HS2 Euston needs full design reset as costs set to double

Aaron Morby 2 years ago
Share

The public spending watchdog has called for an urgent total design rethink of the Euston terminus of HS2 as costs soar.

National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.
National Audit Offcie calls for full project review to develop a design that is deliverable and value for money.

A new National Audit Office report into the station warns that forecast project costs have continued to balloon despite attempts to simplify the project.

The original £2.6bn station budget is now reckoned to have soared to £4.8bn, even with the cost-cutting decision to trim back platforms from 11 to 10.

Spending to date on advanced works has already hit £548m.

NAO experts warn that the Government’s latest two-year pause in new construction can only inflate long-term costs further.

This is due to costs associated with demobilising and then remobilising teams, contractual changes, and managing the project for longer.

It has called on the Government to use the two-year pause to go back to the drawing board and develop a design that is affordable, deliverable and value for money.

The NAO’s report recommends the DfT works with stakeholders: Euston Partnership, HS2 Ltd, Network Rail, Lendlease and local partners to reassess the expectations for the HS2 Euston project, its budget, and the public benefits.

Gareth Davies, the head of the NAO said: “Government is once again having to revise plans for Euston HS2.

“Clearly, the 2020 reset of the station design has not succeeded.

“DfT and HS2 Ltd have not been able to develop an affordable scope that is integrated with other activity at Euston, despite their focus on costs and governance since 2020. Recent high inflation has added to the challenge.

“The March 2023 announcement by the Transport Secretary pausing new construction work should now give DfT and HS2 Ltd the necessary time to put the HS2 Euston project on a more realistic and stable footing.

“However, the deferral of spending to manage inflationary pressures will lead to additional costs and potentially a more expensive project overall, and that will need to be managed closely.”

Meg Hillier MP, Chair of the Committee of Public Accounts. added: “Attempts to reset the High Speed 2 Euston Station have failed.

“It is still unaffordable and no further forward than it was three years ago.

“Today’s NAO report shows that the redesigned station would have cost nearly double what was budgeted.

“Department for Transport and High Speed Two Ltd have wasted enough time and money. They must get Euston right next time or risk squandering what benefits remain.”

Euston Station cost reality check


  • In January 2020, the NAO reported that the work at Euston was more complex than originally anticipated and that there was uncertainty over the HS2 station design.
  • The following month the Oakervee Review 2 raised concerns about the design of the HS2 Euston station and concluded that the existing design was unsatisfactory.
  • In April 2020, HS2 Ltd set the station budget at £2.6bn, but by June 2020 it estimated that it could cost as much as £4.4bn.
  • In November 2020, the DfT instructed HS2 Ltd to pause construction on the 11-platform design to begin work on a new 10-platform plan.
  • These new plans are now £0.4bn more expensive than the previous 11-platform design.
  • In Autumn 2021 the Department also directed HS2 Ltd to integrate more closely with Network Rail’s redevelopment of the existing rail station and confirmed the extent of the surrounding commercial and residential developments.
  • Much of the previous design work was then scrapped, at a cost of £106m to the taxpayer, despite DfT’s efforts to minimise this.
  • To help with this integration, and in response to the Oakervee recommendations, in December 2021 the DfT formally established the Euston Partnership to bring together the different bodies involved with projects on the Euston site, including delivery of HS2 Euston station.
  • Following the Transport Secretary’s announcement to delay works in March 2023, the DfT will now need to consider how best to control the budget.
  • By the end of December 2022 HS2 Ltd had spent more than £2bn on the HS2 Euston station and its approaches, including design, land, and preparatory works.
  • The land purchases and preparatory works cost £1.5bn and were funded from the wider HS2 budget.

Latest news

Demolition giant John F Hunt Group sold to staff

Chairman John Hall to remain at helm
17 hours ago

University of Warwick advances £700m campus plan

Enabling works to get underway for main build works next year
23 hours ago

Go-ahead for £750m East London data centre

Urban 11-storey data centre to be built next to River Lea and A13 in Newham
2 days ago

Keltbray Infrastructure Services buys Linbrooke rail arm

First deal since infrastructure business was bought by private equity this summer
2 days ago

Elizabeth Line wins Stirling Prize for architecture

Infrastructure scheme wins premier design prize
22 hours ago

Winners named for Worcestershire and West Mids framework

Deal covers development work from design to construction
22 hours ago

Piling starts on HS2 Curzon Street Station

Mace Dragados Joint Venture and Keltbray working on Birmingham site
22 hours ago

M Group joins top seven as revenue jumps to £2.2bn

Infrastructure services specialist continues to hunt acquisitions
2 days ago

BlackRock to take control of Lanes Group

Takeover of leading water contractor to complete this month
2 days ago

Yorkshire and Lincolnshire builders’ merchant goes under

1928-founded Builders Merchant Company hit by winding up petition
2 days ago

Trio wins £170m West Country new build housing deal

Curo Enterprise, E.G. Carter and Speller Metcalfe Malvern
2 days ago

Roofer dies in fall from potato box on forklift

Court hears how victim fell 16ft from makeshift platform
2 days ago

Clancy bolsters senior management team

Skanska project director Jon Arnold joins as operations director of energy
2 days ago

High tech construction plant could save country £417bn

Costain report says kit which connects and drives itself will provide a massive economic boost
3 days ago

Concrete frame defects cost Bellway another £14m

Cost of repairing Greenwich scheme rises while £5.4m was spent on aborted Crest Nicholson chase
3 days ago

Green light for 52-storey Isle of Dogs resi tower

460 flats One East Point project will be built at 3-4 Harbour Exchange
3 days ago

Contractors urged to “hire now” as labour supply crunch looms

Vacancies rise and wages grow as fight for new workers intensifies
3 days ago

Kier confirmed for £20m Yasa Motors Bicester HQ

Developer Bicester Motion advances future mobility business park
4 days ago

Data centres and airport expansion to spur growth

Government hails £25bn data centre and £1.1bn Stansted Airport expansion plan
4 days ago

Hinkley Point second reactor unit build up to 30% faster

Engineering team lifts last giant steel ring onto reactor 2 yesterday
3 days ago

BAM reassures supply chain after winding-up petition

Firm's credit rating temporarily affected after dispute with supplier
4 days ago

Winvic secures Leeds build to rent scheme

Phase one of £500m Sweet Street South Bank regeneration starts
4 days ago

£60m turnover construction group sold to staff

Meldrum Construction Services Group becomes Employee Owned Trust
4 days ago

Starmer vows to “rip out” obstacles to investment

Prime Minister to make pledge at inaugural International Investment Summit
4 days ago

VolkerFitzpatrick starts prep-work for £210m M3 junction upgrade

Main works to begin in early 2025 on Winchester junction job
4 days ago

London super sewer turned on after eight years of construction

£4.5bn project starts protecting River Thames from pollution
4 days ago

Housing and office new work jump fuels output recovery

August new construction work rebounds 1.6% after early summer fall
7 days ago

£300m London City fringe office tower approved

Rocket's 27-storey One Fairchild Street job set for take-off
1 week ago

Consultants named for London Tube Bakerloo Line extension

Aecom and architect WW+P to work up designs for four new stations
7 days ago

15 giant bridge beams lifted into place at HS2 station

Balfour Beatty VINCI carries-out civils work for Solihull station: Video
1 week ago

Contractor services