In one incident an overhead cable the Kier workers brought down hit a lorry. The second time a cable landed on the motorway.
An HSE investigation found after one incident Kier workers failed to immediately tell the network provider Scottish Power what they had done.
A civil engineering firm has been fined more than £4m after its staff twice struck overhead powerlines while working on the M6 motorway.https://t.co/L4thXoKaN5
Footage of the first incident below. pic.twitter.com/b99N8vL15m
— Health and Safety Executive (@H_S_E) January 13, 2023
Both incidents happened on overnight road works as part of the smart motorway scheme between junctions 16 and 18 near Sandbach in Cheshire.
During the first incident, a team of three from Kier were working a night shift on 28 March 2018. The workers were clearing tarmac from the hard shoulder and loading a truck with a digger.
As they moved the truck along with an attached loading bucket raised it struck and severed a 11kV overhead powerline that landed in the motorway and in a nearby field.
The company failed to immediately tell Scottish Power, which meant the cable was reenergised a number of times while it was lying on the motorway and vehicles were passing.
During the second incident, another team from Kier were taking down a motorway barrier on 21 January 2019. Their crane struck an overhead cable which led to an unmarked 11kV powerline being hit and snapped by an oncoming lorry.
HSE found that inadequate planning from Kier meant the vehicle used in the first incident was unsuitable despite other more suitable vehicles being available. There was also no task-specific risk assessment available for the workers.
In the second incident the workers were unaware of the overhead hazards.
Kier Infrastructure and Overseas Limited pleaded guilty to safety breaches and were fined £4.415m and ordered to pay costs of £80,759.60 at Manchester Crown Court yesterday.
HSE inspector Mike Lisle said: “This is a significant fine reflecting the seriousness of the failures here. The company’s failure to plan the work properly and provide an adequate risk assessment put its workers and those using the motorway in significant danger.”