HS2 reveals images of giant Midlands dig

Grant Prior 4 years ago
Share

Drone footage has revealed the scale of HS2’s largest construction site in the Midlands.

The site in Warwickshire is being prepared for the launch of a tunnel boring machine (TBM) that will dig under Long Itchington Wood, creating a 1 mile twin bore tunnel before the route heads North and swings into Birmingham’s Curzon Street Station.

Main contractor on the job is the BBV Joint Venture of Balfour Beatty and Vinci who will be one of the biggest recruiters in the Midlands over the next two years, expecting to recruit 7,000 jobs to support the delivery of its HS2 programme of work.

There are currently 60 workers on site including student engineers and apprentices.

Current work on the 1km sq site entails a large and deep excavation, with 250,000m3 of material being excavated in layers before being transported and deposited locally to form environmental embankments for the main line.

The 2,000 tonne tunnel boring machine, which has been manufactured in Germany by Herrenknecht, is due for delivery on site in early 2021.

It will be launched in Summer 2021 and completion of the boring will be mid 2022. The tunnel will be around 9-10 metres in diameter.

On this stretch of the route there are two tunnels being built by BBV – the other one is Bromford Tunnel. There are also 100 bridges, 35 viaducts, 36 cuttings and 70 bridge structures.

Michael Dyke, Managing Director of Balfour Beatty VINCI said: “In readiness for the arrival of the first tunnel boring machine, works have already commenced in earnest to prepare the Long Itchington Wood Tunnel north portal site, with our expert team and valued supply chain partners excavating 250,000m3 of material before reusing it elsewhere across the route.

“Critical to the successful delivery of Europe’s largest infrastructure project – HS2, the 2,000 tonne tunnel boring machine will set off on its journey from the portal next Summer, travelling from North to South to create the twin bore Long Itchington Wood Tunnel.”

The TBM will take around 5 months to complete the first bore of the twin bore tunnel.

Once the first bore is complete, the TBM will be extracted at the South Portal reception box before being transported by road back to the North Portal to commence the second bore.

A large portion of the TBM support modules will be drawn back through the bored tunnel before being positioned on the cradle for the second bore.

Works on a Green Tunnel located south of the South Portal will commence later this year using the D-Wall rigs mobilised for the reception box.

Excavation of the reception box will be undertaken in this period with the material being stockpiled locally.

Specialists working on the site include Collins Earthworks who are undertaking bulk earthmoving. Collins, based in Derbyshire, has around 120 employees working on HS2 sites in the Midlands.

Other suppliers working on the site include:

  • SB3, a joint venture between Soletanche Bachy and Balfour Beatty Ground Engineering, are undertaking the soil nailing and shotcrete at the North Portal plus the D-walls, Secant piles and Slurry Walls at the South Portal.
  • Balfour Beatty Plant and Fleet HUB providing the solutions for temporary cabins and the permanent modular buildings.
  • Rail Stone Solutions are the providers of aggregates and stone fills across the project
  • Tarmac will be providing the concrete for the majority of the works.

Latest news

Keltbray fine increased to £18m after failed bid rigging appeal

Contractor loses penalty discount for settling with competition authorities
1 day ago

Luxury house builder goes under with 70 job losses

Octagon Developments in administration after 40 years in business
2 days ago

Top Ten best read stories of 2024

The biggest headlines of an eventful year. Have a good one and here's to a successful 2025
2 days ago

BAM Nuttall fined £800,000 after concrete skip tragedy

Young labourer killed by falling bale arm
3 days ago

Keltbray infrastructure business reveals new name

AUREOS means "new dawn" after private equity acquisition
2 days ago

Stiffer fines for over-running street works from next Summer

Cash raised from lane rentals to be channeled into pothole repairs
2 days ago

£113m Basildon rental homes scheme seals build finance

Work expected to start early next year on Market Square project
2 days ago

Notting Hill Genesis seeks more tier 1 repairs contractors

London housing trust seeks eight firms for new £1.5bn repairs framework
2 days ago

Reclaimed steel oil rig columns worked into London office revamp

Curo will use reclaimed bricks and steel for Fitzrovia office overhaul
2 days ago

CITB delays levy approval consultation

Levy agreement talks pushed back by ongoing review into effectiveness of training body
3 days ago

Ofwat approves £104bn water industry spending plan

Household water bills to rise by 36% to fund quadrupling of investment
3 days ago

Costain/ Siemens JV clinches HS2 power supply job

£300m deal for HV power supply systems over the 225km route
3 days ago

Demolition team assembles on Multiplex London Wall site

Erith to start work next month at Deutsche Bank's former headquarters
4 days ago

Norwich Council acts to revive £300m Anglia Square scheme

Council uses Homes England funding to buy stalled site with planning for 1,100 homes
3 days ago

Go-ahead for 4,500-home Cambridgeshire new town

Waterbeach new town plan stalled three years ago after an Environment Agency objection
3 days ago

Henry Boot to take total control of Stonebridge Homes

Deal worth at least £30m
3 days ago

HS2 costs could hit £66bn

Government looking for next estimate to be lower
4 days ago

Mace to close construction logistics arm

Specialist business being wound down
4 days ago

National Grid to invest £35bn over next five years

Plan set out for record investment in electricity transmission infrastructure
4 days ago

Profits double at Barhale

Civils specialist sees order book top £1bn
4 days ago

Balfour wins 68km HV underground power cable deal

Main works to start next year on Eastern Green Link 2 job
4 days ago

Stunning site wrap unveiled on Sloane Street

Hoarding creates illusion of fully formed façade on £53m Galliford Try job
4 days ago

Heathrow Airport upgrade spend takes off again

Airport operator will spend £2.3bn over the next two years
4 days ago

Government buys back over 36,000 military homes

Public ownership deal to release wave of upgrade and new build work
5 days ago

Story Contracting staff braced for rail job losses

Work coming through slower than expected from Network Rail
5 days ago

Ballymore submits two plans for 3,700 East London homes

Construction could start in 2025 on Thames Road and Knights Road schemes
5 days ago

Blackpool council steps in on failed developer’s £300m scheme

Blackpool Central site clearance to start in the New Year as hunt starts for new developer
5 days ago

Brookfield submits retro-first London office plan

Milton Gate plan for Square Mile will hike space by nearly 50%
5 days ago

Bowmer + Kirkland gets start date for £100m Siemens site

Construction to begin early next year on Chippenham scheme
5 days ago

Torsion sells under-construction Leeds BTR scheme

Concrete frame due to start soon on 300-apartment complex
5 days ago

Contractor services