HS2 minister admits concern over speed of cost rises

Aaron Morby 3 years ago
Share

HS2 Minister Andrew Stephenson has admitted he is concerned about the rate of cost rises on the £40bn phase one project.

HS2 Minister Andrew Stephenson is monitoring cost and programme progress
HS2 Minister Andrew Stephenson is monitoring cost and programme progress

His latest assessment of progress and spending comes as HS2 has spent just over a third of the target cost.

Since HS2’s watchdog MP last produced his six-month progress report for the Government actual and potential additional costs have jumped by a further £900m.

The hike comes from a £500m increase in contingency drawdown plus an extra £400m from potential further cost pressures.

“Whilst these pressures are manageable within the target cost given the remaining contingency, I am nonetheless concerned at the rate of their increase,” he admitted.

“I expect HS2 to maintain its focus on delivery to the target cost.”

So far a total of £1.3bn has been drawn down from the £5.6bn project contingency fund, leaving £4.3bn in reserve.

He revealed that the Government and HS2 were currently working to assess and mitigate the impact of ‘short-term’ global inflationary pressure on materials and labour supply on the programme.

Stephenson said £800m of the extra cost pressures arose from additional main works civils costs due to further design costs and slower than expected progress in some areas.

An extra £400m will be needed for the Euston station HS2 terminus. Although Stephenson said he hoped the move to a smaller, less complex 10-platform single-stage delivery strategy would reduce this identfied extra spend.

An extra £200m will be needed for changes to Network Rail infrastructure at Euston and Old Oak Common, while an extra £300m is needed for other parts of the overall programme.

HS2 has yet to formally cost in the impact of Covid 19 working restrictions. Its assessment of the likely financial impact of the pandemic remains between £400m and £700m.

Formal claims will be subject to government scrutiny and will require formal approval from the Treasury before funds from government-retained contingency can be allocated.

Over the next 6 months, HS2 will continue the ramp-up of construction work, launch the fourth TBM on the programme to start excavation of the London tunnels and we will see HS2 award a contract for the construction of the Interchange Station.

On Phase 2a, focus will be on progressing environmental and enabling work, early land acquisitions plus the procurement for the design delivery partner and progressing the procurement for the main works civils framework.

To date, out of the Phase One target cost of £40.3bn, £14.9bn has been spent, with an additional £0.8bn for land and property provisions. £12.7bn has been contracted and has not been spent, with the remaining amount not yet under contract.

 

Latest news

Pension fund charges hit profits at Wates

Bottom line also hit by closing out construction contracts
7 hours ago

Construction worker dies on Essex site

Fatal accident at housing job run by Rose Builders
5 hours ago

Renamed Bovis Construction suffered £16m loss last year

Firm slumped into red before being sold to US group Atlas Holdings
11 hours ago

Plans in for £1bn Liverpool Street Station scheme

21-storey offices above station main concourse to help fund upgrade
12 hours ago

Project director leaves giant McAlpine car battery site

Change in site team at flagship £4bn Agratas factory
12 hours ago

Nexus Infrastructure orders up 11% at half-year

Tamdown housing civils arm orders up despite housing recovery delay
11 hours ago

Five firms win £450m Scottish electricity network upgrade

Major investment by Energy company SSEN Distribution
1 day ago

Private equity firm buys trio of marine construction specialists

Move will create a new national marine infrastructure group
11 hours ago

Firm wanted for £35m Royal Observatory revamp

Upgrade includes new pavilion and energy saving measures
1 day ago

Wates wins £111m Victoria Tower restoration

Palace of Westminster's tallest tower overhaul will take six years
1 day ago

Cappagh Group founder passes away

Tom Ferncombe founded utility and infrastructure contractor in 1973
1 day ago

Mace tops contracts league with Euston Tower win

Contractor leads monthly work haul for second month running
1 day ago

Police hunt boss on the run after site manslaughter charge

Company director fails to turn up to court to face safety charges after site death
2 days ago

Glasgow civils firm buys building refurb specialist

M Squared buys EBS Construction in move to target £25m sales
1 day ago

Lynch plant hire fined £800,000 over abnormal load

Travelling excavator caught in police clampdown
1 day ago

Buyers flag fears over civil engineering slowdown

All sectors in reverse during "challenging" March
4 days ago

Police recover £100,000 of stolen plant at Harwich port

Polish man arrested on suspicion of handling stolen goods
1 day ago

Winners named for £380m Scottish council housing upkeep deal

PfH Scotland names 38 firms for social housing landlord deal
4 days ago

Torsion and Khalbros to build new Leeds £1bn neighbourhood

Eastgate Quarter site acquired from Hammerson
5 days ago

Kier wins first phase of £700m Warwick Uni campus build

Firm to start work on science and engineering precinct last this year
5 days ago

JCB to double size of US factory in wake of Trump tariffs

$500m Texas factory under construction to expand to 1m sq ft
5 days ago

Green light for £2.4bn Luton Airport expansion

Government go-ahead to transform airport
5 days ago

Mivan looks to boost supply chain network

Subcontractors and suppliers invited to meet the buyer event: Book places now
4 days ago

Diversification pays off for concrete frame specialist Statom

Strong results as £180m turnover firm expands into infrastructure sector
5 days ago

Cardo in talks to buy Breyer roofing arm

More than 100 jobs could be saved at Breyer Roofing
5 days ago

Quartet win £750m Wales & Western railway deal

Network Rail confirms partners for Reactive and Minor Works framework
5 days ago

Plans in for £350m London Bridge life sciences hub

Snowsfields Quarter will consist of three buildings containing labs
5 days ago

Surging labour costs push tender price forecast up

Pick-up in tender prices despite weak growth
5 days ago

Permasteelisa wins cladding deal on Multiplex city tower

Facade specialist wins work on Fenchurch Street ‘hanging gardens’ tower
5 days ago

Wates wins fit-out for Manchester First Street Hub

Smartspace arm secures another Government hub deal
6 days ago

Contractor services