As Highways England’s East Region Delivery Partner, the firm is seeking to get earthwork specialists on board for early contractor involvement to provide technical and commercial input into the detailed design phase and help formulate the budget and programme.
The first of the two projects is dualling of 3km of the A47 from Blofield to North Burlingham. This is due to start on site in late 2022 and will take around one and a half years to complete.
The other bigger dualling project will see 9km of new dual carriageway from Tuddenham to Easton.
This project is due to commence on site in early 2023 and will take around two years to complete.
It also involves building two new junctions and four new bridges.
Both dualling projects were recently submitted for Development Consent.
Earthworks Outline Scope of Works
A47 Tuddenham to Easton Dualling
Stage 1 ECI works will commence in September 2021.
- Quantities excavation of class 5a 224,000m3
- Excavation excluding class 5a 715,000m3
- Imported Fill 75,000m3
- Deposition of fill 702,000m3
A47 Blofield to North Burlingham Dualling
Stage 1 ECI works will commence in August 2021
- Excavation of class 5a 74,000m3
- Excavation excluding class 5a 109,000m3
- Imported Fill 205,000m3
- Deposition of fill 54,000m3
- Compaction of Fill 205,000m3
Notifications of Interest must be submitted by Friday 4 June 2021. Contact the project team by email.