Tory leadership battle delays bidding for HS2 phase 2a

Aaron Morby 2 years ago
Share

The hiatus in decision-taking caused by the Tory leadership race has delayed procurement of the main works civils framework for phase 2a of HS2 .

Main civil works packages on West Midlands to Crewe route will be worth over £1.6bn
Main civil works packages on West Midlands to Crewe route will be worth over £1.6bn

Prequalification for main civil engineering works on the 5.2bn to £7.2bn West Midlands to Crewe stretch of the scheme originally was expected to start in July.

Prospective bidders have now been told that “as a result of the ongoing leadership changes in government, the approvals we need to issue the PQQ have been delayed”.

Procurement chiefs are now hoping to get sign-off to proceed with the long-awaited bid contest before the end of September but said they would confirm a new date when there is more certainty about the timing.

Previously HS2 intended to split section 2a into two major civils worth together over £1.6bn.

But latest thinking suggests the 58km section will now be split up into seven civils packages.

In the meantime, HS2 is planning to update firms on the latest commercial model that will be used later this month to keep the process on track.

Main civil engineering works for Phase 2a of the project will include two bored tunnels totalling 2.5km, 17 viaducts of 6.2km, 61 bridges, 19million m3 of embankments, 20million m3 of cuttings

This month HS2 was also due to announce the £500m Design and Delivery Partner for the projects.

Shortlisted bidders are: 2 Connect JV (AECOM /Costain Integrated Services);  AMS JV (Atkins /Mace Consult / SYSTRA; and Jacobs UK.

Bam Nuttal, Galliford Try, Laing O’Rourke and Skanska are also waiting to hear this month on the outcome of their race for a £240m two-part enabling works contract.

This second stage enabling works deal follows on from Kier’s earlier £50m first stage highways and utility enabling works award.

The three-year deal splits work along the route into two separate packages with one contractor delivering the works on the northern sections and a separate contractor delivering works for the southern sections.

Advanced civil works are due to begin this Autumn.

Latest news

Winners revealed for £5.4bn electricity grid upgrade

SP Energy Networks unveils 19 winners - full list
19 hours ago

Malaysian property giant to buy 50% stake in JRL

IJM Land to buy into diversified £800m turnover south east contractor
1 day ago

Fast-track skills hubs to train 5,000 extra apprentices

Plan for network of 32 skills hubs to rain construction apprentices in half the time
18 hours ago

Luxury house builder files administration notice

£31m turnover Octagon Developments Ltd lodges court notice
1 day ago

Morgan Sindall takes on £22m stalled ISG Cardiff school job

Workplan is being drawn up ahead of restart on Penarth school
1 day ago

Walker Modular wins bathroom pod deal on student tower

Sealant-free construction method helps supplier dominate student market
1 day ago

Over £600m awarded for decarbonisation projects – full lists

Over 240 public building energy upgrade projects secure cash
2 days ago

Enabling works to start on £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
2 days ago

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
2 days ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
2 days ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
2 days ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
2 days ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
2 days ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
2 days ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
3 days ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
3 days ago

House builder Camstead goes into administration

Work stopped on three current sites
4 days ago

Death of piling legend Roger Bullivant

Industry innovator dies after long illness aged 85
3 days ago

ESS Modular went down owing suppliers £7m

Modular specialist owned by ISG owner Cathexis
3 days ago

Builders back farmers in inheritance tax protest

"A rethink is desperately needed" say National Federation of Builders
3 days ago

Willmott Dixon wins £36m leisure centre upgrade

Work to start on historic Westminster 1930s Grade II listed Seymour Centre
3 days ago

Graham wins £100m Cardiff Crossrail phase 1

Work on route to Cardiff Bay to start before end of next year
4 days ago

Laing O’Rourke appoints new European MD

Peter Lyons to take-up new role in February
5 days ago

Profits dip at Stepnell ahead of demerger

Turnover and secured workloads up ahead of restructure
5 days ago

HS2 green bridge deck takes shape

100m-wide wildlife bridge to carry hedgerows and country lane over HS2
4 days ago

1,000-home Wolverhampton city centre scheme in for planning

ECF and council advance City Centre West build to rent scheme
5 days ago

Sisk clinches £54m North London council HQ revamp

Haringey's iconic Grade II listed civic centre to be brought back into use
5 days ago

Ofgem approves £2.5bn Eastern Green Link 1

Work to start next Spring on cable project from Scotland to the north of England
5 days ago

Anglian Water hunts for £1bn delivery partner

Programme delivery partner wil integrate with client team over 15-year plan
5 days ago

Hadden collapse costs supply chain £6.7m

"Highly unlikely" subcontractors will receive anything for their unpaid invoices
5 days ago

Contractor services