Vinci UK holds margin at 2% through pandemic

Aaron Morby 4 years ago
Share

Vinci UK’s construction operations rose to the challenges of the pandemic last year managing to maintain group operating margin at around 2%.

Vinci is ramping up its use of digital technology across the building division
Vinci is ramping up its use of digital technology across the building division

Across the group, pre-tax profit remained stable at £16.9m (£17.7m) on revenue down by just 5% to £858m.

Giles Godard, chief executive of Vinci UK, said: “While the pandemic has impacted our clients in the retail, accommodation and catering industries very hard, we have also been in a position to help our clients in the health sector and in particular help the NHS fight the virus.”

The resilient performance saw Vinci maintain its available cash above £250m.

Godard added: “Bidding opportunities are strong and as a result of the formal awards of the HS2 N1 and N2 contracts main civils works our order book exceeds £2bn.”

Across the business, the Building division maintained stable profit despite a dip in revenue from delayed projects and contracts, while Taylor Woodrow managed to improve on its 2019 performance, raising margins to 1.7%.

Vinci trading by division
Pre-tax profit Revenue Margin
Building £8.8m (£8.8m) £381m (£429m) 2.3% (2%)
Taylor Woodrow £2.9m (£1.7m) £172m (£164m) 1.7% (1%)
Vinci Facilities £6.1m (£8.6m) £302m (£303m) 2% (2.8%)

 

At the end of the year, Vinci’s building arm had secured 82% of this year’s target turnover gaining preferred bidder status on over £750m of projects.

Workload is on track to return to 2019 levels, with the majority of its jobs secured in the north west and London and south regions.

The Taylor Woodrow civil engineering business also boasts a healthy forward order book with a forecast of £241m and £313m of revenue booked in for this year and 2022 respectively.

Godard said pipeline opportunities remained strong as far out as 2026 and were assessed at more than £1bn per annum.

HS2 is now Taylor Woodrow’s biggest client and for the next five years should account for 50% of civils work by value.

The procurement team is planning to submit bids for further HS2 work including a new depot at Washwood Heath, the people mover at Birmingham Interchange and the Phase 2a extension from Birmingham to Crewe where procurement is expected to start next year.

The business also plans to bid for Gatwick Airport main runway resurfacing and the redevelopment of Manston airport for commercial freight.

Latest news

Breyer Group files administration notice

Staff hope rival firm could buy assets and save jobs
10 hours ago

Peel Ports reveals winners for £750m framework

18 firms win places on deal: Full list
8 hours ago

Wates wins fit-out for Manchester First Street Hub

Smartspace arm secures another Government hub deal
8 hours ago

Big trade names dropped in M Group rebrand

Acquisitive group formed from Morrison Utility services in 2016
6 hours ago

Former Severfield director takes helm at Embrace Steel

New CEO Martin Kelly aims to step up expansion of steelwork contractor
11 hours ago

£302m upgrade funding awarded to FE colleges – list

Cash shared out between England’s 179 college groups
10 hours ago

FK Facades thrives but construction arm hit by ISG row

Dispute with failed contractor costs specialist £5.5m
11 hours ago

Galliford Try gets go-ahead for Milton Keynes PRS tower

33-storey tower needs gateway 2 approval before work can start
1 day ago

Small house builders get £150m funding for green homes

Developers will have to meet-up to ten new criteria to benefit from interest rate discounts
11 hours ago

Lendlease Construction renamed Bovis

US private equity firm completes £35m purchase of UK contracting business and rebrands
1 day ago

Breyer Group battles for survival as rivals circle

Housing maintenance firm fights three winding up petitions in a month
1 day ago

Careys facing £2.4m claim by developer over demolition cartel

Giant Hong Kong developer claims it was overcharged on Lots Road Power Station job
1 day ago

Multiplex profit drops a third as revenue rises to £780m

Spate of new orders sets contractor up for three years of work
1 day ago

Galliford Try and Breheny land latest Sizewell C road deals

More infrastructure deals for new nuclear power station
2 days ago

Worker trapped in collapsed septic tank pit

Contractor and director fined after worker suffers multiple fractures
1 day ago

Homes England buys stalled Broad Marsh site

Demolition to finally be completed as developer hunt begins
2 days ago

Vistry go-ahead for 353 homes at Rochester Riverside

Work to start on next phase of Kent town regeneration at end of this year
2 days ago

M&E firm J S Wright collapsed owing £19m

Trade creditors hit for £11.4m by employee-owned Midlands firm
2 days ago

Right to work checks to be extended to self-employed

Government plans crackdown on illegal working and rogue employers
2 days ago

Midlands developer turns to London with £1bn resi schemes trio

SevenCapital plans 1,000 flats in Kensington, Islington and the Isle of Dogs projects
2 days ago

Deck falls off huge scissor lift at Winvic site

Two men seriously injured as platform plunges to the ground
5 days ago

Weston targets Build to Rent with new division

Weston Partnerships signs first deals with asset managers and councils
2 days ago

Bouygues seals deal for £119m Cardiff college campus

Construction to start in June on two new buildings
5 days ago

£140m cash injection to speed-up flood defence schemes

Funding part of £2.65bn investment over the next two years
2 days ago

Bid race starts for £15bn schools framework refresh

DfE throws framework open to more contractors
5 days ago

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
6 days ago

London Mayor calls in blocked 600-bed student scheme

Refused 20-storey London PBSA block may still be built
5 days ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
6 days ago

Arrest after pedestrian death on construction site

Tragedy during site preparation works for new Wigan car park
5 days ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
6 days ago

Contractor services