm will build 82 council houses on site of Hough Top school
4 days ago

Welding crisis road bridges revealed

Bridge projects in Midlands, Gateshead and Cornwall impacted
5 days ago

£1bn Bishopsgate Goodsyard phase one go-ahead

London Mayor approves 550,000 sq ft office scheme above Shoreditch station
5 days ago

Costain poised for major HS2 tunnel fit out deal

Latest major deal on project due imminently
5 days ago

New builds overtake refurbs in London office market

Drop in new construction starts but developers remain bullish
5 days ago

Willmott Dixon wins £23m net zero Surrey SEND school

Hopescourt School job takes low carbon work pipeline to £1.4bn
5 days ago

£1.6m fine after mast climber crush tragedy

Court hears how worker died while unloading work platform
5 days ago

Severfield welding crisis hits five National Highways bridges

Full penetration butt welds under scrutiny as weight restrictions imposed
6 days ago

HS2 awards £3bn of track contracts

Ferrovial BAM and Colas Rail among 'rail systems' winners
1 week ago

Chinese diggers face 83.5% duty after JCB dumping complaint

Fair trade body finds UK kit prices were undercut by 23%
6 days ago

Contractor services