Unfit planning system means 4,700-year wait for onshore wind

Aaron Morby 2 years ago
Share

The current planning system will fail to deliver the Government’s ambitions to build infrastructure to meet net zero goals and housing needs.

That is the conclusion of a damning report by the Institute for Public Policy Research, which is calling for a complete reset of planning.

It warns that it would take 4,700 years for England to reach the onshore wind capacity called for by government advisers, at the current rate of development.

Progress in England was stalled in 2015 when planning laws were changed to make it more difficult to gain permission for new onshore wind turbines – in what was effectively a ban. 

Since then only 17 onshore wind farms have been approved, generating just 6.7 megawatts of power – equivalent to just 0.02% of the on-shore total needed in England based on National Grid estimates.

The IPPR report calls for restrictions on onshore wind and solar power to be reduced and for local authorities to be compelled to identify land suitable for onshore wind and solar generation. 

It also calls for big planning reforms to get many more houses built, while also moving faster to meet net zero targets.

In particular, the report calls for decisions on new home building to be linked into plans for low-carbon transport networks.

Between them, housing and transport account for over 40% of total emissions, but since 1990 emissions from both sectors have barely declined. 

The report also sheds fresh light on the critical failures of the current system. These include the lack of clear rules for developers and local authorities on when planning permission should be granted, leading to uncertainty and speculative buying of land. 

It argues that local authorities should be compelled to draw up detailed plans for development in their areas that integrate environmental targets, to provide greater certainty.

It proposes that if a planned house building project meets new net zero targets alongside other local requirements, it should be given an automatic green light, removing much of councils’ discretion from the system. 

It calls for national and local house building targets to be reinstated so that councils can be compelled to enable more homes to be built. 

But the report calls for the public to be given a more meaningful say over the future of their local areas than they do at present. 

Luke Murphy, IPPR associate director for energy, climate, housing, and infrastructure, said: “The current planning system in England is not remotely fit for purpose to build a net zero world, restore nature, or meet housing need.

“Fundamental planning reform is needed to accelerate efforts to reduce emissions and restore nature, rollout renewable energy generation, and to deliver the level of housebuilding that the country so desperately needs.”

 

Latest news

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
15 hours ago

New boss at Eric Wright Civil Engineering

Gavin Hulme takes top job as Diane Bourne moves to group role
8 minutes ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
16 hours ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
16 hours ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
15 hours ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
2 days ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
1 day ago

Permasteelisa wins cladding deal on Bovis city tower

Facade specialist lands package at 60 Gracechurch Street
15 hours ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
1 day ago

Major Building Safety Regulator shake-up to end tower delays

HSE stripped of control and top fire chiefs brought in to fast-track stalled schemes
2 days ago

Hinkley trio sign Sizewell civils deal

Balfour,Bouygues and Laing O'Rourke form Civil Works Alliance for new power station
2 days ago

£3.9bn data centre plan for Ravenscraig steelworks

Green energy to power massive new steel to silicon AI campus
2 days ago

Breakthrough on HS2’s second longest tunnel

8.4 mile Northolt to Old Oak Common drive completes
2 days ago

Neilcott on fast-track to debt-free employee ownership

£22.5m loan nearly paid down after big profit year
2 days ago

TfL kicks off race for £700m Tube station upgrade

South Kensington and Elephant & Castle top the pipeline list
2 days ago

Corbyn Plant Hire fleet goes under the hammer

Kit to be sold off by sister firm to collapsed groundworks contractor
2 days ago

Government wields procurement stick on late payment

New rules would block slow payers from bidding on big public jobs
5 days ago

Hercules buys power line labour firm for £15.7m

Labour supply specialist snaps up Advantage NRG to tap booming electricity upgrade market
5 days ago

Universal bid to fast-track planning for theme park

Entertainment giant eyes 2026 start at Bedford site
5 days ago

Developer Breck to transform former Ibstock brick factory

Ravenhead works to become 300-home development
5 days ago

SP Energy Networks awards contracts worth £1.4bn

First round of awards under £5.4bn national electricity grid upgrade programme
6 days ago

Travelodge to convert Liverpool Street office building

Office-to-hotel conversion in City of London
5 days ago

Plans lodged for 1m sq ft City of London office

Barbican landmark building will reuse 40% of existing structure
5 days ago

PTSG acquires roofing specialist HD Sharman Group

Premier Technical Services Group expands building maintenance division
5 days ago

Balfour Beatty lands £833m carbon capture power plant job

Work to start later this year on Teesside carbon capture gas-fired power station
6 days ago

Svella agrees deal to save Cubby Construction

Solvent purchase set to save 214 jobs and protect supply chain
6 days ago

J Coffey holds line on margins despite £52m revenue slide

Pre-tax profit down 14% but firm eyes strong pipeline to bounce back
6 days ago

Consultants called up for £2.3bn NHS SBS panel reboot

Market asked for views ahead of next-gen procurement rollout
6 days ago

Hochtief launches new UK data centre division

German business model to be introduced for UK construction
7 days ago

Construction skills body launches with 100,000 worker target

Industry to work closer with Jobcentres to find new talent
6 days ago